PMI Lexicon & PMBOK Glossary Flashcards

PMI Lexicon Version 3.2 published September 2017 PMI PMBOK Guide Seventh Edition (426 cards)

1
Q

Acceptance Criteria

A

A set of conditions that are met before deliverables are accepted.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Accuracy

A

Within the quality management system, accuracy is an assessment of correctness

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Activity

A

A distinct, scheduled portion of work performed during the course of a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Activity Code

A

An alphanumeric value assigned to each activity. Enabled classifying, sorting, and filtering.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Activity Identifier

A

A unique alphanumeric value assigned to an activity. Used to differentiate that activity from other activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Activity Label

A

A phrase that names and describes an activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Activity List

A

A documented tabulation of schedule activities that shows the activity description, activity identifier, and a sufficiently detailed scope of work description so project team members understand what work is to be performed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Actual Cost (AC)

A

The realized cost incurred for the work performed on an activity during a specific time period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Adaptive Approach

A

A development approach in which the requirements are subject to a high level of uncertainty and volatility and are likely to change throughout the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Affinity Diagram

A

A diagram that shows large numbers of ideas classified into groups for review and analysis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Affinity Grouping

A

The process of classifying items into similar categories or collections on the basis of their likeness.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Agile

A

A term used to describe a mindset of values and principles as set forth in the Agile Manifesto.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Alternatives Analysis

A

A method used to evaluate identified options in order to select the options or approaches to use to perform the work of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Ambiguity

A

A state of being unclear, having difficulty in identifying the cause of events, or having multiple options from which to choose.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Analogous Estimating

A

A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Apportioned Effort

A

An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts.

Apportioned effort is one of three earned value management (EVM) types of activities used to measure work performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Artifact

A

A template, document, output, or project deliverable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Assumption

A

A factor in the planning process considered to be true, real, or certain without proof of demonstration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Assumption and Constraint Analysis

A

An assessment that ensures assumptions and constraints are integrated into the project plans and documents, and that there is consistency among them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Assumption Log

A

A project document used to record all assumptions and constraints throughout the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Authority

A

The right to apply project resources, expend funds, make decisions, or give approvals.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Backlog

A

An ordered list of work to be done

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Backlog Refinement

A

Progressive elaboration of the content in the backlog and (re)prioritization of it to identify the work that can be accomplished in an upcoming iteration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Backward Pass

