NAVEDTRA 14233A, NAVAL CONSTRUCTION FORCE:SEABEE 1 & C Chapter 3 Flashcards Preview

NAVEDTRA > NAVEDTRA 14233A, NAVAL CONSTRUCTION FORCE:SEABEE 1 & C Chapter 3 > Flashcards

Flashcards in NAVEDTRA 14233A, NAVAL CONSTRUCTION FORCE:SEABEE 1 & C Chapter 3 Deck (18)
Loading flashcards...
1
Q

What program has the purpose of preventing discrepancies where the quality of the worksmanship and the materials fail to match the requirements in the plans and specifications? (Page 3-3)

A

Quality Control (QC)

2
Q

Who is responsible for developing an aggressive QC plan for each project? (Page 3-3)

A

Crewleader

3
Q

What is the most common source of informal training? (Page 3-7)

A

OJT

4
Q

What is responsible for inspection and surveillance of ongoing Seabee projects? (Page 3-9)

A

FEAD

5
Q

Any scope changes that require 50 or more man-days of additional direct labor, or increase the cost of the project by what amount or more require approval of higher headquarters? (Page 3-9)

A

$500

6
Q

A utility interruption request form should be submitted to Ops at least how many weeks in advance of required outage? (Page 3-22)

A

Two

7
Q

What is the most important phase of project planning? (Page 3-26)

A

Material take-off

8
Q

What is used to order an already existing BMLI? (Page 3-27)

A

Reorder

9
Q

What tells you the current status of your materials once they are ordered from CONUS? (Page 3-28)

A

PSR/PCR

10
Q

How often does the battalion receive a PSR/PCR showing the status of all project materials? (Page 3-28)

A

Monthly

11
Q

Materials should only be requisitioned that you will need over what time frame? (Page 3-31)

A

Two weeks

12
Q

What form is all material requisitioned on? (Page 3-31)

A

NAVSUP Form 1250-1

13
Q

For requisition materials that have to be obtained from CONUS locations, allow at least 60 days for normal requisitions and how many days for long lead items? (Page 3-31)

A

120

14
Q

When a job is completed, all remaining materials must be offered to the customer. Materials the customer does not want are stored in MLO for how many months? (Page 3-31)

A

Six

15
Q

What shall be provided for any hazardous project materials received from MLO? (Page 3-31)

A

Material Safety Data Sheet (MSDS)

16
Q

What system was developed to provide Non-Tactical Automated Data Processing (ADP) capabilities for units? (Page 3-32)

A

MicroSNAP

17
Q

How many working days is the interval between PM service inspection for NCF equipment? (Page 3-34)

A

40

18
Q

What provides an opportunity to document that the crewleader has demonstrated the capability to carry out assigned projects? (Page 3-43)

A

RDE