PMI Lexicon Flashcards

(187 cards)

1
Q

A set of conditions that are met before deliverables are accepted.

A

Acceptance Criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A distinct, scheduled position of work performed during the course of a project.

A

Activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

An alphanumeric value assigned to each activity the enables classifying, sorting, and filtering.

A

Activity Code

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A unique alphanumeric value assigned to an activity and used to differentiate that activity from other activities.

A

Activity Identifier

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A phrase that names and describes an activity.

A

Activity Label

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The realized cost incurred for the work performed on an activity during a specific time period.

A

Actual Cost (AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project.

A

Analogous Estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

An activity where effort is allotted proportionality across certain discrete efforts and not divisible into discrete efforts.

A

Apportioned Effort

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A factor in the planning process considered to be true, real, or certain, without proof or demonstration.

A

Assumption

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.

A

Backward Pass

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The approved version of a work product that can be changed using formal change control procedures and is used as the basis for comparison to actual results.

A

Baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure.

A

Bottom-Up Estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The sum of all budgets established for the work to be performed.

A

Budget at Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

A process whereby modifications to documents, deliverables, or baselines associated with the project are identified, documented, approved, or rejected.

A

Change Control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A formally chartered group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project, and for recording and communicating such decisions.

A

Change Control Board

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.

A

Change Control System

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

A formal proposal to modify a document, deliverable, or baseline.

A

Change Request

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

A numbering system used to uniquely identify each component of the work breakdown structure.

A

Code of Accounts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

A component of the project, program, or portfolio management plan that describes how, when, and by whom information will be administered and disseminated.

A

Communications Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

A collection of procedures used to track project artifacts and monitor and control changes to these artifacts.

A

Configuration Management System

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

A factor that limits the options for managing a project, program, portfolio, or process.

A

Constraint

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

A document describing actions that the project team can take if predetermined trigger conditions occur.

A

Contingency Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Time or money allocated in the schedule or cost baseline for known risks with active response strategies.

A

Contingency Reserve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

A management control point where scope, budget, actual cost, and schedule are integrated and compared to earned value for performance measurement.