A

A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Baseline
The approved version of a work product used as the basis for comparison to actual results. Can be changed using the formal change control procedures.
26
Basis of Estimates
Supporting documentation outlining the details used in establishing project estimates such as assumptions, constraints, level of detail, ranges, and confidence levels.
27
Benchmarking
The comparison of actual or planned products, processes, and practices to those of comparable organizations to identify best practices, generate ideas for improvement, and provide a basis for measuring performance.
28
Benefits Management Plan
The documented explanation defining the processes for creating, maximizing, and sustaining the benefits provided by a project or program.
29
Bid Documents
All documents used to solicit information, quotations, or proposals from prospective sellers.
30
Bidder Conference
The meetings with prospective sellers prior to the preparation of a bid or proposal to ensure all prospective vendors have a clear and common understanding of the procurement. Also known as contractor conferences, vendor conferences, or pre-bid conferences.
31
Bottom-Up Estimating
A method of estimating project duration or cost by aggregating the estimates of the lower-level component of the work breakdown structure (WBS).
32
Budget
The approved estimate for the project or any work breakdown structure (WBS) component or any schedule activity.
33
Budget at Completion (BAC)
The sum of all budgets established for the work to be performed.
34
Burn Chart
A graphical representation of the work remaining in a timebox or the work completed toward the release of a product or project deliverable.
35
Business Case
A value proposition for a proposed project that may include financial and nonfinancial benefits.
36
Business Model Canvas
A one-page, visual summary that describes the value proposition, infrastructure, customers, and finances. These are often used in Lean Startup situations.
37
Business Value
The net quantifiable benefit derived from a business endeavor that may be tangible, intangible, or both.
38
Cadence
A rhythm of activities conducted throughout the project.
39
Cause-and-Effect Diagram
A visual representation that helps trace an undesirable effect back to its root cause.
40
Change
A modification to any formally controlled deliverable, project management plan component, or project document.
41
Change Control
A process whereby modifications to documents, deliverables, or baselines associated with the project are identified, documented, approved, or rejected.
42
Change Control Board (CCB)
A formally chartered group responsible for reviewing, evaluating, approving, delaying, or rejecting changed to the project, and for recording and communicating such decisions.
43
Change Control Plan
A component of the project management plan that establishes the change control board, documents the extent of its authority, and describes how the change control system will be implemented.
44
Change Control System
A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
45
Change Log
A comprehensive list of changes submitted during the project and their current status.
46
Change Management
A comprehensive, cyclic, and structured approach for transitioning individuals, groups, and organizations from a current state to a future state with intended business benefits.
47
Change Request
A formal proposal to modify a document, deliverable, or baseline.
48
Check Sheet
A tally sheet that can be used as a checklist when gathering data.
49
Closing Process Group
The process(es) performed to formally complete or close a project, phase, or contract.
50
Code of Accounts
A numbering system used to uniquely identify each component of the work breakdown structure (WBS).
51
Communications Management Plan
A component of the project, program, or portfolio management plan that described how, when, and by whom information will be administered and disseminated.
52
Complexity
A characteristic of a program or project or its environment that is difficult to manage due to human behavior, system behavior, and ambiguity.
53
Configuration Management System
A collection of procedures used to track project artifacts and monitor and control changes to these artifacts.
54
Confirmation Bias
A type of cognitive bias that confirms preexisting beliefs or hypotheses.
55
Conformance
The degree to which the results meet the set quality requirements.
56
Constraint
A factor that limits the options for managing a project, program, portfolio, or process.
57
Contingency
An event or occurrence that could affect the execution of the project, which may be accounted for with a reserve.
58
Contingency Plan
A document describing actions that the project team can take if predetermined trigger conditions occur.
59
Contingency Reserve
Time or money allocated in the schedule or cost baseline for known risks with active response strategies.
60
Continuous Delivery
The practice of delivering feature increments immediately to customers, often through the use of small batches of work and automation technology.
61
Contract
A mutually binding agreement that obligates the seller to provide the specified product, service, or result and obligates the buyer to pay for it.
62
Control
The process of comparing actual performance with planned performance, analyzing variances, assessing trends to effect process improvements, evaluating possible alternatives, and recommending appropriate corrective action as needed.
63
Control Account
A management control point where scope, budget, actual cost, and schedule are integrated and compared to earned value for performance measurement.
64
Control Chart
A graphic display of process data over time and against established control limits, which has a centerline that assists in detecting a trend of plotted values toward either control limit.
65
Corrective Action
An intentional activity that realigns the performance of the project work with the project management plan.
66
Cost Baseline
The approved version of work package cost estimates and contingency reserve used as the basis for comparison to actual results. Can be changed using formal change control procudures.
67
Cost-Benefit Analysis
A financial analysis method used to determine the benefits provided by a project against its costs.
68
Cost Management Plan
A component of a project or program management plan that describes how costs will be planned, structured, and controlled.
69
Cost of Quality (COQ)
All costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraisal of the product or service for conformance to requirements, and failure to meet requirements.
70
Cost Performance Index (CPI)
A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
71
Cost Plus Award Fee Contract (CPAF)
A category of contract that involves payments to the seller for all legitimate actual costs incurred for completed work, plus an award fee representing seller profit.
72
Cost Plus Fixed Fee Contract (CPFF)
A type of cost-reimbursable contract where the buyer reimburses the seller for the seller’s allowable costs (allowable costs are defined by the contract) plus a fixed amount of profit (fee).
73
Cost Plus Incentive Fee Contract (CPIF)
A type of cost-reimbursable contract where the buyer reimburses the seller for the seller’s allowable costs (allowable costs are defined by the contract), and the seller earns its profit if it meets defined performance criteria.
74
Cost-Reimbursable Contract
A type of contract involving payment to the seller for the seller’s actual costs, plus a fee typically representing the seller’s profit.
75
Cost Variance (CV)
The amount of budget deficit or surplus at a given point in time expressed as the difference between the earned value and the actual cost.
76
Crashing
A schedule compression technique used to shorten the schedule duration for the least incremental cost by adding resources.
77
Criteria
Standards, rules, or tests on which a judgment or decision can be based or by which a product, service, result, or process can be evaluated.
78
Critical Chain Method
A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
79
Critical Path
The sequence of activities that represents the longest path through a project, which determines the shortest possible duration.
