perforance and breach of contract Flashcards
(45 cards)
breach of contract
a breach of committed when a party without lawful excuse fails or refuses to perform what is due to him under the contract
where do obligations in a contract come from?
Express Terms: Production specification
Implied Terms: Contracts between trader and consumers: A term that the good are satisfactory
Strict liability
default position in contract law - only have to prove that they didn’t do it
fault-based liability
take ‘reasonable care’ or ‘use reasonable endeavours’
what are the two basic remedies for breach of contract
damages and termination of contract
damages
an award of monetary compensation and the objective is to put the innocent party in the position as if the contract had been performed.
termination of contract
if the innocent party is entitled to terminate the contract because of a breach, they can effectively tear up the contract and refuse to perform or accept performance of future obligations. It is powerful and an advantageous remedy and it is used commercially
Is an innocent party always entitled to terminate the contract
No
condition precedent
something that must be done as a condition of the other party’s performance - something has to be performed before a contract price arises
entire obligations rule
a party must perform his entire obligation before receiving payment
severable obligations rule
party can receive payments at various stages of the contract
Cutter v Powell
Mr Powell engaged Mr cutter as a second mate on a ship and the contract provided for a high level of pay if Mr Cutter continues and does his duty from the port of Jamaica to the port of Liverpool. Mr Cutter died and his widowed wife wanted to claim for a proportion of his wages under this contract.. Courts held that the obligation to pay the contract price had not arisen has he didn’t finish the performance.
Law Reform (frustrated contract) act 1943 - where non-performance arises due to frustration (like in Cutter v powell) the court may award a ‘just sum’ in respect to the valuable benefit.
Taylor v Laird
Commander of ship hired for £50 a month, but he didn’t complete the voyage. Held that it was a severable obligation so he had to pay for the work he done
substantial performance doctrine
mitigates the harshness of the entire obligations rule. If the work is done and is regarded fit for the purpose, then the party is obliged to receiving his contractual price
Hoenig v Issacs
redecoration of flat for £750, minor defects totalling up to £55. Courts held that that the works were finished and the claimant was entitled to the full contract price, but defendant could set-off £55
Bolton v Mahadeva
Installation of central heating system for £564. System had serious defects and unfit for purpose so the customer not obliged to pay the contract price.
quantum merit
‘as much as it deserves’ - courts may award a sum of the benefit obtained by the other party if a contract has only been partly performed and the right to the price has not yet arisen. VERY RESTRICTIVE AND LIMITED
Anticipatory breach
after a contract is made, but before it was meant to be performed. Breach before the works are meant to start
White and Carter (Councils) v McGregor
McGregor’s agent entered into a contract for the advertising of McGregors business on local authority litter bins. Before the contract began, Mc found out and informed the council he did not want the contract. His actions amounted to an anticipatory breach of contract.
POLICY QUESTIONS: should this be actionable? some may argue that they should be held to the terms of the contract and it undermines contract sanctity. However the innocent party could obtain performance elsewhere
what can an innocent party do when there is an anticipatory breach
They can accept it, regard the contract as terminated and sue for damages immediately. Honchster v De la Tour: the innocent party does not have to wait till the contract was about to begin
what does the law allow the innocent party to do in the event of an anticipatory breach
The law allows the innocent party to affirm (continue with) the contract and claim the contract prices like in White and Carter v Mcgregor
2 exceptions for when they can’t carry on the contract after an anticipatory breach
- When the innocent’s party performance of the contract would require the other party to do something i.e. their co-operation
- When the innocent party has no legitimate interest in performing the contract and damages would be an adequate remedy - Gator Shipping Corporation v Trans-Asiatic Oil Ltd SA and Occidental shipping establishment
can every breach of contract entitle the innocent party to terminate the contract
no
what happens when your entitled to terminate a contract
you can effectively tear up a contract and refuse to perform or accept performance of future obligations.