A

Control Account

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
An intentional activity that realigns the performance of the project work with the project management plan.
Corrective Active
26
The approved version of work page cost estimates and contingency reserve that can be changed using formal change control procedures and is used as the basis for comparison to actual results.
Cost Baseline
27
A component of a project or program management plan that describes how costs will be planned, structured, and controlled.
Cost Management Plan
28
A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Cost Performance Index
29
The amount of budget deficit or surplus at a given point in time, expressed as the difference between the earned value and the actual cost.
Cost Variance
30
A schedule compression technique used to shorten the schedule duration for the last incremental cost by adding resources.
Crashing
31
A schedule method that allowed the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
Critical Chain Method
32
The sequence of activities that represents the longest path through a project, which determines the shortest possible duration.
Critical Path
33
Any activity on the critical path in a project schedule.
Critical Path Activity
34
A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.
Critical Path Method
35
A point in time when the status of the project is recorded.
Data Date
36
A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
Decision Tree Analysis
37
A technique used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts.
Decomposition
38
An intentional activity to modify a nonconforming product or product component.
Defect Repair
39
Any unique and verifiable product, result, or capability to perform a service that is produced to complete a process, phase, or project.
Deliverable
40
An activity that can be planned and measured and that yields a specific output.
Discrete Effort
41
The total number of work periods required to complete an activity or work breakdown structure component, expressed in hours, days, or weeks.
Duration
42
In the critical path method, the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic, the data date, and any schedule constraints.
Early Finish Date
43
In the critical path method, the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic, the data date, and any schedule constraints.
Early Start Date
44
The measure of work performed expressed in terms of the budget authorized for that work.
Earned Value
45
A methodology that combines scope, schedule, and resource measurements to asses project performance and progress.
Earned Value Management
46
The number of labor units required to complete a schedule activity or work breakdown structure component, often expressed in hours, days, or weeks.
Effort
47
Conditions, not under the immediate control of the team, that influence, constrain, or direct the project, program, or portfolio.
Enterprise Environmental Factors
48
The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Estimation at Completion (EAC)
49
The expected cost to finish all the remaining project work.
Estimate to Complete (ETC)
50
A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Fast Tracking
51
A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Finish-to-Finish
52
A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Finish-to-Start
53
method of estimating earned value in which a specific percentage of the budget value of a work package is assigned to the start milestone and the remaining percentage is assigned when the work package is complete.
Fixed Formula Method
54
A critical path method technique for calculating the early start and finish dates by working forward through the schedule model from the project start date or a given point in time.
Forward Pass
55
The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
Free Float
56
An organizational structure in which staff is grouped by areas of specialization and the project manager has limited authority to assign work and apply resources.
Functional Organization
57
A bar chart of schedule information where activities are listed on the vertical axis, dates are shown on the horizontal axis, and activity durations are shown as horizontal bars placed according to start and finish dates.
Gantt Chart
58
The amount of time whereby a successor will be delayed with respect to a predecessor activity.
Lag
59
In the critical path method, the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic, the project completion date, and any schedule constraints.
Late Finish Date
60
In the critical path method, the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic, the project completion date, and any schedule constraints.
Late Start Date
61
The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Lead
62
The knowledge gained during a project which shows how project events were addressed or schedule be addressed in the future for the purpose of improving future performance.
Lessons Learned
63
An activity that does not produce definitive end products and is measured by the passage of time.
Level of Effort
64
A dependency between two activities or between an activity and a milestone.
Logical Relationship
65
Time or money that management sets aside in additional to the schedule or cost baseline and releases for unforeseen work that is within the scope of project.
Management Reserve
66
An organizational structure in which the project manager shares authority with the functional manager temporarily to assign work and apply resources.
Matrix Organization
67
A significant point or event in a project, program, or portfolio.
Milestone
68
A type of schedule that presents milestones with planned dates.
Milestone Schedule
69
An estimate of the most probably activity duration that takes into account all of the known variables that could affect performance.
Most Likely Duration
70
An activity with a total float that is deemed to be low based on expert judgment.
Near-Critical Activity
71
A sequence of activities with low float which, if exhausted, becomes a critical path sequence for the project.
Near-Critical Path
72
All activity dependencies in a project schedule network diagram.
Network Logic
73
A sequence of activities connected by logical relationships in a project schedule network diagram.
Network Path
74
A point at which dependency lines connect on a schedule network diagram.
Node
75
A risk that would have a positive effect on one or more project objective.
Opportunity
76
An estimate of the shortest activity duration that takes into account all of the known variables that count affect performance.
Optimistic Duration
77
A hierarchical representation of the project organization, which illustrates the relationship between project activities and the organizational units that will perform those activities.
Organizational Breakdown Structure
78
A structural, cultural, technological, or human-resource practice that the performing organization can use to achieve strategic objectives.
Organizational Enabler
79
Plans, processes, policies, procedures, and knowledge bases specific to and used by the performing organization.
Organizational Process Assets
80
A framework in which portfolio, program, and project management are integrated with organizational enablers in order to achieve strategic objectives.
