NCARB Sample Questions Flashcards
(47 cards)
The architect informs the owner that because of budget constraints and ceiling heights, the sprinkler piping must be exposed. The owner directs the architect to delete the sprinkler system. Prior to deleting the system, the architect should check the requirements for sprinklers in
o the building code
o the plumbing code
o ASTM
o ACI
o the building code
Which of the following methods of bidding is required
on most projects for which government funds are to
be used?
o Direct
o Negotiated
o Invited
o Public
o Public
Which of the following project delivery methods always
requires preparation of several individual bid-document
packages?
o Design-bid-build
o Fast track
o Design-build
o Turnkey
o Fast track
In developing a list of bidders for a private project, the
architect’s role is to
o select the contractor
o recommend qualified contractors
o rank the contractors in order of preference
o discourage owner-recommended contractors
o recommend qualified contractors
A contractor’s ability to obtain a performance bond for a
specific construction contract is determined by the
o owner
o architect
o contractor
o surety
o surety
AIA Document A305, Contractor’s Qualification
Statement, includes a
o financial statement
o list of subcontractors
o list of proposed consultants
o list of proposed material suppliers
o financial statement
After considering all bids, the owner favors a bid with
irregularities. According to AIA Document A701,
Instructions to Bidders, the owner
o has the right to waive irregularities and accept the bid
o has the right to extend the bidding period for corrections
o must informally request corrections from the bidder
o must only consider bids without irregularities
o has the right to waive irregularities and accept the bid
A local bank has a budget of $30,000,000 to construct a new main office. The bank wants to use contractors who are customers of the bank; however, none of the bank’s contractor customers can bond the entire amount of the contract. Which of the following is a possible option?
o Design-build
o Fast-track
o Multiple prime contractors
o Additive change orders
o Multiple prime contractors
Which of the following is an appropriate agenda item for
the prebid conference?
o Occupancy-permit procedures
o Notification of future addenda
o Pre-commissioning procedures
o Status of change orders
o Notification of future addenda
A contractor under a fixed-price construction contract
has allowed the electrical subcontractor to install
lighting fixtures other than those stated in the contract
documents. The electrical subcontractor and the
contractor both believe the substituted fixtures to be of
equal value. The construction is substantially completed
[substantially performed] and the architect rejects these
fixtures. According to AIA Document A201,
General Conditions, which of the following is true?
o The architect must accept the lighting fixtures as
installed without a cost credit to the owner.
o The architect must accept the lighting fixtures as
installed but with a cost credit to he owner.
o The contractor is required to replace the lighting
fixtures with the fixtures specified without
reimbursement.
o The contractor must replace the lighting fixtures with
the fixtures specified but is entitled to reimbursement
for labor costs for the replacement.
o The contractor is required to replace the lighting
fixtures with the fixtures specified without
reimbursement.
Architect estimates of construction costs based on final
documents should consider which of the following?
o Known change order sums
o The bidding climate
o The amount of monthly certificate of payment
o The amount of retainage
o The bidding climate
A preconstruction conference is generally held in order to
o review bonds and affidavits
o determine whether a performance bond and a
payment bond are required
o discuss changes to completed work
o clarify responsibilities and operating procedures
o clarify responsibilities and operating procedures
Shop drawings for dormitory windows have been
prepared by the manufacturer, checked by the local
distributor, and reviewed and approved by the contractor and the architect. During installation, it is discovered that the quantity of windows as indicated on the shop drawings is one less than that shown in the contract documents. Who is responsible for the discrepancy?
o The architect
o The manufacturer
o The distributor
o The contractor
o The contractor
On- site field observations by the architect are made to
determine which of the following? Check the three that
apply.
