PMP Flashcards
(44 cards)
Cost Variance (CV) =
Earned Value (EV) – Actual Cost (AC)
Schedule Variance (SV) =
Earned Value (EV) – Planned Value (PV)
Cost Performance Index (CPI) =
EV / AC
Schedule Performance Index (SPI) =
EV / PV
EAC =
AC + Bottom-up ETC
EAC =
BAC / Cumulative CPI
EAC =
AC + (BAC – EV)
EAC =
AC + [BAC – EV / (Cumulative CPI ´ Cumulative SPI)]
Channels of communication
[N(N-1)/2]
Mutually exclusive
Events that cannot occur together in a single trial are known as
Handed project charter
now identify stakeholders to get input on scope
High probability risk, low impact
add to watch list
Passive risk acceptance =
deal with risk as it occurs
Join organization, first thing -
talk to stakeholders to get understanding of org and projects
Environmental risks consultant
time and materials contract
Determines priorities n large org
PMO
Best interest of project for risk to happen
Exploit
Stakeholder analysis =
learning about requirements of stakeholders and adjusting to meet needs
Buffers =
act as a cushion for risks
Acceptance =
no appropriate risk response and risk is inevitable
Best for completing lessons learned =
stakeholders
Stakeholders are dissatisfied with deliverables =
should have defined scope better
start formula
late start - early start
positive float
is amount of time as a buffer to delay