Organizational Project Management
81
The level of an organization's ability to deliver the desired strategic outcomes in a predictable, controllable, and reliable manner.
Organizational Project Management Maturity
82
An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
Parametric Estimating
83
A relationship in which a schedule activity has more than one predecessor.
Path Convergence
84
A relationship in which a schedule activity has more than one successor.
Path Divergence
85
An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.
Percent Complete
86
Integrated scope, schedule, and cost baselines used for comparison to manage, measure, and control project execution.
Performance Measurement Baseline
87
An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Performing Organization
88
An estimate of the longest activity duration that takes into account all of the known variables that count affect performance.
Pessimistic Duration
89
A review at the end of a phase in which a decision is made to continue to the next phase, to continue with medication, or to end a project or program.
Phase Gate
90
The authorized budget assigned to scheduled work.
Planned Value
91
Projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives.
Portfolio
92
The process of optimizing the mix of portfolio component to further the strategic objectives of the organization.
Portfolio Balancing
93
A document issued by a sponsor that authorizes and specifies the portfolio structure and links the portfolio to the organization's strategic objectives.
Portfolio Charter
94
The centralized management of one or more portfolios to achieve strategic objectives.
Portfolio Management
95
A document that specifies how a portfolio will be organized, monitored, and controlled.
Portfolio Management Plan
96
The person or group assigned by the performing organization to establish, balance, monitor, and control portfolio components in order to achieve strategic business objectives.
Portfolio Manager
97
A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
Precedence Diagramming Method
98
An activity that logically comes before a dependent activity in a schedule.
Predecessor Activity
99
An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
Preventive Action
100
A grid for mapping the probability of occurrence of each risk and its impact on the project objectives if that risk occurs.
Probability and Impact Matrix
101
A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Procurement Management Plan
102
The series of phases that represent the evolution of a product, from concept through delivery, growth, maturity, and to retirement.
Product Life Cycle
103
Related project, subsidiary programs, and program activities managed in a coordinated manner to obtain benefits not available from managing them individually.
Program
104
A document issued by a sponsor that authorizes the program management team to use organizational resources to execute the program and links the program to the organization's strategic objectives.
Program Charter
105
A technique used to estimate project duration through a weighted average of optimistic, pessimistic, and most likely activity durations when there is uncertainty with the individual activity estimates.
Program Evaluation and Review Technique (PERT)
106
The application of knowledge, skills, and principles to a program to achieve the program objectives and to obtain the benefits and control not available by managing program components individually.
Program Management
107
A management structure that standardizes the program-related governance processes and facilitates the sharing of resources, methodologies, tools, and techniques.
Program Management Office
108
A document that integrates the program's subsidiary plans and established the management controls and overall plan for integrating and managing the program's individual components.
Program Management Plan
109
The person authorized by the performing organization to lead the team or teams responsible for achieving program objectives.
Program Manager
110
The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
Progressive Elaboration
111
A temporary endeavor undertaken to create a unique project, service, or result.
Project
112
The sum of work package cost estimates, contingency reserve, and management reserve.
Project Budget
113
A calendar that identifies working days and shifts that are available for scheduled activities.
Project Calendar
114
A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Project Charter
115
An organizational structure in which the project manager has full authority to assign work and apply resources.
Projectized Organization
116
The series of phases that a project passes through from its start to completion.
Project Life Cycle
117
The application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.
Project Management
118
A management structure that standardizes the project-related governance processes and facilitates the sharing of resources, methodologies, tools, and techniques.
Project Management Office
119
The document that describes how the project will be executed, monitored and controlled, and closed.
Project Management Plan
120
The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.
Project Manager
121
A collection of logically related project activities that culminates in the completion of one or more deliverables.
Project Phase
122
An output of a schedule model that presents linked activities with planned dates, durations, milestones, and resources.
Project Schedule
123
A graphical representation of the logical relationships among the project schedule activities.
Project Schedule Network Diagram
124
The work performed to deliver a product, service, or result with the specified features and functions.
Project Scope
125
The description of the project scope, major deliverables, assumptions, and constraints.
Project Scope Statement
126
A component of the project or program management plan that describes how an organization's policies, procedures, and guidelines will be implemented to achieve the quality objectives.
Quality Management Plan
127
A component of the project or program management plan that describes how requirements will be analyzed, documented, and managed.
Requirements Management Plan
128
A grid that links product requirements from their origin to the deliverables that satisfy them.
Requirements Traceability Matrix
129
The risk that remains after risk responses have been implemented.
Residual Risk
130
A hierarchical representation of resources by category and type.
Resource Breakdown Structure
131
A calendar that identifies the working days and shifts upon which each specific resource is available.
Resource Calendar
132
A resource optimization technique in which adjustments are made to the project schedule to optimize the allocation of resources and which may affect critical path.
Resource Leveling
133
A component of the project management plan that describes how project resources are acquired, allocated, and controlled.
Resource Management Plan
134
A technique in which activity start and finish dates are adjusted to balance demand for resources with the available supply.
Resource Optimization Technique
135
A resource optimization technique in which free and total float are used without affecting the critical path.
