PMI-ACP Definitions Flashcards

(103 cards)

1
Q

PMI-ACP Definitions

A variation of test-driven development where a team develops tests to evaluate products from a customer’s perspective before creating products.

A

acceptance test-driven development

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

PMI-ACP Definitions

A leader’s ability to adjust leadership styles and adapt to situations

A

adaptive leadership

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

PMI-ACP Definitions

An estimating technique that asks team members to silently order user stories before estimating the amount of work they could complete in an interation.

A

affinity estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

PMI-ACP Definitions

A form of project management and product development based on a process of incremental and iterative improvements.

A

Agile development

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

PMI-ACP Definitions

The act of using models on Agile projects to illustrate relationships among project elements.

A

Agile modeling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

PMI-ACP Definitions

The tools and techniques unique to Agile practices that help teams complete work and satisfy project objectives.

A

Agile tooling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

PMI-ACP Definitions

A simplified modification of the IBM Rational Unified Process (RUP), an iterative software development process framework.

A

Agile Unified Process (AUP)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

PMI-ACP Definitions

Line charts that track the amount of work completed in iterations or projects.

A

burn charts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

PMI-ACP Definitions

A line chart that tracks the amount of work completed in an iteration or release. The point at which the downward trend of the line intersects with the x-axis indicates the probable completion date.

A

burndown chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

PMI-ACP Definitions

A line chart that shows an accumulation of the work completed in an iteration or release. The upward trend of the chart can be followed to estimate how many requirements will be satisfied by the release or iteration completion date.

A

burn-up chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

PMI-ACP Definitions

The ability to work together to reach a common goal.

A

collaboration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

PMI-ACP Definitions

Actions undertaken to ensure that all relevant specifications, regulations, policies, or laws are followed and satisfied.

A

compliance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

PMI-ACP Definitions

Addressing underlying issues for disagreements and developing solutions that are acceptable to all parties involved.

A

conflict resolution

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

PMI-ACP Definitions

Practice where team members merge work results regularly and frequently to ensure that the completed product or product increment works as designed.

A

continuous integration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

PMI-ACP Definitions

Documented direction for executing the project work to bring expected future performance of the project work in line with the project management plan [PMI project management definition]

A

corrective action

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

PMI-ACP Definitions

An undisciplined software development method that gives developers autonomy and control over many project parameters (scheduling, quality, code style, etc.).

A

cowboy coding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

PMI-ACP Definitions

A group of development methodologies that focuses more on people than on the tools, processes, or architecture of a project. Practices are “stretched to fit” the needs of the project.

A

Crystal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

PMI-ACP Definitions

An area chart that shows the progress of each portion of a project life cycle. The work in each phase of a project is compiled in a cumulative line chart; comparing the distances between the lines on the chart shows the amount of work-in-process and the duration of work in each project phase.

A

cumulative flow diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

PMI-ACP Definitions

Ordering process that places a higher priority on user stories that provide the most value to customers (as opposed to assigning higher priority to stories that address cost, compliance, or market conditions).

A

customer-valued prioritization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

PMI-ACP Definitions

The amount of time it takes to complete an activity, including all delays and waiting times.

A

cycle time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

PMI-ACP Definitions

Scrum-specific term for the daily project meeting held to provide a status update to team members. Also known as daily stand-up or daily team status meeting.

A

daily scrum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

PMI-ACP Definitions

Daily Agile project meeting held to provide a status update to team members; also known as the daily scrum or daily huddle.

A

daily stand-up

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

PMI-ACP Definitions

Daily 15-minute project meetings held to provide status updates to team members; also known as daily stand-ups or daily scrums.

A

daily team status meeting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

PMI-ACP Definitions

All portions are complete (as agreed to by all parties) with no perceived changes or corrections necessary. The product can be used by the customer as intended.