80
Critical Path Activity
Any activity on the critical path in a project schedule.
81
Critical Path Method (CPM)
A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths withing the schedule model.
82
Cumulative Flow Diagram (CFD)
A chart indicating features completed over time, features in other states of development, and those in the backlog.
83
Cycle Time
The total elapsed time from the start of a particular activity or work item to its completion.
84
Cycle Time Chart
A diagram that shows the average cycle time of the work items completed over time.
85
Daily Standup
A brief, daily collaboration meeting in which the team reviews progress from the previous day, declares intentions for the current day, and highlights any obstacles encountered or anticipated.
86
Dashboard
A set of charts and graphs showing progress or performance against important measures of the project.
87
Data Date
A point in time when the status of the project is recorded.
88
Data Gathering and Analysis Methods
Methods used to collect, assess, and evaluate data and information to gain a deeper understanding of a situation.
89
Decision Tree Analysis
A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
90
Decomposition
A technique used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts.
91
Defect Repair
An intentional activity to modify a nonconforming product or product component.
92
Definition of Done (DoD)
A checklist of all the criteria required to be met so that a deliverable can be considered ready for customer use.
93
Deliverable
Any unique and verifiable product, result, or capability to perform a service that is produced to complete a process, phase, or project.
94
Delivery Performance Domain
The performance domain that addresses activities and functions associated with delivering the scope and quality that the project was undertaken to achieve.
95
Development Approach
A method used to create and evolve the product, service, or result during the project life cycle, such as a predictive, iterative, incremental, agile, or hybrid method.
96
Development Approach and Life Cycle Performance Domain
The performance domain that addresses activities and functions associated with the development approach, cadence, and life cycle phases of the project.
97
DevOps
A collection of practices for creating a smooth flow of deliveries by improving collaboration between development and operations staff.
98
Digital Product
A product or service that is delivered, used, and stored in an electronic format.
99
Discrete Effort
An activity that can be planned and measured and that yields a specific output. Discrete Effort is one of three earned value management (EVM) types of activities used to measure work performance.
100
Discretionary Dependency
A relationship that is based on best practices or project preferences.
101
Duration
The total number of work periods required to complete an activity or work breakdown structure (WBS) component. Expressed in hours, days, or weeks.
102
Early Finish Date
In the critical path method, the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic, the data date, and any schedule constraints.
103
Earned Value (EV)
The measure of work performed expressed in terms of the budget authorized for that work.
104
Earned Value Analysis (EVA)
An analysis method that uses a set of measures associated with scope, schedule, and cost to determine the cost and schedule performance of a project.
105
Earned Value Management
A methodology that combines scope, schedule, and resource measurements to assess project performance and progress.
106
Effort
The number of labor units required to complete a schedule activity or work breakdown structure (WBS) component. Often expressed in hours, days, or weeks.
107
Emotional Intelligence
The ability to identify, assess, and manage the personal emotions of oneself and other people, as well as the collective emotions of groups of people.
108
Enterprise Environmental Factors (EEF)
Conditions not under immediate control of the team that influence, constraint, or direct the project, program, or portfolio.
109
Epic
A large, related body of work intended to hierarchically organize a set of requirements and deliver specific business outcomes.
110
Estimate
A quantitative assessment of the likely amount or outcome of a variable, such as project costs, resources, effort, or durations.
111
Estimate at Completion (EAC)
The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
112
Estimate to Complete (ETC)
The expected cost to finish all the remaining project work.
113
Estimating Methods
Methods used to develop an approximation of work, time, or cost on a project.
114
Executing Process Group
Those processes performed to complete the work defined in the project management plan to satisfy the project requirements.
115
Expected Monetary Value (EMV)
The estimated value of an outcome expressed in monetary terms.
116
Explicit Knowledge
Knowledge that can be codified using symbols such as words, numbers, and pictures.
117
External Dependency
A relationship between project activities and non-project activities.
118
Fast Tracking
A schedule compression technique in which activities or phrases normally done in sequence are performed in parallel for at least a portion of their duration.
119
Feature
A set of related requirements or functionalities that provides value to an organization.
120
Finish-to-Finish (FF)
A logical relationship in which a successor activity cannot finish until a predecessor activity has finished. A must be completed for B to be completed.
121
Finish-to-Start (FS)
A logical relationship in which a successor activity cannot start until a predecessor activity has finished. A must be completed for B to be started.
122
Firm Fixed Price Contract (FFP)
A type of fixed-price contract where the buyer pays the seller a set amount (as defined by the contract), regardless of the seller’s costs.
123
Fixed Duration
A type of activity where the length of time required to complete the activity remains constant regardless of the number of people or resources assigned to the activity.
124
Fixed Formula Method
A method of estimating earned value (EV). A specified percentage of the budget value of a work package is assigned to the start milestone, and the remaining percentage is assigned when the work package is complete.
125
Fixed-Price Contract
An agreement that sets the fee that will be paid for a defined scope of work regardless of the cost or effort to deliver it.
126
Fixed Price Incentive Fee Contract (FPIF)
A type of contract where the buyer pays the seller a set amount (as defined by the contract), and the seller can earn an additional amount if the seller meets defined performance criteria
127
Fixed Price with Economic Price Adjustment Contract (FPEPA)
A fixed-price contract, but with a special provision allowing for predefined final adjustments to the contract price due to changed conditions, such as inflation changes, or cost increases (or decreases) for specific commodities.
128
Flow
The measure of how efficiently work moves through a given process or framework.
129
Flowchart
The depiction in a diagram format of the inputs, process actions, and outputs of one or more processes within a system.
130
Forecast
An estimate or prediction of conditions and events in the project’s future based on information and knowledge available at the time of the forecast.
131
Forward Pass
A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
132
Free Float
The amount of time that schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
133
Functional Organization
An organizational structure in which staff are grouped by areas of specialization. The project manager has limited authority to assign work and apply resources.
134
Function Point
An estimate of the amount of business functionality in an information system, used to calculate the functional size measurement of a software system.
135
Gantt Chart
A bar chart of schedule information. Activities are listed on the vertical axis. Dates are on the horizontal axis. Activity durations are shown as horizontal bars placed according to start and finish dates.
136
Governance
The framework for directing and enabling an organization through its established policies, practices, and other relevant documentation.
