PjM Basics - Contracts Flashcards

(58 cards)

1
Q

What are the main parts of AIA contract B101?

A

Owner- Architect Agreement
1. Architect must be on time and under budget (or no more than 10% over)
2. Architect must get a cost estimate after SD, DD, and CD
3. Excuse the architect from mistakes by owner’s consultants
4. Architect must visit the site 1 year after substantial completion
5.Owner can terminate for convenience
6.Claims must be brought within 10 Years
7.Allows for liquidated damages if a claim arises

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What types of insurance does AIA Contract B101 typically require?

A
  1. Automotive Liability Insurance
    - biggest risk for firms , extends to personal cars and taxis
  2. Professional Liability Insurance
  3. General Liability Insurance
  4. Workers Compensation Insurance
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What does general liability insurance cover?

A

-protection for property damage and workplace injuries
-Covers both legit and fraudulent claims
-There is usually a dollar limit or aggregate limit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What does professional liability insurance cover?

A

(Errors and Omission)
- protection against claims that you failed to do your job properly
-protection against violations of ADA, OSHA, Fair Housing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are paths for resolving conflicts between Architect and Owner per AIA Contract B101?

A

Mediation then arbitration or mediation then litigation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the architectural basic services per AIA Contract B101?

A

Submit a schedule, meet code, facilitate bidding, certify payments to contractor, review submittals, consider sustainability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What constitutes an additional service for the architect?

A

everything beyond a single drawings set with MEP and Structural

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the owner responsible for?

A

Geotech, everything site and permit related, coordinating their own consultants

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Who owns the drawings?

A

Architect and Consultants

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When can the architect terminate the contact?

A

If owner doesn’t pay or suspends project for 90 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

When does the contract automatically terminate?

A

1 year after substantial completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When does the architect get a cost estimate?

A

After SD, DD, and CD

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Does the architect return to the site after the building is complete?

A

Yes, 1 year after substantial completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How long does the owner or architect have to bring claims?

A

10 Years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What if the bidding phase doesn’t start within 90 days after CDs?

A

The owner’s budget needs to be adjusted to reflect changes in costs for construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

what does the architect do if the project phase is delayed past substantial completion?

A

ask for additional services

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What are the steps when the architect identifies or is notified of a change that will affect cost or schedule?

A

adjust the work plan, explain the facts and circumstances to the owner, and send a change order for approval in writing - AIA B101 4.2.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What should the architect do if they notice unsafe site conditions?

A

notify the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What are liquidated damages?

A

per-day penalty for a delayed construction project completion, agreed upon at the beginning (cannot be taken in the form of withholding payment without formal agreement)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What are consequential damages?

A

estimated cost of potentially lost profit due to project delays (not allowed)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is the first step if the owner and contractor have a disagreement?

A

the initial decision maker steps in, the architect by default

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What are the “contract documents?”

A

Conditions of the contract, Drawings, Specs, Addenda, and other documents listed in A101

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

When does the contractor’s warranty end?

A

1 year after substantial completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

When is a project late?

A

when substantial completion is late

25
Who certifies substantial completion?
the architect
26
When is retainage paid?
when substantial completion certificate is awarded
27
How does the contractor get paid per AIA Contract A101?
an application for payment (G702) is made by the contractor and given to the architect for review. If the work is in line with the contract documents, the architect will issue a certificate for payment to the owner, who will pay the contractor
28
What is the pay period for an application of payment (G702) per AIA Contract A101?
one calendar month ending on the last day of the month unless otherwise specified
29
When is the final payment to the contractor made and what does it include?
the owner pays the contractor the final payment consisting of the entire contract sum after the contractor has fully performed the responsibilities outlined in the contract, and the final certificate for payment has been issued by the architect owner must pay within 30 days
30
G Series in AIA Contracts
Change Orders, Application for Payment, Continuation Sheet, Certificate of Substantial Completion, RFIs
31
General Conditions of the Contract for Construction require the contractor's insurance policy to cover
Damages related to vehicles Damages dye to bodily injust from falling material on site Bodily injury or property damage after the contractor has left the site Workers compensation
32
A101
Owner Contractor Agreement
33
A201
General Conditions of the Contract for Construction
34
B101
Owner Architect Agreement
35
C401
Architect Consultant Agreement
36
A132
Owner Contractor Agreement when using CM as Advisor or CM as Agent
37
A133
Owner CM as Constructor Agreement
38
A195
Owner and Contractor for Integrated Project Delivery
39
G701
CHange Order
40
G702
Application for Payment
41
G703
Continuation Sheet
42
G704
Certificate of Substantial Completion
43
G716
RFI
44
A Series
Owner Contractor Agreements
45
B Series
Owner Architect Agreements
46
C Series
Consultant and Other Agreements
47
D Series
Miscellaneous Documents
48
E Series
Exhibits
49
G Series
Contract Administration and Project Management Forms
50
A103
Owner Contractor Agreement for Cost plus Fee without GMP
51
A141
Owner and Design Builder Agreement
52
E203
BIM
53
E204
Sustainable Projects
54
G710
Architects Supplemental Instructions
55
A714
Construction Change Directive
56
B205
Historic Preservations
57
B214
LEED Certifications
58
B210
Facility Support