MSTE Flashcards

(105 cards)

1
Q

Standard shape of stop sign

A

octagon

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Standard shape for GIVE WAY sign

A

equilateral triangle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Color of no loading/unloading zone markings

A

red

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Device mounted on a fixed support
(permanent signs) or portable support
(temporary signs) whereby a specific message
is conveyed by means of words or symbols
placed or erected for the purpose of
regulating, warning or guiding traffic.

A

Traffic Signs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Signs which inform and advise road users
of directions, distances, routes and the
location of services for road users and point
of interest.

A

Guide Signs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Signs used to guide drivers through a
change in horizontal alignment of the road.

A

Chevron Signs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The design element which is the most
affected by the volume of traffic.

A

Number of Traffic Lanes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The primary consideration in the design
of geometric cross sections for highways,
runways and taxiways is _______.

A

Drainage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Reaction times vary widely. As a result,
the usual practice is to use a single, rather
conservative value. AASHTO suggests a value
of ____ in its Policy on Geometric Design of
Highways and Streets.

A

2.5 sec

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

It provides the detailed requirements
for the materials, equipment and workmanship
to be incorporated into the project.

A

Specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

This refers to drawing, usually
accompanied by notes, of various aspects or
components of the design.

A

Plans

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

It include cost estimates for various
parts of the project and are used to evaluate
the acceptability of bids and the financial
feasibility of the project.

A

Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

It is the process where a load is
prepared for lifting using a lifting
machine. The main part of this process is
the tying up of the load with sling and other
connecting devices so that the load could be
hooked onto a crane.

A

Rigging

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Complete or partial dismantling of a
building or structure by pre
-planned and
controlled methods or procedures.

A

Demolition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

It is capable of spreading,
consolidating, and finishing a concrete slab
without the use of conventional forms.

A

Slipform Paver

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

It is a very versatile machine that has
the longest reach for digging and dumping of
any member of the crane shovel family
.

A

Dragline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

The bucket volume contained within the
bucket when following the outline of the
bucket sides is called:

A

Plate line capacity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Assumes a level of material flush with
the lowest edge of the bucket.

A

Waterline Capacity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

The bucket capacity when the load is
struck off flush with the bucket sides.

A

Struck Capacity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

It represents those components of cycle
time other than travel time.

A

Fixed Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

This represents the travel time required
for a unit to haul material to the unloading
site and return

A

Variable Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Construction workers who are working
from unguarded surfaced _________ or more
above grade, temporary or permanent floor
platform, scaffold or where they are exposed
to the possibility of falls hazardous to life
or limb, must be provided with safety
harnesses and lifelines.

A

6 meters

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Every construction project shall have a
suitable _________________, which must be in
accordance with these rules, and other
orders and issuances issued by the
Department of Labor and Employment.

A

Construction Safety and Health Program

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

This refers to a method of protecting
employees from cave-ins, from material that
could fall or roll from an excavation face
or into an excavation, and from the collapse
of adjacent structures.

