Part 3 Flashcards

(43 cards)

1
Q

Public consultation process UK

A
  1. Pre application consultation
  2. Application submission
  3. Consultation period
  4. Decision
  5. Appeals/ further engagement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Public consultation process China

A
  1. Planning stage (less formal)
  2. Limited public engagement
    (Public notice period shorter)
  3. Transparency
  4. Final approval
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Fees calculation cost methods

A
  1. Percentage of consultation cost
  2. Lump sum/ fixed fee
  3. Time based fee
  4. Unit cost
  5. Stage payments
  6. Performance based fee (less common)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Role of contract administrator

A
  1. Plays a formal role at stage 5,6
    (5) Administering building contract
    Issuing instructions
    Certifying payments
    Monitering progress
    Assessing extensions of time

(6) practical completion
Defects
Final account

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Who is usually the contract administrator

A

Architect or project manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What does qs do with 50-70% design

A

Preliminary cost estimating
Risk identification
Procurement advice
Cash flow forecasting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What can qs NOT do

A

Bill of quantities (BOQ)
Fixed cost tendering
VE trade off
Detailed cost control during construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is DRM

A

Design responsibility matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Asvantages of DRM

A

Clear allocation of design responsibilities
Reduce risk of design gaps
Improve coordination
Enhance contractual clarity
Ensure smooth design reviews and approvals
Support compliance and regulatory submissions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Risk of architects producing cost plans

A

Liability risk
Lack of market data/ benchmarking
Conflict of interest
Impact on procurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Saw bad health and safety practice why do u have to act? How to act?

A

Under standard 1&3
- honesty, integrity, competence
-Should prioritize safety of others

Report concerns
Intervene informally
Escalate issue to HSE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is liquidated damages

A

Pre agreed financial penalties in construction contract, payable by contractor to client if project not completed by agreed completion date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Why do we need liquidated damages

A

Protects employer
Encourage timely performance
Avoid need for client to prove actual loss

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When to calculate liquidated damage

A

Calculated in pre contract stage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Why are sustainability and heritage can be opposing forces?

A

Retention vs performance
-Heritage requires to retain original materials
-Sustainable tends to alter these elements

Material compatibility
-Heritage protected by planning controls
-Sustainable interventions being limited

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How does intellectual property protect architects within appointed documents

A

Legally protect original creative works AR produces
Protection under the (copyright, design and patent act 1988)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Which legal structure for own practice is preferred

A

Private limited company

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Private linited company pros and cons

A

Overall easier to scale and build
Build credibility with banks and clients
Formal structure, clear governance and roles
Tax planning opportunities
Protects personal assets if business in debt

Cons
Extra admin work
Requires compliance with HMRC and company house

19
Q

Which procurement route to minimize risk

A

Design and build

20
Q

Why design and build minimize risk

A

Single point of responsibility
Cost certainty
Programme efficiency

21
Q

‘Back to back’ clause

A

Main contractor includes clauses in their subcontract mirroring their obligations to clients, also make subcontractor responsible to those same obligations

22
Q

Collateral warranty

A

Legal agreement that create direct contractual link between 3rd party and party that would normally not have contract with

Usually in construction projects

23
Q

What to do if find out project has collateral warranty

A
  1. Check appointment terms
  2. Request draft wording early
  3. Review carefully/ seek legal advice
  4. Notify insurer
24
Q

‘Adjudication’ ‘Litigation’ which is preferred

25
Why is adjudication preferred usually
Quick interim dispute resolution process 28 days doesnt take months or years Binding immediately Works for payment dispute, delay, defect
26
Litigation
Take months / years Presided over judge in courtroom Decisions final unless appeal More expensive and formal with strict legal rules
27
Arbitration
Take months Fees medium to high Private (agreed by both parties) Proceedings not public Flexible process Decision similar to court judgement
28
Why is parity important when handle tender
Ensure fairness Transparency Better value for client Protects reputation Legal compliance
29
Who is suitable to be contract administrator if not architect
Qs Project manager Employer’s agent
30
Why is timesheets important
Fee tracking Resource planning Invoicing Justification Project performance analysis Professional obligations
31
Why should we submit pre planning application for project
1. Early feedback from local authority 2. Improve chances of approval 3. De risking the project 4. Stakeholder confidence 5. Design validation
32
What are reserved matters
Detail aspects of the development that are not approved as part of outline planning application But must submit before work start and approved
33
5 reserved matters
Access Appearance Landscaping Layout Scale
34
Documents for planning application
Application form Location plan Site plan Existing and proposed floor plans Elevations Sections Design and access statements Planning statements (sometiems) Heritage statement (if in conservation) Landscape report Utilities Fee payment Community consultation statement (if pre app is done)
35
Relevant event
Delay outside of contractor control (Extension of time)
36
Relevant matter
Event causing loss to contractor (Additional payment)
37
Relevant event example
Exceptional weather conditionss Strikes Force events Loss of access to site (not cause by contractor) Delay in receiving info
38
Relevant matter example
Late issue of instruction/ approval Employer failure to give possession of site Suspension by contractor due to non payment
39
Approaching new client
Initial contact/ intro Preliminary meeting and consultation Client brief development (stage 1) Demonstrate value and expertise Discuss fees and appointment terms Discuss next steps
40
Risk of bespoke contract
May have Disproportionate liability May have Extended duty of care May have unclear terms Conflict with PI insurance
41
full name PI insurance
Professional indemnity insurance
42
What is PI insurance
Protect architects and other professions against legal claims made by clients/ 3rd parties that suffer loss due to architect negligence advice/design/service
43
PI insurance cover
Negligence Breach if contract Defamation Loss of documents Infringement ip rights Breach of confidentiality