PJM Flashcards
(252 cards)
Transmission Owners are required to provide notice of all transmission
outages:
Prior to the first day of the month, preceding the month of the outage
Provide notice of all hotline transmission work, five days or less, by 0800 three days prior to the start of the outage (345kV and above)
Starting March 16th. When does it need submitted by to be on time?
Hotline work starting on March 16th must be submitted by
07:59 on March 13th to be on time
1-Month Rule: Transmission Owners are required to Provide notice of all transmission outages, five days or less, prior to the
first day of the month preceding the month of the outage.
5 Day outage starting in June, when must it be submitted to be on time?
A 5-day outage starting in June must be submitted by
23:59 on April 31 to be on time
6-Month Rule: The TO is required to Submit all outage requests in excess of 5 days in duration, prior to the 1st of the
month, six months in advance of the start of the outage.
6 Day outage starting in October, when must it be submitted to be on time?
6-day outage begins in October, the outage must be submitted by 23:59
on March 31 to be on time
30-Day Rule: Outages scheduled for the following Planning year (i.e. June 1 – May 31), exceeding 30 days Submitted via eDART prior to February 1 for use in the annual FTR auction,
unless the 6-month rule is more restrictive.
An outage greater than 30 days starts in September. It must be submitted by:
6-month rule: Must be submitted by February 29 @ 23:59
30-day rule: Must be submitted by January 31 @ 23:59
‒ Since the 30-day rule is more conservative, it applies
An outage greater than 30 days starts in July. It must be submitted by?
6 month rule: December 31 of the year prior @ 2359
30 day rule: January 31 @ 2359
‒ Since the 6 month rule is more conservative, it applies
eDART:
Creating a New Transmission Outage Ticket - Business Rules
Ticket must be submitted a minimum how many days in advance of start date?
3 Business days. Unless Emergency
Emergency: Outage due to equipment problem or tripping and must be
taken immediately
‒ 3 day notice NOT required for emergency job
eDART: Vegetation Trip
If outage was a tripping caused by tree contact, this
checkbox must be checked. What else needs to be reported?
Needs to be reported to NERC
eDART: Color Coding
Congestion Expected Flag
RED
PJM will check this flag
when a studied outage
causes the potential for
off-cost operation
eDART: Color Coding
Conflict Flag
Orange
If an outage is submitted violating a scenario, immediate feedback on impacted previously submitted tickets will be provided.
eDART: Color Coding
EMS Tripping Tickets
Yellow
Tripped equipment (from PJM EMS) automatically creates an eDART outage ticket.
All equipment 115kV and above.
eDART: Color Coding
“System Impact” Flag
Magenta
Allows the reliability engineers to pre-screen outages based on known impacts to
generation, thermal overloads, voltage violations, stability restrictions, etc.
before studying the outage.
eDART: Color Coding
Potentially Incomplete Flag
Lavendar / Light Purple
Added to transmission outage tickets to flag tickets that may need further
review by PJM
eDART: Color Coding
Soon to be In-Service Flag
Mint Green
To be Put in Service Soon
eDART: Color Coding
Soon to be Retired Flag
Blue
To be retired from system soon
What type of system is where current lags voltage?
Inductive
What type of Configuration uses a neutral connection?
Delta-Wye
What type of communications must you have at the primary and back-up control centers?
Satellite Phones
What is the maximum amount of time allowed to transfer from the primary control center to the back-up control center?
2 Hours
If the operator loses communication from the system for longer than 30 minutes, what is the maximum amount of time the operator must notify PJM of the communication loss?
60 minutes
If communication from the system is down, how often must the operator update PJM?
30 minutes
How long do you have to preform an IROL Load Dump Action?
5 Minutes
A Relays ability to see all the faults within its zones is best described as?
Sensitivity
You are in system restoration and have black start capability throughout your region and have received word that your neighboring utility also was affected but they remained party connected but their system is unstable. What system restoration method should you use?
Bottom Up