137
Grade
A category or rank used to distinguish items that have the same functional use but do not share the same requirements for quality.
138
Hierarchy Chart
A chart that begins with high-level information that is progressively decomposed into lower levels of detail.
139
Histogram
A bar chart that shows the graphical representation of numerical data.
140
Hybrid Approach
A combination of two or more agile and nonagile elements, having a nonagile end result.
141
Impact Mapping
A strategic planning method that serves as a visual roadmap for the organization during product development.
142
Impediment
An obstacle that prevents the team from achieving its objectives. Also known as a Blocker.
143
Incremental Approach
An adaptive development approach in which the deliverable is produced successively, adding functionality until the deliverable contains the necessary and sufficient capability to be considered complete.
144
Indefinite Delivery Indefinite Quantity (IDIQ)
A contract that provides for an indefinite quantity of goods or services, with a stated lower and upper limit, within a fixed time period.
145
Influence Diagram
A graphical representation of situations showing causal influences, time ordering of events, and other relationships among variables and outcomes.
146
Information Radiator
A visible, physical display that provides information to the rest of the organization, enabling timely knowledge sharing.
147
Initiating Process Group
Those processes performed to define a new project or a new phase of an existing project by obtaining authorization to start the project or phase.
148
Internal Dependency
A relationship between two or more project activities.
149
Interpersonal Skills
Skills used to establish and maintain relationships with other people.
150
Issue
A current condition or situation that may have an impact on the project objectives.
151
Issue Log
A project document where information about issues is recorded and monitored.
152
Iteration
A timeboxed cycle of development on a product or deliverable in which all of the work that is needed to deliver value is performed.
153
Iteration Plan
A detailed plan for the current iteration.
154
Iteration Planning
A meeting to clarify the details of the backlog items, acceptance criteria, and work effort required to meet an upcoming iteration commitment.
155
Iteration Review
A meeting held at the end of an iteration to demonstrate the work that was accomplished during the iteration.
156
Iterative Approach
A development approach that focuses on an initial, simplified implementation then progressively elaborates adding to the feature set until the final deliverable is complete.
157
Kanban Board
A visualization tool that shows work in progress to help identify bottlenecks and overcommitments, thereby allowing the team to optimize the workflow.
158
Kickoff Meeting
A gathering of team members and other key stakeholders at the outset of a project to formally set expectations, gain a common understanding, and commence work.
159
Knowledge
A mixture of experience, values and beliefs, contextual information, intuition, and insight that people use to make sense of new experiences and information.
160
Lag
The amount of time whereby a successor activity will be delayed with respect to a predecessor activity.
161
Last Responsible Moment
The concept of deferring a decision to allow the team to consider multiple options until the cost of further delay would exceed the benefit.
162
Late Finish Date
In the critical path method, the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic, the project completion date, and any schedule constraints.
163
Late Start Date
In the critical path method, the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic, the project completion date, and any schedule constraints.
164
Lead
The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
165
Lead Time
The time between a customer request and the actual delivery.
166
Lead Time Chart
A diagram showing the trend over time of the average lead time of the items completed in work.
167
Lean Startup Canvas
A one-page template designed to communicate a business plan with key stakeholders in an efficient and effective manner.
168
Lessons Learned
The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance.
169
Lessons Learned Register
A project document used to record knowledge gained during a project, phase, or iteration so that it can be used to improve future performance for the team and the organization
170
Level of Effort
An activity that does not produce definitive end product and is measured by the passage of time Level of Effort is one of three earned value management (EVM) types of activities used to measure work performance.
171
Life Cycle Assessment (LCA)
A tool used to evaluate the total environmental impact of a product, process, or system.
172
Log
A document used to record and describe or denote selected items identified during execution of a process or activity. Usually used with a modifier, such as issue, change, or assumption.
173
Logical Relationship
A dependency between two activities or between an activity and a milestone.
174
Make-or-Buy Analysis
The process of gathering and organizing data about product requirements and analyzing them against available alternatives including the purchase or internal manufacture of the product.
175
Management Reserve
Time or money that management sets aside in addition to the schedule or cost baseline and releases for unforeseen work that is within the scope of the project.
176
Mandatory Dependency
A relationship that is contractually required or inherent in the nature of the work.
177
Matrix Organization
An organizational structure in which the project manager temporarily shares authority with the functional manager to assign work and apply resources. Weak Matrix: The Functional Manager has more authority and control over the project team. Project Manager often seen as a coordinator or expeditor. Strong Matrix: The Project Manager has more authority and control over the project team. Project Manager is seen as the primary authority figure.
178
Measurement Performance Domain
The performance domain that addresses activities and functions associated with assessing project performance and taking appropriate actions to maintain acceptable performance.
179
Measures of Performance
Measures that characterize physical or functional attributes relating to system operation.
180
Method
A means for achieving an outcome, output, result, or project deliverable.
181
Methodology
A system of practices, techniques, procedures, and rules used by those who work in a discipline.
182
Metric
A description of a project or product attribute and how to measure it.
183
Milestone
A significant point or event in a project, program, or portfolio.
184
Milestone Schedule
A type of schedule that presents milestones with planned dates.
185
Minimum Viable Product (MVP)
A concept used to define the scope of the first release of a solution to customers by identifying the fewest number of features or requirements that would deliver value.
186
Modeling
Creating simplified representations of systems, solutions, or deliverables, such as prototypes, diagrams, or storyboards
187
Monitor
Collect project performance data, produce performance measures, and report and disseminate performance information.
188
Monitoring and Controlling Process Group
Those processes required to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate corresponding changes.
189
Monte Carlo Simulation
A method of identifying the potential impacts of risk and uncertainty using multiple iterations of a computer model to develop a probability distribution of a range of outcomes that could result from a decision or course of action.
190
Mood Chart
A visualization chart for tracking moods or reactions to identify areas for improvement.
191
Most Likely Duration
An estimate of the most probably activity duration that takes into account all the known variables that could affect performance.
192
Multipoint Estimating
A method used to estimate cost or duration by applying an average or weighted average of optimistic, pessimistic, and most likely estimates when there is uncertainty with the individual activity estimates.