A

done

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
# PMI-ACP Definitions An iterative and incremental software development methodology that stresses continuous user/customer involvement.
Dynamic Systems Development Method (DSDM)
26
# PMI-ACP Definitions A comparison of work planned to work completed and to costs incurred, at any specific point in time.
earned value management
27
# PMI-ACP Definitions An individual's ability to recognize, understand, and control his emotions, and to understand and relate to the emotions of others.
emotional intelligence
28
# PMI-ACP Definitions Errors that are not corrected or user stories that are not completed in an iteration.
escaped defects
29
# PMI-ACP Definitions A software development methodology that emphasizes simplicity, often employing pair programming and a cycle of frequent testing and feedback.
Extreme Programming (XP)
30
# PMI-ACP Definitions A model-driven, short-iteration approach to software development.
Feature-Driven Development (FDD)
31
# PMI-ACP Definitions A prediction of work duration that does not compensate for interruptions that may occur. Ideal time assumes that workers will be able to focus completely on the work, while real time accounts for work interruptions.
ideal time
32
# PMI-ACP Definitions Large display of critical team information that is continuously updated and located in a spot where the team can see it constantly; the term was introduced by Alistair Cockburn.
information radiator
33
# PMI-ACP Definitions Reviewing all change requests, approving changes, and managing changes to the deliverables, organizational process assets, project documents, and project management plan [PMI project management definition]
integrated change control
34
# PMI-ACP Definitions Any unique and verifiable product, result, or capability to perform a service that is produced during a process, phase, or project [PMI project management definition]
interim deliverable
35
# PMI-ACP Definitions The benefit of an investment divided by its cost, over a given time period.
internal rate of return
36
# PMI-ACP Definitions A time-delineated development cycle that produces a complete product that could be marketed or released to the customer.
iteration
37
# PMI-ACP Definitions Process in which the Agile team and product owner meet at the beginning of an iteration to determine which stories they will complete in the iteration.
iteration planning
38
# PMI-ACP Definitions An informational meeting in which team members demonstrate to stakeholders which stories were completed in the just-concluded iteration and begin to prepare for the next iteration.
iteration review
39
# PMI-ACP Definitions A story board that shows how many user stories are included in each phase of a project. Also known as a task board.
Kanban board
40
# PMI-ACP Definitions Software development based on lean methodology, which focuses on eliminating waste and unnecessary steps or processes that do not add value to the final product or service.
Lean Software Development
41
# PMI-ACP Definitions Discussions to explore options and reach an agreement.
negotiation
42
# PMI-ACP Definitions Financial technique that compares the value of an amount of money today to the value of the same amount at a date in the future.
net present value
43
# PMI-ACP Definitions Communication in the context of an Agile project that is picked up or absorbed by another team member, often through background hearing.
osmotic communication
44
# PMI-ACP Definitions A core Extreme Programming practice in which two team members work together at one workstation to develop a product.
pair programming
45
# PMI-ACP Definitions Fictional characters that represent the users of a product.
personas
46
# PMI-ACP Definitions An estimating technique based on Wideband Delphi in which teams use pre-labeled cards to express work estimates.
planning poker
47
# PMI-ACP Definitions The adjustment of processes and procedures to meet the needs of individual Agile projects.
process tailoring
48
# PMI-ACP Definitions the list of prioritized customer requirements that the team and product manager choose from to determine which customer needs will be met in an iteration. Also called the work queue.
product backlog
49
# PMI-ACP Definitions The person who represents the customer, user, or other stakeholders in an Agile project.
product manager
50
# PMI-ACP Definitions Scrum-specific term for the person who represents the customer, user, or other stakeholders in an Agile project.
product owner
51
# PMI-ACP Definitions A two-to-five-year vision that describes what you would like the product to do and when you would like it to be done. It generally includes additional details for the first 10-12 months.
product roadmap
52
# PMI-ACP Definitions The process of organizing a project at a high level and letting the details of the project evolve as the project develops.
progressive elaboration
53
# PMI-ACP Definitions A document issued by the project initiator or sponsor that formally authorizes the existence of a project, and provides the project manager with the authority to apply organizational resources to project activities
project charter
54
# PMI-ACP Definitions A prediction of work duration that takes into account interruptions that may occur.
real time
55
# PMI-ACP Definitions Improving a product or portion of a product without changing its behavior or functionality.
refactoring
56
# PMI-ACP Definitions Ranking system that categorizes user stories into simple, broad-based categories (such as "high, medium, and low" or "mandatory, critical, and optional").
relative prioritization
57
# PMI-ACP Definitions One or more iterations.
release
58
# PMI-ACP Definitions A larger product development cycle that includes multiple iterations and results in the transition of a finished product to production, operations, or the customer.
release cycle
59
# PMI-ACP Definitions Process in which an organization decides when it will release products to customers.
release planning
60
# PMI-ACP Definitions A meeting at the end of each iteration in which the team discusses how well it worked together to create the product and what changes they could make to improve in subsequent iterations.
retrospective
61
# PMI-ACP Definitions Comparison of money earned to money spent. Usually calculated for a given time period as (money earned minus money spent) divided by money spent.
return on investment
62
# PMI-ACP Definitions A line chart that tracks the amount of risk remaining in an iteration or release.
risk burndown graph
63
# PMI-ACP Definitions A calculation that helps a team quantitatively prioritize project risks.
risk score
64
# PMI-ACP Definitions A product backlog that takes risk factors into account in prioritizing user stories.
risk-adjusted backlog
65
