Flashcards in Plans Theme Deck (7)
Loading flashcards...
1
Q

Who approves the project, stage and exception plans with tolerances?

A

Exec/ board

2
Q

Who commits business resources to stages? e.g. finances?

A

Senior User and Senior Supplier

3
Q

Who design the plans?

Prepares project and stage plans, and if required, an exception plan

A

PM

4
Q

Who contributes specific expertise to the PM when possible?

A

Project Support

5
Q

Who prepares the Team Plan?

A

TM

6
Q

Is the Team Plan mandatory?

A

No

7
Q

What is minimum number of stages?

A
  1. Initiation

2. Further Stage