Resource Smoothing
136
A grid that shows the project resources assigned to each work package.
Responsibility Assignment Matrix
137
An uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives.
Risk
138
A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Risk Acceptance
139
The degree of uncertainty an organization or individual is willing to accept in anticipation of a reward.
Risk Appetite
140
A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Risk Avoidance
141
A hierarchical representation of potential sources of risk.
Risk Breakdown Structure
142
A group of potential causes of risk.
Risk Category
143
A risk response strategy whereby the project team acts to increase the probability of occurrence or impact of an opportunity.
Risk Enhancement
144
A risk response strategy whereby the project team acts to ensure that an opportunity occurs.
Risk Exploiting
145
An aggregate measure of the potential impact of al risks at any given point in time in a project, program, or portfolio.
Risk Exposure
146
A component of the project, program, or portfolio management plan that describes how risk management activities will be structured and performed.
Risk Management Plan
147
A risk response strategy whereby the project team acts to decrease the probability of occurrence or impact of a threat.
Risk Mitigation
148
The person responsible for monitoring the risk and for selecting and implementing an appropriate risk response strategy.
Risk Owner
149
A repository in which outputs of risk management processes are recorded.
Risk Register
150
A risk response strategy whereby the project team allocates ownership of an opportunity to a third party who is best able to capture the benefit of that opportunity.
Risk Sharing
151
The measure of acceptable variation around an objective that reflects the risk appetite of the organization and stakeholders.
Risk Threshold
152
A risk response strategy whereby the project team shifts the impact of a threat to a third party, together with the ownership of the response.
Risk Transference
153
An iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future if planned at a higher level.
Rolling Wave Planning
154
The approved version of a schedule model that can be changed using formal change control procedures and is used as the basis for comparison to actual results.
Schedule Baseline
155
A technique used to shorten the schedule duration whiteout reducing the project scope.
Schedule Compression
156
A component of the project or program management plan that establishes the criteria and the activities for developing, monitoring and controlling the schedule.
Schedule Management Plan
157
A representation of the plan for executing the project's activities, including durations, dependencies, and other planning information, used to produce a project schedule along with other scheduling artifacts.
Schedule Model
158
A process used to investigate or analyze the output of the schedule model in order to optimize the schedule.
Schedule Model Analysis
159
A technique to identify early and late start dates, as well as early and late finish dates, for the uncompleted portions of project activities.
Schedule Network Analysis
160
A measure of schedule efficiency expressed as the ratio of earned value to planned value.
Schedule Performance Index (SPI)
161
A measure of schedule performance expressed as the difference between the earned value and planned value.
Schedule Variance (SV)
162
The approved version of a scope statement, work breakdown structure, and its associated WBS dictionary that can be changed using formal change control procedures and is used as the basis for comparison to actual results.
Scope Baseline
163
The uncontrolled expansion to product or project scope without adjustments to time, cost, and resources.
Scope Creep
164
A component of the project or program management plan that describes how the scope will be defined, developed, monitored, controlled, and validated.
Scope Management Plan
165
A technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
S-Curve Analysis
166
A risk that arises as a direct result of implementing a risk response.
Secondary Risk
167
An individual or a group that provides resources and support for the project, program, or portfolio, and is accountable for enabling success.
Sponsor
168
A component of the resource management plan that describes when and how team members will be acquired and how long they will be needed.
Staffing Management Plan
169
An individual, group, or organization that may affect, be affected by, or perceive itself to be affected by a decision, activity, or outcome of a project, program, or portfolio.
Stakeholder
170
A component of the project or project management plan that identifies the strategies and actions required to promote productive involvement of stakeholders in project or program decision making and execution.
Stakeholder Engagement Plan
171
A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Start-to-Finish
172
A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Start-to-Start
173
A dependent activity that logically comes after another activity in a schedule.
Successor Activity
174
A group of related schedule activities aggregated and displayed as a single activity.
Summary Activity
175
A risk that would have a negative effect on one or more project objectives.
Threat
176
A technique used to estimate cost or duration by applying an average or weighted average of optimistic, pessimistic, and most likely estimates when there is uncertainty with the individual activity estimates.
Three-Point Estimating
177
A measure of the cost performance that is achieved with the remaining resources in order to met a specified management goal, expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
To-Complete Performance Index (TCPI)
178
The amount of time that a schedule activity can be delayed or extended from its early start date without dealing the project finish date or violating a schedule constraint.
Total Float
179
An event or situation that indicates that a risk is about to occur.
Trigger Condition
180
A technique for determining the. cause and degree of difference between the baseline and actual performance.
Variance Analysis
181
A projection of the amount of budget deficit or surplus, expressed as the difference between the budget at completion and the estimate at completion.
Variance at Completion (VAC)
182
A document that provides detailed deliverable, activity, and schedule information about each component in the work breakdown structure.
WBS Dictionary
183
A method of estimating earned value in which the budget value of a work package is divided into measurable segments, each ending with a milestone that is assigned a weighted budget value.
Weighted Milestone Method
184
The process of evaluating scenarios in order to predict their effect on project objectives.
What-If Scenario Analysis
185
An immediate and temporary response to an issue for which a prior response had not been planned or was not effective.
Workaround
186
A hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables.
Work Breakdown Structure (WBS)
187
The work defined at the lowest level of the work breakdown structure for which cost and duration as estimated and managed.
Work Package