A

Protective System

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
This refers to structures such as underpinning, bracing, and shoring that provide support to an adjacent structure or underground installation or to the sides of an excavation or trench.
Support System
26
It is the movement of plastic concrete into its final position (usually within forms).
Placing
27
In general, ________ may be done when the water sheen has disappeared and the concrete will support the weight of the finisher.
Floating
28
This is done on slabs that are to be left exposed or to receive thin finishes, such as resilient flooring, carpet, tile, or paint.
Troweling
29
It is defined as the fraction of time that vehicles are present at a point in space.
Occupancy
30
It is the maximum number of vehicles, passengers, or the like, which can be accommodated by a given facility or system under given conditions at a given level of service.
Service Volume
31
The points at which the cut or fill slopes intersect the existing ground are referred to as _______.
Catch Points
32
A comprehensive list of parts, items, assemblies, subassemblies, intermediate assemblies, documents, drawings, and other materials required to create a product.
Bill of Materials
33
A list of materials and services required to perform a project. The list includes materials, labor, and quantities of each.
Bill of Quantities
34
The amount by which the outer edge of a curve or a railroad is banked above the inner edge to help offset the centripetal force developed as the vehicle goes around a curve.
Superelevation
35
Cracks approximately at right angles to the pavement centerline. These may be caused by shrinkage or differential thermal stress of the asphalt concrete or maybe reflective cracks.
Transverse Cracking
36
Cracks approximately parallel to the pavement centerline. These are caused by poorly constructed construction joints and shrinkage of asphalt concrete surface.
Longitudinal Cracking
37
Wearing way of the pavement surface caused by dislodging of aggregated particles and binder. This is usually a result of insufficient asphalt binder in the mix or stripping of asphalt from particles of aggregate.
Raveling
38
Progressive disintegration of the surface between the wheel paths caused by dripping of gasoline or oil from vehicles.
Drip Track Raveling
39
The extruding of bitumen onto the pavement surface, causing a reduction in skid resistance. It is generally caused by excessive amounts of asphalt in the mix or low air voids content. It occurs when asphalt fills the voids in the mix during hot weather and then exudes out onto the surface of the pavement.
Bleeding or Flushing
40
Elevation differences between adjacent slabs at transverse joints. It is usually the result of pumping and is a major source of Portland Concrete pavement structure.
Faulting
41
Localized upward buckling and shattering of the slabs at transverse joint or cracks. They can occur when transverse joints are filled with incompressible solid materials.
Blowups
42
A series of interconnected or interlaced cracks caused by fatigue failure of the asphalt concrete surface under repeated traffic loading.
Alligator Cracking
43
Cracks forming large interconnected polygons, usually with sharp corners or angle. These cracks are generally caused by hardening and shrinkage of the asphalt and or reflection cracking from underlying layers such as cement-treated base.
Block Cracking
44
A method of protecting workers from cave-ins by excavating the sides of an excavation to form one or a series of horizontal levels or steps, usually with vertical or near vertical surfaces between levels.
Benching
45
Protects workers by using trench boxes or other types of supports to prevent soil cave-ins.
Shielding
46
This requires installing aluminum hydraulic or other types of supports to prevent soil movement and cave-ins.
Shoring
47
It is defined as the maximum safe speed that can be maintained over a specified section of a highway when conditions are so favorable that the design features of the highway govern.
Design Speed
48
The basic lane width appropriate for national road is _______.
3.35 m
49
It is advisable for a site plan to contain a large-scale map of the overall area and to indicate where the project is located on the site.
Vicinity Map
50
This drawing has elevation as its vertical axis and horizontal distance as measured along the centerline of the facility as its horizontal axis.
Profile
51
This applies to curved facilities, suc as highways or railways only. It consists of a graph with a roadway or railway cross slope versus horizontal distance.
Superelevation Diagram
52
This view has elevation as its vertical axis and horizontal distance, measured perpendicular to the centerline, as its horizontal axis.
Geometric Cross Section
53
It is a violation of an accepted safe procedure which could permit the occurrence of an accident.
Unsafe Act
54
A hazardous physical condition or circumstance which could directly permit the occurrence of an accident.
Unsafe Condition
55
Rule is the guidelines regarding Personal Protective Equipment (PPE).
Rule 1080
56
How do you test the relative consistency of concrete?
Slump-test
57
Most important process to prepare concrete:
Batching
58
The number of days final curing for a concrete cement pavement is done for:
14 days
59
Joints placed in concrete pavements, which are usually placed transversely, at regular intervals, to provide adequate expansion space for the slab to expand when the pavement is subjected to an increase in temperature.
Expansion Joint
60
Joints placed in concrete pavements, which are usually placed transversely regular intervals across the width of the pavement to release some of the tensile stresses that are due to a decrease in temperature.
Contraction Joint
61
Joints placed in concrete pavements, which are usually placed transversely across the pavement width to provide suitable transition between concrete placed at different times or on different days.
Construction Joint
62
Joints placed in concrete pavements at right angles to the center line of the pavement is called:
Transverse Joint
63
It is a type of thermoplastic lane marking designed to aid and provide motorist with visual, audio, and warning on the road.
Rumble Strips
64
Generally, the dry materials used in making quality concrete are heavier than water. Thus, shortly after placement, they have a tendency to settle to the bottom and displace the mixing water to the surface, which is called _____.
Bleeding
65
The surface of newly placed concrete is struck off by moving a straightedge back and forth with a saw-like motion across the top of the forms.
Screeding
66
The bringing of a concrete surface to true grade with enough mortar to produce the desired finish.
Leveling
67
Immediately following or during edging, pre-molded inserts are placed in concrete slabs to control cracking in the concrete as a result of shrinkage.
Jointing
