MS Project Flashcards Preview

INST335 > MS Project > Flashcards

Flashcards in MS Project Deck (12):
1

Series of tasks that don't need to be completed on time for a project to finish on schedule

Non critical path

2

A tasks______is the latest date that a task can commence without delaying the project finish date

Late start

3

A task that comes before a specific task on a project schedule

predecessor

4

The amount of time a task can slip before it has an effect on other tasks or the project finish date

slack

5

the date at which assigned work is schedule to commence

assignment date

6

a tasks____ is the latest date that a task can be completed without delaying the project finish date

late finish

7

The earliest date provided in a project plan, this date determines when work or task can commence

project start date

8

A task that must be completed as schedule for the project to finish on schedule

critical task

9

the schedule ending date

finish

10

the latest due to complete all tasks in a project plan

project finish date

11

a project activity that has a beginning and an end

task

12

the total time require to complete a task

duration