193
Near-Critical Activity
An activity with a total float that is deemed to be low based on expert judgement.
194
Near-Critical Path
A sequence of activities with low float which, if exhausted, becomes a critical path sequence for the project.
195
Net Promoter Score®
An index that measures the willingness of customers to recommend an organization’s products or services to others.
196
Network Logic
All activity dependencies in a project schedule network diagram.
197
Network Path
A sequence of activities connected by logical relationships in a project schedule network diagram.
198
Node
A point at which dependency lines connect on a schedule network diagram.
199
Objective
Something toward which work is to be directed, a strategic position to be attained, a purpose to be achieved, a result to be obtained, a product to be produced, or a service to be performed.
200
Opportunity
A risk that would have a positive effect on one or more project objectives.
201
Optimistic Duration
An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
202
Organizational Breakdown Structure (OBS)
A hierarchical representation of the project organization. Illustrated the relationship between project activities and the organizational units that will perform those activities.
203
Organizational Enabler
A structural, cultural, technological, or human-resource practice that the performing organization can use to achieve strategic objectives.
204
Organizational Process Assets (OPA)
Plans, processes, policies, procedures, and knowledge bases specific to and used by the performing organization.
205
Organizational Project Management
A framework in which portfolio, program, and project management are integrated with organizational enablers in order to achieve strategic objectives.
206
Organizational Project Management Maturity
The level of an organization's ability to deliver the desired strategic outcomes in a predictable, controllable, and reliable manner.
207
Osmotic Communication
Means of receiving information without direct communication by overhearing and through nonverbal cues.
208
Outcome
An end result or consequence of a process or project.
209
Parametric Estimating
An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
210
Path Convergence
A relationship in which a schedule activity has more than on predecessor.
211
Path Divergence
A relationship in which a schedule activity has more than on successor.
212
Percent Complete
An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure (WBS) component.
213
Performance Measurement Baseline (PMB)
Integrated scope, schedule, and cost baselines used for comparison to manage, measure, and control project execution.
214
Performing Organization
An enterprise whose personnel are the most directly involved in doing the work of the project or program.
215
Pessimistic Duration
As estimate of the longest activity duration that takes into account all of the known variables that could affect performance.
216
Phase Gate
A review at the end of a phase in which a decision is made to continue to the next phase, to continue with modification, or to end a project or program.
217
Plan
A proposed means of accomplishing something.
218
Planned Value (PV)
The authorized budget assigned to scheduled work.
219
Planning Performance Domain
The performance domain that addresses activities and functions associated with the initial, ongoing, and evolving organization and coordination necessary for delivering project deliverables and results.
220
Planning Process Group
Those processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project was undertaken to achieve.
221
Portfolio
Projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives.
222
Portfolio Balancing
The process of optimizing the mix of portfolio component to further the strategic objectives of the organization.
223
Portfolio Charter
A document issues by a sponsor that authorizes and specifies the portfolio structure and links the portfolio to the organization's strategic objectives.
224
Portfolio Management
The centralized management of one or more portfolios to achieve strategic objectives.
225
Portfolio Management Plan
A document that specifies how a portfolio will be organized, monitored, and controlled.
226
Portfolio Manager
The person or group assigned by the performing organization to establish, balance, monitor, and control portfolio components in order to achieve strategic business objectives.
227
Precedence Diagramming Method (PDM)
A technique used for constructing a schedule model. Activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequences in which the activities are to be performed.
228
Precision
Within the quality management system, precision is an assessment of exactness.
229
Predecessor Activity
An activity that logically comes before a dependent activity in a schedule.
230
Predictive Approach
A development approach in which the project scope, time, and cost are determined in the early phases of the life cycle.
231
Preventive Action
An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
232
Prioritization Matrix
A scatter diagram that plots effort against value so as to classify items by priority.
233
Prioritization Schema
Methods used to prioritize portfolio, program, or project components, as well as requirements, risks, features, or other product information.
234
Probabilistic Estimating
A method used to develop a range of estimates along with the associated probabilities within that range.
235
Probability and Impact Matrix
A grid for mapping the probability of occurrence of each risk and its impact on project objectives if that risk occurs.
236
Procurement Management Plan
A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
237
Product
An artifact that is produced, is quantifiable, and can be either an end item in itself or a component item.
238
Product Breakdown Structure
A hierarchical structure reflecting a product’s components and deliverables.
239
Product Life Cycle
The series of phases that represent the evolution of a product, from concept through delivery, growth, maturity, and to retirement.
240
Product Management
The integration of people, data, processes, and business systems to create, maintain, and evolve a product or service throughout its life cycle.
241
Product Owner
A person responsible for maximizing the value of the product and accountable for the end product
242
Product Scope
The features and functions that characterize a product, service, or result
243
Program
Related projects, subsidiary programs, and program activities managed in a coordinated manner to obtain benefits not available from managing them individually.
244
Program Charter
A document issues by a sponsor that authorizes the program management team to use organizational resources to execute the program and links the program to the organization's strategic objectives.
245
Program Evaluation and Review Technique (PERT)
A technique used to estimate project duration through a weighted average of optimistic, pessimistic, and most likely activity durations when there is uncertainty with the individual activity estimates.
246
Program Management
The application of knowledge, skills, and principles to a program to achieve program objectives an to obtain benefits and control not available by managing program components individually.
247
Program Management Office
A management structure that standardizes the program-related governance processes and facilitates the sharing of resources, methodologies, tools, and techniques.
248
Program Management Plan
A document that integrates the program's subsidiary plans and establishes the management controls and overall plan for integrating and managing the program's individual component.
249
Program Manager
The person authorized by the performing organization to lead the team or teams responsible for achieving program objectives.
250
Progressive Elaboration
The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
251
Project
A temporary endeavor undertaken to create a unique product, service, or result.
252
Project Brief
A high-level overview of the goals, deliverables, and processes for the project.
253
Project Budget
The sum of work package cost estimates, contingency reserve, and management reserve.
