PMBOK Acronyms Flashcards
(54 cards)
2
Q
AC
A
actual cost
3
Q
ACWP
A
actual cost of work performed
4
Q
BAC
A
budget at completion
5
Q
BCWP
A
budgeted cost of work performed
6
Q
BCWS
A
budgeted cost of work scheduled
7
Q
CCB
A
change control board
8
Q
COQ
A
cost of quality
9
Q
CPAF
A
cost plus award fee
10
Q
CPF
A
cost plus fee
11
Q
CPFF
A
cost plus fixed fee
12
Q
CPI
A
cost performance index
13
Q
CPIF
A
cost plus incentive fee
14
Q
CPM
A
critical path methodology
15
Q
CV
A
cost variance
16
Q
EAC
A
estimate at completion
17
Q
EF
A
early finish date
18
Q
EMV
A
expected monetary value
19
Q
ES
A
early start date
20
Q
ETC
A
estimate to complete
21
Q
EV
A
earned value
22
Q
EVM
A
earned value management
23
Q
FF
A
finish-to-finish
24
Q
FFP
A
firm fixed price
25
Q
FMEA
A
failure mode and effect analysis
26
FP-EPA
fixed price with economic price adjustment
27
FPIF
fixed price incentive fee
28
FS
finish-to-start
29
IFB
invitation for bid
30
LF
late finish date
31
LOE
level of effort
32
LS
late start date
33
OBS
organizational breakdown structure
34
PDM
precedence diagramming method
35
PMBOK
project management body of knowledge
36
PMIS
project management information system
37
PMP
project management professional
38
PV
planned value
39
QA
quality assurance
40
QC
quality control
41
RACI
responsible, accountable, consult, and inform
42
RAM
responsibility assignment matrix
43
RBS
risk breakdown structure
44
RFI
request for information
45
RFP
request for proposal
46
RFQ
request for quotation
47
SF
start-to-finish
48
SOW
statement of work
49
SPI
schedule performance index
50
SS
start-to-start
51
SV
schedule variance
52
SWOT
strengths, weaknesses, opportunities, and threats
53
T&M
time and material
54
TQM
total quality management
55
WBS
work breakdown structure