PM & Forecasting Flashcards
(44 cards)
When to use Earned Value Analysis
- To compute how far ahead or
behind schedule a project is. - To compute how over or under
budget a project is.
Budgeted Cost of Work Scheduled
BCWS
% Schedulled x Budget
BCWS is the amount of money you planned to spend on the project up to a certain point in time based on the scheduled tasks.
Eg. Budgeted Cost of Work Scheduled BCWS
Example:
Total project budget = $100,000
By Week 4, you planned to complete 40% of the work.
Then:
𝐵𝐶𝑊𝑆 = 40%×$100,000 =$40,000
BCWC Budgeted Cost of Work Completed to date for the activity
% completed x Budget
How much we expected to spend based on the actual amount of completed work
Total BCWS
Sum of BCWS for each activity
Total BCWC (Earned Value)
Sum of BCWC for each activity
How do you calculate how far ahead or behind schedule an ACTIVITY is?
% Schedulled - % Completed / Schedulled x 100
OR
BCWS - BCWC / BCWS x 100 %
How do you calculate how far ahead or behind schedule the PROJECT is?
(BCWS total - BCWC total / BCWS total) X 100
ACWC
Actual Cost of Work Completed
Actual Cost of Work Completed
How much we actually spend based on the actual amount of completed work
Forecasting
Statistical estimate of future demand, that can be used to plan current activities.
Qualitative Forecasting Methods
- Executive Judgement
- Market Research
- Panel Concensus
Quantitative Forecasting Methods
Typical Time Series of Past Demands
Forecastng Notation
At and Ft
At
The actual demand at time t
Ft
The forecasted demand at time t
Methods to forecast demand at time t Ft
- Simple Moving Averages
- Weighted Moving Averages
- Exponential Smoothing
n-period Simple Moving Averages
Ft = At1+At2+…+At-1 / nt-1
n-period weighted moving average (WMA)
Ft = w1xAt1 + W2xAt2 +…+ wnxAt-1
W1 is the most recent observed demand, greater weight. De abajo para arriba
Can assign different weight to different time periods
Forecast error at time t
Ft - At
How to evaluate a forecast
Using the mean absolute error (MAE)
Mean Absolute Error - MAE
∑ ∣ Forecast t − Actual t ∣ / T
Advantages of Forecasting with more periods
More data = less randomness and more reliable averages
If there’s no trend, more data = lower forecasting error.
What are the downsides of using too many periods in a forecast?
Slower to react to real changes in demand
If there’s a trend, more data can actually make the forecast worse