PM AND SCRUM ACRONYMS Flashcards
(111 cards)
1
Q
AC
A
ACTUAL COST
2
Q
ADM
A
ARROW DIAGRAMMING METHOD
3
Q
ADR
A
ALTERNATIVE DISPUTE RESOLUTION
4
Q
AE
A
APPORTIONED EFFORT
5
Q
AOA
A
ACTIVITY ON ARROW
6
Q
AON
A
ACTIVITY ON NODE
7
Q
BAC
A
BUDGET AT COMPLETION
8
Q
BCR
A
BENEFIT COST RATIO
9
Q
BOM
A
BILL OF MATERIALS
10
Q
CA
A
CONTROL ACCOUNT
11
Q
CBT
A
COMPUTER BASED TEST (FOR PMP EXAM)
12
Q
CCB
A
CHANGE CONTROL BOARD
13
Q
CCR
A
CONTINUING CERTIFICATION REQUIREMENTS
14
Q
CMMI
A
CAPABILITY MATURITY MODEL INTEGRATED
15
Q
COC
A
COST OF CONFORMANCE
16
Q
CONC
A
COST OF NON CONFORMANCE
17
Q
COQ
A
COST OF QUALITY
18
Q
CPAF
A
COST PLUS AWARD FEE (CONTRACT)
19
Q
CPFF
A
COST PLUS FIXED FEE
20
Q
CPI
A
COST PERFORMANCE INDEX
21
Q
CPIF
A
COST PLUS INCENTIVE FEE (CONTRACT)
22
Q
CPM
A
CRITICAL PATH METHOD
23
Q
CPPC
A
COST PLUS PERCENTAGE OF COST
24
Q
CR
A
CHANGE REQUEST
25
CV
COST VARIANCE
26
CWBS
CONTRACT WORK BREAKDOWN STRUCTURE
27
DOE
DESIGN OF EXPERIMENTS
28
EAC
ESTIMATE AT COMPLETION
29
EEF
ENTERPRISE ENVIRONMENTAL FACTORS
30
EF
EARLY FINISH
31
EMV
EXPECTED MONETARY VALUE
32
EPV
EXPECTED PRESENT VALUE
33
ES
EARLY START
34
ETC
ESTIMATE TO COMPLE
35
EV
EARNED VALUE
36
EVA
EARNED VALUE ANALYSIS
37
EVM
EARNED VALUE MANAGEMENT
38
EVT
EARNED VALUE TECHNIQUE
39
FF
FINISH-TO-FINISH
40
FFP
FIRM FIXED PRICE (CONTRACT)
41
FMEA
FAILURE MODE AND EFFECT ANALYSIS
42
FPEPA
FIXED PRICE IWTH ECONOMIC PRICE ADJUSTMENT (CONTRACT)
43
FPIF
FIXED PRICE INCENTIVE FEE (CONTRACT)
44
FS
FINISH-TO-START
45
IFB
INVITATION FOR BID
46
IRR
INTERNAL RATE OF RETURN
47
ITTO
INPUTS, TOOLS, TECHNIQUES AND OUTPUTS
48
JIT
JUST IN TIME
49
LF
LATE FINISH
50
LOE
LEVEL OF EFFORT
51
LS
LATE START
52
NPV
NET PRESENT VALUE
53
OBS
ORGANIZATIONAL BREAKDOWN STRUCTURE
54
OPA
ORGANINATIONS PROCESS ASSETS
55
OPM3
ORGANIZATION PROJECT MANAGEMENT MATURITY MODEL
56
PBT
PAPER BASED TEST (PMP EXAM)
57
PDCA
PLAN-DO-CHECK-ACT
58
PDM
PRECEDENCE DIAGRAMMING METHOD
59
PDU
PROFESSIONAL DEVELOPMENT UNIT
60
PERT
PROGRAM EVALUATION AND REVIEW TECHNIQUE
61
PM
PROJECT MANAGER
62
PMB
PERFORMANCE MEASUREMENT BASELINE
63
PMBOK
A GUIDE TO THE PM BODY OF KNOWLEDGE
64
PMI
PROJECT MANAGEMENT INSTITUTE
65
PMIS
PROJECT MANAGEMENT INFORMATION SYSTEM
66
PMO
PROJECT MANAGEMENT OFFICE
67
PMP
PROJECT MANAGEMENT PROFESSIONAL
68
PS
PLANNED START DATE
69
PTA
POINT OF TOTAL ASSUMPTION
70
PV
PLANNED VALUE OR PRESENT VALUE
71
QA
QUALITY ASSURANCE
72
QC
QUALITY CONTROL
73
QFD
QUALITY FUNCTION DEPLOYMENT
74
RACI
RESPONSIBLE, ACCOUNTABLE, CONSULT, INFORM (CHART)
75
RAM
RESPONSIBILITY ASSIGNMENT MATRIX
76
RBS
RESOURCE BREAKDOWN STRUCTURE OR RISK BREAKDOWN STRUCTURE
77
RFI
REQUEST FOR INFORMATION
78
RFP
REQUEST FOR PROPOSAL
79
RFQ
REQUEST FOR QUOTATION
80
ROI
RETURN ON INVESTMENT
81
ROM
ROUGH ORDER OF MAGNITUDE
82
SF
START-TO-FINISH
83
SME
SUBJECT MATTER EXPERTS
84
SOW
STATEMENT OF WORK
85
SPI
SCHEDULE PERFORMANCE INDEX
86
SS
START-TO-START
87
SV
SCHEDULE VARIANCE
88
SWOT ANALYSIS
STRENGTHS, WEAKNESSES, OPPORTUNITIES AND THREATS ANALYSIS
89
T&M
TIME & MATERIALS
90
TCPI
TO-COMPLETE PERFORMANCE INDEX
91
TQM
TOTAL QUALITY MANAGEMENT
92
TS
TARGET START DATE
93
VAC
VARIENCE AT COMPLETION
94
VE
VALUE ENGINEERING
95
VOC
VOICE OF THE CUSTOMER
96
WAS
WORTH AUTHORIZATION SYSTEM
97
WBS
WORK BREAKDOWN STRUCTURE
98
ATDD
ACCEPTANCE TEST-DRIVEN DEVELOPMENT (AGILE)
99
BDD
BEHAVIOR-DRIVEN DEVELOPMENT
100
BRD
BUSINESS REQUIREMENT DOCUMENTS
101
DA
DISCIPLINED AGILE
102
DoD
DEFINITION OF DONE
103
DoR
DEFINITION OF READY
104
DSDM
DYNAMIC SYSTEMS DEVELOPEMENT MODEL
105
Evo
EVOLUTIONARY VALUE DELIVERY
106
LeSS
LARGE-SCALE SCRUM
107
LSD
LEAN SOFTWARE DEVELOPMENT
108
RUP
RATIONAL UNIFIED PROCESS
109
SAFe
SCALED AGILE FRAMEWORK
110
SBE
SPECIFICATION BY EXAMPLE
111
XP
EXTREME PROGRAMMING