OCP C Exam Review Flashcards
Any unwanted electrical signals that are induced into or superimposed onto a power or signal line is commonly referred to as _____.
Electromagnetic interference
At the conclusion of a project, a qualified person or agency, supervises the acceptance and testing of the system. This acceptance and testing of the system is called _____.
commissioning
network configuration that establishes a direct, physical, peer-to-peer communications between two nodes that need to communicate between two or more switches is a(n) _____.
Hierarchical star
The most basic form of network security is the use of a _____.
Firewall
The term “malware” is used to describe _____.
malicious software
The _____ protocol allows users to send e-mail messages to a server.
Simple Mail Transfer
When running the HTTP protocol, a(n) _____ interprets the data stream and builds an on-screen window containing text and images.
Web browser
An Ethernet device is marked as 1000-Base-F. The transceiver is rated for _____ baseband signal over _____.
1Gbps; a fiber optic cable for 500 meters
Most personal computers use the _____ operating system.
Windows
The _____ protocol is now the default protocol used for networking.
Tran
Transmission Control
Use a _____ to support multiple paths through a series of connected networks.
RP
routing protocol
Drawings that show all changes made from the original job plan to the finished state are called _____ drawings.
as built
The communications pathway within an individual computer is called a _____.
bus
The first step in the bidding process is _____.
request for invitation to bid
The term gigahertz (GHz) represents a frequency in the _____ of cycles per second.
1 billion
POE devices may obtain their power from the _____.
Ethernet cables
Multiplexing is a form of combining several _____ into one high-capacity channel that can carry signals from several sources.
signals
The protocol that is used to make the Internet is _____.
Internet Protocol
These drawings are placed at the beginning of a set of drawings.
cover sheets
The last item to be done before the job is successfully finished is _____.
final inspection and sign-off
One advantage of an analog addressable system over a Single Line Carrier (SLC) system is, an addressable system _____.
can report more information
This antenna type is widely used in satellite television.
parabolic dish antenna
Wiring certification diagrams, or wiring list normally become part of the _____.
as-built documentation
During a site survey, a walk around of the complete job site is performed with the key individuals involved with the work to be performed. These key individuals are referred to as _____.
stakeholders