254
Project Calendar
A calendar that identifies working days and shifts that are available for scheduled activities.
255
Project Charter
A document issues by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. Also referred to as Charter.
256
Project Governance
The framework, functions, and processes that guide project management activities in order to create a unique product, service, or result to meet organizational, strategic, and operational goals.
257
Project Lead/Manager
A person who helps the project team to achieve the project objectives, typically by orchestrating the work of the project.
258
Projectized Organization
An organizational structure in which the project manager has full authority to assign work and apply resources.
259
Project Life Cycle
The series of phases that a project passes through from its start to its completion.
260
Project Management
The application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.
261
Project Management Body of Knowledge (PMBOK)
A term that describes the knowledge within the profession of project management.
262
Project Management Office (PMO)
A management structure that standardizes the project-related governance processes and facilitates the sharing of resources, methodologies, tools, and techniques
263
Project Management Plan
The document that describes how the project will be executed, monitored and controlled, and closed
264
Project Management Process Group
A logical grouping of project management inputs, tools and techniques, and outputs. The Project Management Process Groups include Initiating processes, Planning processes, Executing processes, Monitoring and Controlling processes, and Closing processes
265
Project Management Team
The members of the project team who are directly involved in project management activities.
266
Project Phase
A collection of logically related project activities that culminates in the completion of one or more deliverables.
267
Project Review
An event at the end of a phase or project to assess the status, evaluate the value delivered, and determine if the project is ready to move to the next phase or transition to operations.
268
Project Schedule
An output of a schedule model that presents linked activities with planned dates, durations, milestones, and resources. Also referred to as Schedule.
269
Project Schedule Network Diagram
A graphical representation of the logical relationships among the project schedule activities.
270
Project Scope
The work performed to deliver a product, service, or result with the specified features and functions.
271
Project Scope Statement
The description of the project scope, major deliverables, and exclusions.
272
Project Team
A set of individuals performing the work of the project to achieve its objectives.
273
Project Vision Statement
A concise, high-level description of the project that states the purpose and inspires the team to contribute to the project.
274
Project Work Performance Domain
The performance domain that addresses activities and functions associated with establishing project processes, managing physical resources, and fostering a learning environment.
275
Prototype
A working model used to obtain early feedback on the expected product before actually building it
276
Quality
The degree to which a set of inherent characteristics fulfills requirements.
277
Quality Management Plan
A component of the project or program management plan that describes how applicable policies, procedures, and guidelines will be implemented to achieve the quality objectives.
278
Quality Metrics
A description of a project or product attribute and how to measure it.
279
Quality Policy
The basic principles that should govern the organization’s actions as it implements its system for quality management.
280
Quality Report
A project document that includes quality management issues, recommendations for corrective actions, and a summary of findings from quality control activities and may include recommendations for process, project, and product improvements.
281
Register
A written record of regular entries for evolving aspects of a project, such as risks, stakeholders, or defects.
282
Regression Analysis
An analytical method where a series of input variables are examined in relation to their corresponding output results in order to develop a mathematical or statistical relationship.
283
Regulations
Requirements imposed by a governmental body. These requirements can establish product, process, or service characteristics, including applicable administrative provisions that have government-mandated compliance.
284
Relative Estimating
A method for creating estimates that are derived from performing a comparison against a similar body of work, taking effort, complexity, and uncertainty into consideration.
285
Release
One or more components of one or more products, which are intended to be put into production at the same time.
286
Release Plan
The plan that sets expectations for the dates, features, and/or outcomes expected to be delivered over the course of multiple iterations.
287
Release Planning
The process of identifying a high-level plan for releasing or transitioning a product, deliverable, or increment of value.
288
Report
A formal record or summary of information.
289
Requirement
A condition or capability that is necessary to be present in a product, service, or result to satisfy a business need.
290
Requirements Documentation
A record of product requirements and other product information, along with whatever is recorded to manage it.
291
Requirements Management Plan
A component of the project or program management plan that describes how requirements will be analyzed, documented, and managed.
292
Requirements Traceability Matrix
A grid that links product requirements from their origin to the deliverables that satisfy them.
293
Reserve
A provision in the project management plan to mitigate cost and/or schedule risk, often used with a modifier (e.g., management reserve, contingency reserve) to provide further detail on what types of risk are meant to be mitigated.
294
Reserve Analysis
A method used to evaluate the amount of risk on the project and the amount of schedule and budget reserve to determine whether the reserve is sufficient for the remaining risk
295
Residual Risk
The risk that remains after risk responses have been implemented. Also called a Secondary Risk.
296
Resource Breakdown Structure
A hierarchical representation of resources by category and type.
297
Resource Calendar
A calendar that identifies the working days and shifts upon which each specific resource is available.
298
Resource Leveling
A resource optimization technique in which adjustments are made to the project schedule to optimize the allocation of resources and which may affect critical path.
299
Resource Management Plan
A component of the project management plan that describes how project resources are acquired, allocated, monitored, and controlled.
300
Resource Optimization Technique
A technique in which activity start and finish dates are adjusted to balance demand for resources with the available supply.
301
Resource Smoothing
A resource optimization technique in which free and total float are used without affecting the critical path.
302
Responsibility Assignment Matrix (RAM)
A grid that shows the project resources assigned to each work package.
303
Result
An output from performing project management processes and activities.
304
Retrospective
A regularly occurring workshop in which participants explore their work and results in order to improve both the process and product.
305
Rework
Action taken to bring a defective or nonconforming component into compliance with requirements or specifications.
306
Risk
An uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives.
307
Risk Acceptance
A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
308
Risk-Adjusted Backlog
A backlog that includes product work and actions to address threats and opportunities
309
Risk Appetite
The degree of uncertainty an organization or individual is willing to accept in anticipation of a reward. A deprecated term for this is Risk Tolerance.
310
Risk Avoidance
A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
311
Risk Breakdown Structure (RBS)
