Notes from PDF Flashcards
Who is Prince 2 relevant to?
The PRINCE2® qualification is intended for project managers and aspiring project
managers.
It is also relevant to other key staff involved in the design, development and delivery of
projects, including project board members, team managers, project assurance, project support, and
operational line managers/staff.
The definition and characteristics of a project
Project: \
A temporary organization that is created for the purpose of delivering one or more business
products according to an agreed business case.
Characteristics of a project that distinguish project work from business as usual:
- Change Projects are the means by which we introduce change.
- Temporary As the definition of a project states, projects are temporary in nature.
- Cross-functional A project involves a team of people with different skills working together (on a
temporary basis) to introduce a change that will impact others outside the team. - Unique Every project is unique.
The six aspects of project performance to be managed
- Costs The degree of permissible overspend or underspend against an agreed budget.
- Timescales The degree to which a project is permitted to deliver later or earlier than an agreed
target completion date. - Quality How much something can vary from agreed quality criteria.
- Scope Permissible variation of the plan’s products.
- Benefits The degree to which it is permissible to under-deliver or over-deliver benefits (realized
or estimated). - Risk Limits on the plan’s aggregated risks.
- PRINCE2 principles: The principles are the guiding obligations and good practices which
determine whether the project is genuinely being managed using PRINCE2 business case:
- continued business justification
- learn from experience
- defined roles and responsibilities
- manage by stages
- manage by exception
- focus on products
- tailor to suit the project.
- PRINCE2 themes: The themes describe aspects of project management that must be
addressed continually and in parallel throughout the project.
- organization
- quality
- plans
- risk
- change
- progress.
- PRINCE2 processes: The seven processes describe a progression from the pre-project activity
of getting started, through the stages of the project life cycle, to the final act of project closure:
- starting up a project
- directing a project
- initiating a project
- controlling a project
- managing product delivery
- managing a stage boundary
- closing a project.
- The project environment:
Organizations often want a consistent approach to managing projects and tailor
PRINCE2 to create their own project management method.
What makes a project a PRINCE2 project?
For a project to be a ‘PRINCE2 project’, as a minimum it must be possible to demonstrate that it:
- is applying PRINCE2 principles
- is meeting the minimum requirements set out in the PRINCE2 themes
- has project processes that satisfy the purpose and objectives of the PRINCE2 processes
- is either using PRINCE2 recommended techniques or using alternative, equivalent techniques.
The benefits of PRINCE2 for an individual is that the individual will:
- gain a globally recognized certification
- know how to start, manage the steps, and close a project
- learn common project management terminology
- know how to structure a project
- improve career prospects
- improve standing within their organization
- clearly understand their role as project manager
The customer/supplier context on which PRINCE2 is based
PRINCE2 assumes that there will be a customer who will specify the desired result and (usually) pay
for the project, and a supplier who will provide the resources and skills to deliver that result.
Projects can exist within many contexts; they may be stand-alone (with their own business case and
justification) or they may be part of a programme or wider portfolio. Figure 2.2 shows how projects
may fit within a programme and portfolio context. In addition, projects may be wholly managed within the commissioning organization or be part of a commercial relationship.
The PRINCE2 principle of continued business justification is that for all projects:
- there is a justifiable reason for starting the project.
- that justification is recorded and approved.
- the justification remains valid, and is revalidated, throughout the life of the project.
The PRINCE2 principle of learn from experience is that learning from experience takes place
throughout a PRINCE2 project, including:
- when starting a project
- as the project progresses
- as the project closes.
The PRINCE2 principle of defined roles and responsibilities is that all projects have the
following primary stakeholders:
- ‘business’ sponsors who endorse the objectives and ensure that the business investment
- provides value for money.
- ‘users’ who, after the project is completed, will use the products to enable the organization to
- gain the expected benefits
- ‘suppliers’ who provide the resources and expertise required by the project (these may be
- internal or external)
The PRINCE2 principle of manage by stages is that a
PRINCE2 project is planned, monitored
and controlled, management stage by management stage.
The PRINCE2 principle of manage by exception is that
a PRINCE2 project has defined
tolerances for each project objective, to establish limits of delegated authority.
The PRINCE2 principle of focus on products is that a
PRINCE2 project focuses on the definition
and delivery of products, in particular their quality requirements.
The PRINCE2 principle of tailor to suit the project is that
PRINCE2 is tailored to suit the project
environment, size, complexity, importance, team capability and risk.
The following aspects of PRINCE2 may be tailored:
\
- processes may be combined or adapted (e.g. by adding or combining activities
- themes can be applied using techniques that are appropriate to the project may be combined or split,
provided that accountability is maintained and there are no conflicts of interest - management products may be combined or split into any number of documents or data sources
- terminology may be changed to suit other standards or policies, provided it is applied consistently
The purpose of the business case theme is to…
establish mechanisms to judge whether the
project is (and remains) desirable, viable and achievable as a means to support decision-making in its
(continued) Investment.
Benefits management approach…
Defines the management actions that will be put in place to
ensure that the project’s outcomes are achieved and confirm that the project’s benefits are realized.
PRINCE2’s requirements for the business case theme is that to be following PRINCE2, a
project must, as a minimum:
Desirable and viable? Does it outweigh the risks of doing so?
- create and maintain a business justification for the project; usually a business case
- review and update the business justification in response to decisions and events that might impact
desirability, viability or achievability of the project - define the management actions that will be put in place to ensure that the project’s outcomes are
achieved and confirm that the project’s benefits are realized - define and document the roles and responsibilities for the business case and benefits management.
Output
Tangible or intangible specialist products
Key concepts related to business justification:
- Output A specialist product that is handed over to a user (or users). Note that management products
are not outputs but are created solely for the purpose of managing the project. - Outcome The result of change, normally affecting real-world behaviour and/or circumstances.
Outcomes are desired when a change is conceived. They are achieved as a result of the activities
undertaken to effect the change. - Benefit The measurable improvement resulting from an outcome perceived as an
- advantage by one or more stakeholders.
- Dis-benefit A measurable decline resulting from an outcome perceived as negative by one
- or more stakeholders, which reduces one or more organizational objective(s).