Performance Domain Artifact - Plan Flashcards

1
Q

Change control plan

A

Plan Artifacts - is a component of the project management
plan that establishes the change control board, documents the extent of its authority, and describes how the change control system will be implemented.

PLANNING PROJECT DELIVERY

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Communications management plan

A

Plan Artifacts - is a component of the project, program,
or portfolio management plan that describes how, when, and by whom information about the project will be administered and disseminated.

STAKEHOLDER PLANNING PROJECT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Cost management plan

A

Plan Artifacts - is a component of a project or program management
plan that describes how costs will be planned, structured, and controlled.

PLANNING

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Iteration planning

A

Plan Artifacts - meeting is used to clarify the details of the
backlog items, acceptance criteria, and work effort required to meet an upcoming iteration commitment. This meeting may also be referred to as a sprint planning meeting.

STAKEHOLDER PLANNING PROJECT DELIVERY

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Iteration Plan

A

Plan Artifacts - A detailed plan for the current iteration.

PLANNING

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Procurement Management Plan

A

Plan Artifacts - A component of the project or program management plan
that describes how a project team will acquire goods and services from outside of the performing organization.

PLANNING PROJECT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Project Management Plan

A

Plan Artifacts - The document that describes how the project will be executed,
monitored and controlled, and closed.

STAKEHOLDER PLANNING PROJECT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Quality Management Plan

A

Plan Artifacts - A component of the project or program management plan that
describes how applicable policies, procedures, and guidelines will be implemented to achieve the quality objectives.

PLANNING PROJECT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Release Plan

A

Plan Artifacts - The plan that sets expectations for the dates, features, and/or outcomes expected to be delivered over the course of multiple iterations.

PLANNING DELIVERY

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Requirements Management Plan

A

Plan Artifacts - A component of the project or program management plan that
describes how requirements will be analyzed, documented, and managed.

PLANNING DELIVERY

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Resource Management Plan

A

Plan Artifacts - A component of the project management plan that describes how
project resources are acquired, allocated, monitored, and controlled.

PLANNING PROJECT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Risk Management Plan

A

Plan Artifacts - A component of the project, program, or portfolio management plan that
describes how risk management activities will be structured and performed.

PLANNING PROJECT UNCERTAINTY

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Scope Management Plan

A

Plan Artifacts - A component of the project or program management plan that describes
how the scope will be defined, developed, monitored, controlled, and validated.

PLANNING DELIVERY

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Schedule Management Plan

A

Plan Artifacts - A component of the project or program management plan that
establishes the criteria and the activities for developing, monitoring, and controlling the schedule.

PLANNING PROJECT DELIVERY

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Stakeholder Engagement Plan

A

Plan Artifacts - A component of the project management plan that identifies the
strategies and actions required to promote productive involvement of stakeholders in project or program decision making and execution.

STAKEHOLDER PLANNING

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Test Plan

A

Plan Artifacts - A document describing deliverables that will be tested, tests that will be conducted, and the processes that will be used in testing.

PLANNING PROJECT DELIVERY MEASUREMENT