A hierarchical representation of potential sources of risks.
312
Risk Category
A group of potential causes of risk.
313
Risk Enhancement
A risk response strategy whereby the project team acts to increase the probability of occurrence or impact of an opportunity.
314
Risk Escalation
A risk response strategy whereby the team acknowledges that a risk is outside of its sphere of influence and shifts the ownership of the risk to a higher level of the organization where it is more effectively managed.
315
Risk Exploiting
A risk response strategy whereby the project team acts to ensure that an opportunity occurs.
316
Risk Exposure
An aggregate measure of the potential impact of all risks at any given point in time in a project, program, or portfolio.
317
Risk Management Plan
A component of the project, program, or portfolio management plan that describes how risk management activities will be structured and performed.
318
Risk Mitigation
A risk response strategy whereby the project team acts to decrease the probability of occurrence or impact of a threat.
319
Risk Owner
The person responsible for monitoring the risk and for selecting and implementing an appropriate risk response strategy.
320
Risk Register
A repository in which outputs of risk management processes are recorded.
321
Risk Report
A project document that summarizes information on individual project risks and the level of overall project risk.
322
Risk Review
The process of analyzing the status of existing risks and identifying new risks. May also be known as Risk Reassessment.
323
Risk Sharing
A risk response strategy whereby the project team allocates ownership of an opportunity to a third party who is best able to capture the benefit of that opportunity
324
Risk Threshold
The measure of acceptable variation around an objective that reflects the risk appetite of the organization and stakeholders.
325
Risk Transference
A risk response strategy whereby the project team shifts the impact of a threat to a third party, together with ownership of the response.
326
Roadmap
A high-level time line that depicts such things as milestones, significant events, reviews, and decision points.
327
Role
A defined function to be performed by a project team member, such as testing, filing, inspecting, or coding.
328
Rolling Wave Planning
An iterative planning method in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level.
329
Root Cause Analysis
An analytical method used to determine the basic underlying reason that causes a variance or a defect or a risk.
330
Scatter Diagram
A graph that shows the relationship between two variables.
331
Schedule Baseline
The approved version of a schedule model that can be changed using formal change control procedures and is used as the basis for comparison to actual results.
332
Schedule Compression
A method used to shorten the schedule duration without reducing the project scope.
333
Schedule Forecasts
Estimates or predictions of conditions and events in the project’s future based on information and knowledge available at the time the schedule is calculated
334
Schedule Management Plan
A component of the project or program management plan that establishes the criteria and the activities for developing, monitoring, and controlling the schedule
335
Schedule Model
A representation of the plan for executing the project’s activities including durations, dependencies, and other planning information, used to produce a project schedule along with other scheduling artifacts.
336
Schedule Model Analysis
A process used to investigate or analyze the output of the schedule model in order to optimize the schedule.
337
Schedule Network Analysis
A technique to identify early and late start dates, as well as early and late finish dates, for the uncompleted portions of project activities.
338
Schedule Performance Index (SPI)
A measure of schedule efficiency expressed as the ratio of earned value to planned value.
339
Schedule Variance (SV)
A measure of schedule performance expressed as the difference between the earned value and the planned value
340
Scope
The sum of the products, services, and results to be provided as a project.
341
Scope Baseline
The approved version of a scope statement, work breakdown structure (WBS), and its associated WBS dictionary that can be changed using formal change control procedures and is used as the basis for comparison to actual results.
342
Scope Creep
The uncontrolled expansion to product or project scope without adjustments to time, cost, and resources.
343
Scope Management Plan
A component of the project or program management plan that describes how the scope will be defined, developed, monitored, controlled, and validated.
344
S-Curve
A graph that displays cumulative costs over a specified period of time
345
S-Curve Analysis
A technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
346
Self-Organizing Team
A cross-functional team in which people assume leadership as needed to achieve the team’s objectives
347
Sensitivity Analysis
An analysis method to determine which individual project risks or other sources of uncertainty have the most potential impact on project outcomes by correlating variations in project outcomes with variations in elements of a quantitative risk analysis model.
348
Servant Leadership
The practice of leading the team by focusing on understanding and addressing the needs and development of team members in order to enable the highest possible team performance.
349
Simulation
An analytical method that models the combined effect of uncertainties to evaluate their potential impact on objectives.
350
Single-Point Estimating
An estimating method that involves using data to calculate a single value which reflects a best guess estimate.
351
Specification
A precise statement of the needs to be satisfied and the essential characteristics that are required.
352
Sponsor
A person or group who provides resources and support for the project, program, or portfolio and is accountable for enabling success.
353
Sprint
A short time interval within a project during which a usable and potentially releasable increment of the product is created.
354
Staffing Management Plan
A component of the resource management plan that describes when and how team members will be acquired and how long they will be needed.
355
Stakeholder
An individual, group, or organization that may affect, be affected by, or perceive itself to be affected by a decision, activity, or outcome of a project, program, or portfolio.
356
Stakeholder Analysis
A method of systematically gathering and analyzing quantitative and qualitative information to determine whose interests should be taken into account throughout the project.
357
Stakeholder Engagement Assessment Matrix
A matrix that compares current and desired stakeholder engagement levels.
358
Stakeholder Engagement Plan
A component of the project management plan that identifies the strategies and actions required to promote productive involvement of stakeholders in project or program decision making and execution.
359
Stakeholder Performance Domain
The performance domain that addresses activities and functions associated with stakeholders
360
Stakeholder Register
A project document that includes information about project stakeholders including an assessment and classification of project stakeholders.
361
Standard
A document established by an authority, custom, or general consent as a model or example.
362
Start-to-Finish (SF)
A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
363
Start-to-Start
A logical relationship in which a successor activity cannot start until a predecessor activity has started.
364
Statement of Work (SOW)
A narrative description of products, services, or results to be delivered by the project.
365
Status Meeting
A regularly scheduled meeting to exchange and analyze information about the current progress of the project and its performance.
366
Status Report
A report on the current status of the project.
367
Steering Committee
An advisory body of senior stakeholders who provide direction and support for the project team and make decisions outside the project team’s authority.
368
Story Map
A visual model of all the features and functionality desired for a given product, created to give the team a holistic view of what they are building and why.
