PMP Flashcards

(44 cards)

1
Q

Cost Variance (CV) =

A

Earned Value (EV) – Actual Cost (AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Schedule Variance (SV) =

A

Earned Value (EV) – Planned Value (PV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Cost Performance Index (CPI) =

A

EV / AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Schedule Performance Index (SPI) =

A

EV / PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

EAC =

A

AC + Bottom-up ETC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

EAC =

A

BAC / Cumulative CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

EAC =

A

AC + (BAC – EV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

EAC =

A

AC + [BAC – EV / (Cumulative CPI ´ Cumulative SPI)]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Channels of communication

A

[N(N-1)/2]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Mutually exclusive

A

Events that cannot occur together in a single trial are known as

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Handed project charter

A

now identify stakeholders to get input on scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

High probability risk, low impact

A

add to watch list

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Passive risk acceptance =

A

deal with risk as it occurs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Join organization, first thing -

A

talk to stakeholders to get understanding of org and projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Environmental risks consultant

A

time and materials contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Determines priorities n large org

A

PMO

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Best interest of project for risk to happen

A

Exploit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Stakeholder analysis =

A

learning about requirements of stakeholders and adjusting to meet needs

19
Q

Buffers =

A

act as a cushion for risks

20
Q

Acceptance =

A

no appropriate risk response and risk is inevitable

21
Q

Best for completing lessons learned =

22
Q

Stakeholders are dissatisfied with deliverables =

A

should have defined scope better

23
Q

start formula

A

late start - early start

24
Q

positive float

A

is amount of time as a buffer to delay

25
free float
amount of time activity can be delayed without delaying early start date of successor activity
26
project float
amount of time an activity can be delayed without delaying project completion date
27
feeding buffers
added to chain of dependent activities not on critical chain
28
project buffers
added to protect targeted finish date
29
duration buffer
added to non schedule work activities to address uncertainty
30
network diagram
shows interdependencies between activities
31
Beta Standard Deviation =
(P-O)/6
32
PERT =
(P+4M+0) / 6
33
plan cost mgmt process =
process to provide guidance on how to manage and control costs
34
rough order estimate
- made during project initiating | - range of -25% to +75% from actual value
35
budget
- made during project planning | - 10% to +25%
36
definitive
- as things become clear during project | - -5% to +10%
37
negative cost variance =
project is over budget
38
negative SV =
project is behind schedule
39
CPI > 1
good
40
quality mgmt
involves processes and activities that ensure product and product requirements are validated, checked and fulfilled
41
Plan Quality Management Process
identifying requirements and existing standards
42
Pert Estimate =
(Optimistic + (4 X Most Likely) + Pessimistic)/6
43
PV
FV / (1 + r)^n
44
NPV
= Total PV revenue - total PV costs