Multiple Choice Flashcards
(215 cards)
In August, General Motors produced 8200 customized vans at its plant in Oshawa. The labour productivity at this plant is known to have been 0.50 vans per labour-hour during that month. Three-hundred labourers were employed at the plant that month.
How many hours did the average labourer work that month? (Round to the nearest whole number).
55
A strategy is a(n)
action plan to achieve the mission
True of false: Functional strategies are shaped by corporate strategy.
True
The ability of an organization to produce goods or services that have some uniqueness in their characteristics is
competing on differentiation
Which of the following is an example of competing on quick response?
A firm’s products are introduced into the market faster than its competitors’ products.
Response-based competitive advantage can be
Flexible, realiable, and quick response (all of the above)
An operations manager is not likely to be involved in
the identification of customers’ wants and needs
True or false : The number of people employed in manufacturing has increased since 1950
False - Each manufacturing employee now produces about 20 times more than in 1950
The Ten Critical Decisions of Operations Management include
Layout strategies, maintenance, process and capacity design, managing quality (all of the above)
Which of the following is not one of The Ten Critical Decisions of Operations Management?
mass customization
True or False : All organizations, including service firms such as banks and hospitals, have a production function.
True
A foundry produces circular utility access hatches (manhole covers). Currently, 120 covers are produced in a 10-hour shift. If labor productivity can be increased by 25%, it would then be
15 covers/hr
Suppose that a 9-person team (each working 10 hours per day) produces a total of 500 engines each day. If production is increased to 705 engines each day, how many labour hours can be added without losing any productivity (round it to the nearest whole number)?
37
Suppose that a 7-person team (each working 9 hours per day) produces a total of 536 engines each day. What is their productivity in engines per labour-hour
9
A firm cleans chemical tank cars in the Edmonton area. With standard equipment, the firm typically cleaned 70 chemical tank cars per month. They utilized 10 gallons of solvent, and two employees worked 20 days per month, 8 hours a day. The company decided to switch to a larger cleaning machine. Last August, they cleaned 60 tank cars in only 15 days. They utilized 12 gallons of solvent, and the two employees worked 6 hours a day.
What is the percentage (%) change in labour productivity? (Round it to the nearest whole number).
52
Suppose your start-up business won a contract to develop a mobile application that must be tested and running by the start of the next December (2022). If you must complete the project by the beginning of November (2022), you might need to______ to do the same work in less time.
increase the budget of the project
True or false: In PERT analysis, the identification of the critical path can be incorrect if a noncritical activity takes substantially more than its expected time.
True
True or false: The critical path can be determined by use of either the “forward pass” or the “backward pass.”
False
The following represents a project with four activities. All times are in weeks.
What is the minimum expected completion time for the project (please round off to two decimal digits)?
19.33
Learning curves have a variety of purposes, which can be placed into these broad categories:
internal, external, and strategic
If it took 1000 hours to produce the first unit of a product, and the learning curve is 70%, how long will it take to produce units 26 through 50?
3,903 hours
Ethical issues that may arise in projects large and small include
Gifts from customers, exaggerated expense reports, comprised safety or health, pressure to mask delays ( all of the above)
True or false: Gantt charts are visual devices that show the duration of activities in a project.
True
A project manager is interested in crashing a project with variable activity times. Which of the following tools should he/she employ?
PERT