# PMI-ACP Definitions A timeboxed experiment that a team runs to investigate the risks associated with a user story.
risk-based spike
66
# PMI-ACP Definitions A form of progressive elaboration planning where the work to be accomplished in the near term is planned in detail, while the work far in the future is planned at a relatively high level, but the detailed planning of the work to be performed within another one or two periods in the near future is done as work is being completed during the current period
rolling wave planning
67
# PMI-ACP Definitions Scrum-specific term for the potentially shippable result of an iteration. The potentially shippable result must be complete and able to be used by the customer with no additional adjustments or corrections. Also called a potentially shippable product.
sashimi
68
# PMI-ACP Definitions The sum of the products, services, and results to be provided as a project
scope
69
# PMI-ACP Definitions A lightweight, incremental framework for project management, used primarily for software development.
Scrum
70
# PMI-ACP Definitions Scrum-specific term for the person responsible for ensuring that the Scrum process is being followed and that the team is working at the highest level possible.
scrum master
71
# PMI-ACP Definitions Scrum-specific term for the 15-minute daily status meeting that coordinates activities across multiple teams.
scrum of scrums
72
# PMI-ACP Definitions A leader's ability to view his or her role as that of a facilitator and servant to the team, rather than as a manager or director of the team.
servant leadership
73
# PMI-ACP Definitions Scrum-specific term for the time-delineated development cycle that produces a complete product that could be marketed or released to the customer.
sprint
74
# PMI-ACP Definitions Scrum-specific term for the description of the tasks that the team will execute in an iteration to create a potentially shippable product.
sprint backlog
75
# PMI-ACP Definitions Scrum-specific term for the meeting at the end of each iteration in which the team discusses how well it worked together to create the product and what changes they could make to improve in subsequent iterations.
sprint retrospective
76
# PMI-ACP Definitions Scrum-specific term for the informational meeting in which team members demonstrate to stakeholders which stories were completed in the just-concluded iteration and begin to prepare for the next iteration.
sprint review
77
# PMI-ACP Definitions A narrative description of products, services, or results to be supplied
statement of work
78
# PMI-ACP Definitions A graphic visual display that summarizes the team's work.
story board
79
# PMI-ACP Definitions A graphic representation of the product backlog that shows the interdependencies of user stories. High-level activities are placed in order across the top of a page, and the tasks to complete those activities are placed below, with higher priority tasks placed closer to the activities.
story map
80
# PMI-ACP Definitions An estimate of the effort needed to satisfy a customer requirement. The size or complexity of each requirement is scaled in relation to other requirements;
story point
81
# PMI-ACP Definitions Visual elements that separate parts of a diagram.
swim lanes
82
# PMI-ACP Definitions A story board that shows how many user stories are included in each phase of a project (also known as a Kanban board).
task board
83
# PMI-ACP Definitions An area set aside (generally a common area and work areas) to house the team while it works on a project.
team space
84
# PMI-ACP Definitions The burden incurred during development due to poor design choices or hasty development.
technical debt
85
# PMI-ACP Definitions Development process where teams create tests before they develop products, then test the products and make corrections to ensure the tested product will pass the test.
Test-Driven Development (TDD)
86
# PMI-ACP Definitions Development process where teams create tests before they develop products.
test-first development
87
# PMI-ACP Definitions Agile development principles established by software leaders in 2001 that include favoring: Individuals and interactions over processes and tools; Working software over comprehensive documentation; Customer collaboration over contract negotiation; and Responding to change over following a plan.
The Agile Manifesto
88
# PMI-ACP Definitions A preset period of time that constrains how much can be attempted.
timebox
89
# PMI-ACP Definitions The process of setting time constraints or deadlines for iterations or projects.
timeboxing
90
# PMI-ACP Definitions Initial requirements stated as one or more sentences in the routine or business language of the user.
user stories
91
# PMI-ACP Definitions Quality-testing process that relies on external stakeholders to test products.
validation
92
# PMI-ACP Definitions Estimates of the value of user stories. Values of requirements are scaled in relation to each other
value points
93
# PMI-ACP Definitions An evaluation of all of the steps needed to bring a project from initiation to completion.
value stream analysis
94
# PMI-ACP Definitions A technique that shows all value-added and non-value-added process steps.
value stream mapping
95
# PMI-ACP Definitions Re-ordering the product backlog to ensure that those requirements with the greatest value are assigned the highest priorities and are considered first for inclusion in iterations.
value-based prioritization
96
# PMI-ACP Definitions The amount of work that a team can complete in a given period of time (usually one iteration). Only completed work is included; incomplete or partially completed work is not included.
velocity
97
# PMI-ACP Definitions Quality-testing process that relies on the project team to test products.
verification
98
# PMI-ACP Definitions A market research technique for establishing a detailed set of prioritized customer wants and needs.
Voice of the Customer (VOC)
99
# PMI-ACP Definitions Traditional, sequential project management that establishes customer requirements up front and then monitors and controls the project plan until completion.
Waterfall project management
100
# PMI-ACP Definitions An estimating technique in which team members jointly discuss user stories, then individually estimate the amount of work needed to complete the stories. If discrepancies occur, teams continue to develop work estimates until a consensus is reached.
Wideband Delphi
101
# PMI-ACP Definitions A web site used collaboratively by many users to share information of mutual interest.
wiki
102
# PMI-ACP Definitions Visual mock-ups of a product that developers use to verify design concepts and test functionality with users.
wireframes
103
# PMI-ACP Definitions A limit on the number of user stories that can be in a project phase at one time.
work-in-process (WIP) limits