A. The progress and quality of the work
B. The amount work completed for progress payment
C. The techniques of the construction being utilized
D. Whether the work is being performed according to contract documents
E. Whether the contractor is following the proper
sequence of installation
F. Whether the contractor is following proper safety
procedures
A. The progress and quality of the work
B. The amount work completed for progress payment
D. Whether the work is being performed according to contract documents
The contractor for a project submits to the architect
shop drawings that contain deviations from the contract
documents not noted as deviations on the shop drawings. The drawings are then approved and returned to the contractor by the architect. According to AIA Document A201, which of the following is true in this situation?
o The contractor assumes responsibility for deviations
from the contract documents.
o The contractor is allowed to build according to the
approved shop drawings containing deviations.
o The architect assumes responsibility for deviations
from the contract documents because the architect
approved the shop drawings.
o The owner must be informed of all deviations from and alterations to the contract documents.
o The contractor assumes responsibility for deviations
from the contract documents.
At a project site, the architect notices the mechanical
subcontractor unloading equipment for which shop
drawings have not been received. The architect’s most
appropriate first course of action is to
o stop the unloading at once and report the incident to
the owner
o advise the general contractor that the equipment is
subject to rejection pending the architect’s review
o ask whether the shop drawings are in the
subcontractor’s possession
o inspect the equipment to determine whether it meets the requirements set forth in the project specifications
o advise the general contractor that the equipment is
subject to rejection pending the architect’s review
Which of the following conditions should be met before
the start of interior painting?
o The permanent heating system is operational.
o Exterior openings are sealed.
o The exterior temperature is above 50° F.
o Sidewalks have been completed for dirt control.
o Exterior openings are sealed.
During a concrete pour, a portion of the third floor of a
project collapses because of inadequate shoring. The
architect informs the contractor that work in the area of
the collapse will not be approved until the architect can
fully evaluate the impact of the failure on adjacent work in place. The contractor states that the architect will be held responsible for the cost of delays unless the analysis is performed within 24 hours. The architect should
o perform as complete and thorough an analysis as
possible within 24 hours
o perform a complete analysis in a timely manner and
make it clear that the contractor will be responsible for
the schedule
o put the owner on notice that the owner may have to
pay additional costs for an extended completion date
o allow the contractor to proceed with work in the
adjacent area so that no time is lost
o perform a complete analysis in a timely manner and
make it clear that the contractor will be responsible for
the schedule
In accordance with AIA Document A201, General
Conditions, the obligation to pay or to see to the payment of money to a subcontractor, except as may otherwise be required by law, rests with the
o contractor alone
o architect alone
o owner alone
o contractor, the architect, and the owner
o contractor alone
When delivering brick to the site, the supplier offloaded
the bricks at a point very distant from where they are
needed. The contractor requests an extra for relocating
the brick. The architect should
o reject the request for an extra on the grounds that it is the contractor’s responsibility
o require the brick supplier to relocate the brick
o prepare an appropriate change order giving the
contractor a contract increase for relocating the brick
o prepare an addendum to the contract outlining the
responsibility of the brick supplier in the delivery
of brick
o reject the request for an extra on the grounds that it is the contractor’s responsibility
Six months after final payment, the building manager
notifies the architect that an operating and maintenance
manual for a key piece of equipment was never received. The architect should do which of the following?
o Instruct the contractor to provide the manual.
o Withhold an amount of retainage necessary to provide for the manual.
o Suggest the building manager contact the
manufacturer directly for the manual, since final
payment has been made to the contractor.
o Contact the manufacturer directly to obtain
the manual.
o Instruct the contractor to provide the manual.
After occupying a portion of a building, the owner
notices a dent in a wall. The dent was not noted on the
punch list prepared by the contractor and reviewed by the architect. What determination should the architect make?
o The contractor is responsible for the repair
even though it was not on the original punch list.
o The owner has taken occupancy and is therefore
responsible because the cause of the damage cannot
be established.
o The contractor is responsible because only a portion of the building is occupied and other construction
activities continue.
o The architect is responsible because he/she missed the damage during the original punch list walk-through.
o The owner has taken occupancy and is therefore
responsible because the cause of the damage cannot
be established.
A contractor omits an item of incomplete or incorrect
work from the punch list accepted by the architect.
Who is liable for the cost of completing or correcting that item when the omission is discovered?
o The architect
o The surety
o The owner
o The contractor
o The contractor
Which of the following types of test equipment is used to check for air infiltration on an already constructed exterior wall system?
o A smoke pencil
o A cylinder
o An HEPA filter
o An ultrasonic detector
o A smoke pencil