68
When inside the building, one may notice unusual sounds and change in the building. What causes these events?
Temperature
69
Any temporary elevated platform used for supporting employees or materials or both in the course of any construction works.
Scaffold
70
What are the capacity requirement for all scaffoldings?
4 times its own weight
71
It is the timing of signals in relationship to one another so that vehicles travelling at a predetermined speed can pass through the greens of successive signals.
Signal Coordination
72
The speed at which vehicles are presumed to travel through coordinated signal system is known as:
Speed of Progression
73
The time difference between the beginning and end of through band at any point is known as:
Band
74
The red, yellow, or green light that is displayed to driven in a given movement is called an:
Indication
75
The time required for one complete sequence of signal indication is called ____.
Cycle
76
The simplest rail capacity problem is that involving rail rapid transit systems. These usually have the following characteristics: I. One-way operation II. A common speed profile for all trains. That is, each train traverses each section of track at the same speed as all other trains; consequently, trains do not overtake or pass one another. III. Common station dwell times. That is, each train spends the same amount of time stopped at each station as all other trains; dwell times may vary from station to station IV. A fixed minimum front-to-back time gap between trains. A. I-III B.II and IV only C. III only D. All of the above
All of the Above
77
There are three basic ways of resolving crossing conflicts. I. Time sharing solutions II. Space sharing solutions III. Grade separation solutions IV. Crossing conflict solutions A. I-III only B. II and III only C. II only D. All of the above
I-III Only
78
It is the difference between the actual travel time and a given segment of a transportation system and some ideal travel time for that segment.
Delay
79
The time spent in decelerating and accelerating the vehicle in opening and closing doors.
Clearance Time
80
Headways such that the vehicles are just filled at the maximum load point on the route.
Capacity Headway
81
________ is the process of increasing the density of a soil by mechanically forcing the soil particles closer together, thereby expelling air from the void spaces in the soil.
Compaction
82
________ is an increase in soil density of a cohesive soil resulting from the expulsion of water from the soil’s void spaces.
Consolidation
83
Compactor production is based on the following data: I. Number of paces required II. Width compacted per pass III. Compactor speed IV. Compacted lift thickness V. Job Efficiency A. I, III, IV and V B. I, II, IV, and V C. all of the above D. II, III, IV and V
All of the above
84
The process of giving natural soils enough abrasive resistance and shear strength to accommodate traffic or design loads is called.
Ground Modification
85
It involves dropping a heavy weight from a crane onto the ground surface to achieve soil densification.
Dynamic Modification
86
________ or placing additional weight on the soil surface, has long been used to densify cohesive soils.
Surcharging
87
________ is the process of densifying cohesionless soils by inserting a vibratory probe into the soil.
Vibroflotation
88
Workers in an excavation be protected from cave-ins by one of the following methods: I. Sloping or benching of the sides of the excavation. II. Supporting the sides of the excavation by shoring. III. Placing a shield between workers and the sides of the excavation. IV. Drying soil to prevent collapsing. A. all of the above B. I, II, and IV C. I, II, and III D. II, III, and IV
I, II, and III
89
In highway construction, the process of cutting down high spots and filling in low spots of each roadway layer is called.
Balancing
90
Estimates expected activity times in a PERT network. I. Make use of three estimates II. Puts the greatest weight on the most likely time estimate III. Is motivated by the beta distribution A. III only B. I only C. II only D. All of the above
All of the Above
91
Of all paths through the network, the critical path:
has the maximum expected time
92
The calculation of the probability that the critical path will be completed by time T I. Assumes that activity times are statistically independent. II. Assumes that total time of the critical path has approximately a beta distribution III. Requires knowledge of the standard deviation for all activities in the network A. II only B. I only C. II only D. All of the above
I only
93
The CPM time-cost trade off function
cost decreases linearly as time increases
94
The marginal cost of crashing a network could change when A. The activity being crashed reaches its crash time B. The activity being crashed reaches a point where another path is also critical C. Both A and B D. None of the above.
Both A and B
95
Fundamental ideas in the LP network models are activity time equals normal time + crash time I. Earliest start time for an activity leaving a node equals the Max of the earliest finish times for activities leaving that node II. Earliest finish time equals latest finish time minus activity time. A. I only B. II only C. I and II D. None of the above
None of the Above
96
The PERT/COST model assumes that I. Each activity achieves its optimistic time II. The costs are uniformly distributed over the life of the activity III. Activity times are statistically independent. A. I only B. II only C. III only D. None of the above
II only
97
The PERT/Cost control report I. Requires a budget for each activity II. Requires a report on the percentage of completion of each activity III. Calculate overruns A. I only B. II only C. III only D. All of the above
All of the above
98
The process of bringing each roadway layer to its final grade
Trimming
99
It is the breaking away of hardened concrete surface of a slab to a depth of about 1.6 to 4.8 mm. It is usually occurs at an early age of slab.
Scaling
100
It is the occurrence of numerous fine hair cracks in the surface of a newly hardened slab to surface shrinkage.
Crazing
101
Appearance of powdery material on the surface of newly hardened concrete slab.
Dusting
102
Bringing of a concrete surface to true grade with enough mortar to produce the desired finish.
Leveling
103
The surface of newly placed concrete is struck off by moving a straightedge back and forth with a sawlike motion across the top of the forms and screeds.
Screeding
104
Is done on slabs that are to be left exposed or to receive thin finishes, such as resilient flooring, carpet, tile or paint
Troweling
105
Arrange the following in chronological order: I. Broom Finishing II. Screeding III. Bleeding IV. Leveling V. Jointing VI. Edging VII. Floating VIII. Troweling A. I,II,III,IV,V,VI,VII,VIII B. III,II,IV,VI,V,VII,VIII,I C. VIII, VII,VI,V,IV,III,II,I D. II,IV,V,VIII,I,III,VI,VII
B