369
Story Point
A unit used to estimate the relative level of effort needed to implement a user story.
370
Strategic Plan
A high-level document that explains an organization’s vision and mission plus the approach that will be adopted to achieve this mission and vision, including the specific goals and objectives to be achieved during the period covered by the document.
371
Strategy Artifacts
Documents created prior to or at the start of the project that address strategic, business, or high-level information about the project.
372
Successor Activity
A dependent activity that logically comes after another activity in a schedule.
373
Summary Activity
A group of related schedule activities aggregated and displayed as a single activity.
374
Swarm
A method in which multiple team members focus collectively on resolving a specific problem or task.
375
SWOT Analysis
Analysis of strengths, weaknesses, opportunities, and threats of an organization, project, or option.
376
Tacit Knowledge
Personal knowledge that can be difficult to articulate and share such as beliefs, experience, and insights.
377
Tailoring
The deliberate adaptation of approach, governance, and processes to make them more suitable for the given environment and the work at hand.
378
Task Board
A visual representation of the progress of the planned work that allows everyone to see the status of the tasks.
379
Team Charter
A document that records the team values, agreements, and operating guidelines, as well as establishes clear expectations regarding acceptable behavior by project team members.
380
Team Performance Domain
The performance domain that addresses activities and functions associated with the people who are responsible for producing project deliverables that realize business outcomes.
381
Technical Performance Measures
Quantifiable measures of technical performance that are used to ensure system components meet the technical requirements.
382
Template
A partially complete document in a predefined format that provides a defined structure for collecting, organizing, and presenting information and data.
383
Test Plan
A document describing deliverables that will be tested, tests that will be conducted, and the processes that will be used in testing.
384
Threat
A risk that would have a negative effect on one or more project objectives.
385
Three-Point Estimating
A technique used to estimate cost or duration by applying an average or weighted average to optimistic, pessimistic, and most likely estimates when there is uncertainty with the individual activity estimates.
386
Threshold
A predetermined value of a measurable project variable that represents a limit that requires action to be taken if it is reached.
387
Throughput
The number of items passing through a process.
388
Throughput Chart
A diagram that shows the accepted deliverables over time.
389
Time and Materials Contract (T&M)
A type of contract that is a hybrid contractual arrangement containing aspects of both cost-reimbursable and fixed-price contracts.
390
Timebox
A short, fixed period of time in which work is to be completed.
391
To-Complete Performance Index (TCPI)
A measure of the cost performance that is achieved with the remaining resources in order to meet a specified management goal. Expressed as the ratio of the cost to finish the outstanding work to the remaining budget. TCPI = (BAC - EV) / (BAC - AC)
392
Tolerance
The quantified description of acceptable variation for a quality requirement.
393
Total Float
The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
394
Trend Analysis
An analytical method that uses mathematical models to forecast future outcomes based on historical results.
395
Trigger Condition
An event or situation that indicates that a risk is about to occur.
396
Triple Bottom Line
A framework for considering the full cost of doing business by evaluating a company’s bottom line from the perspective of profit, people, and the planet.
397
Uncertainty
A lack of understanding and awareness of issues, events, path to follow, or solutions to pursue.
398
Uncertainty Domain
The performance domain that addresses activities and functions associated with risk and uncertainty.
399
Use Case
An artifact for describing and exploring how a user interacts with a system to achieve a specific goal.
400
User Story
A brief description of an outcome for a specific user, which is a promise for a conversation to clarify details.
401
Validation
The assurance that a product, service, or result meets the needs of the customer and other identified stakeholders.
402
Value
The worth, importance, or usefulness of something.
403
Value Delivery Office (VDO)
A project delivery support structure that focuses on coaching teams; building agile skills and capabilities throughout the organization; and mentoring sponsors and product owners to be more effective in those roles.
404
Value Delivery System
A collection of strategic business activities aimed at building, sustaining, and/or advancing an organization.
405
Value Proposition
The value of a product or service that an organization communicates to its customers.
406
Value Stream Map
A display of the critical steps in a process and the time taken in each step used to identify waste.
407
Value Stream Mapping
A lean enterprise method used to document, analyze, and improve the flow of information or materials required to produce a product or service for a customer.
408
Vanity Metric
A measure that appears to show some result but does not provide useful information for making decisions.
409
Variance
A quantifiable deviation, departure, or divergence away from a known baseline or expected value.
410
Variance Analysis
A method for determining the cause and degree of difference between the baseline and actual performance.
411
Variance at Completion (VAC)
A projection of the amount of budget deficit or surplus, expressed as the difference between the budget at completion and the estimate at completion.
412
Velocity
A measure of a team’s productivity rate at which the deliverables are produced, validated, and accepted within a predefined interval.
413
Velocity Chart
A chart that tracks the rate at which the deliverables are produced, validated, and accepted within a predefined interval.
414
Verification
The evaluation of whether or not a product, service, or result complies with a regulation, requirement, specification, or imposed condition.
415
Virtual Team
A group of people with a shared goal who work in different locations and who engage with each other primarily through phone and other electronic communications.
416
Vision Statement
A summarized, high-level description about the expectations for a product such as target market, users, major benefits, and what differentiates the product from others in the market.
417
Visual Data and Information
Artifacts that organize and present data and information in a visual format, such as charts, graphs, matrices, and diagrams.
418
Voice of the Customer
A planning method used to provide products, services, and results that truly reflect customer requirements by translating those customer requirements into the appropriate technical requirements for each phase of project or product development.
419
Volatility
The possibility for rapid and unpredictable change.
420
Waste
Activities that consume resources and/or time without adding value.
421
WBS Dictionary
A document that provides detailed deliverable, activity, and scheduling information about each component in the work breakdown structure (WBS).
422
What-If-Scenario Analysis
The process of evaluating scenarios in order to predict their effect on project objectives.
423
Wideband Delphi
An estimating method in which subject matter experts go through multiple rounds of producing estimates individually, with a team discussion after each round, until a consensus is achieved.
424
Work Breakdown Structure (WBS)
A hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables.
424
Workaround
An immediate and temporary response to an issue for which a prior response had not been planned or was not effective.
425
Work Package
The work defined at the lowest level of the work breakdown structure for which cost and duration are estimated and managed.