PMP Flashcards
(304 cards)
What is the difference between “individual Project Risk” and “Overall Project Risk”?
Individual project risk is a single uncertain event or condition that can impact the project.
Overall project risk is the risk exposure of the project as a whole
What is the difference between “risk appetite” and “risk tolerance”
Risk appetite is the amount of risk you are willing to take for a reward
- ex: not willing to go to vegas because you don’t want to take that risk
Risk tolerance is the amount of volume of risk you are willing to take
- ex: how much you are willing to play in the slot machine
What is a “known-known” risk?
Risk that you know about and generally know how to respond to it
What is a “Known-Unknown” risk
risks that you know about but you haven’t analyzed to the full extend.
What is an “unknown-unknown” risk
a risk you don’t know about but it could happen
What is the difference between Variability Risk and Ambiguity Risk?
Both Non-Event Risks
Variability risk is some aspect of a planned task or situation that is uncertain. E.g.: productivity targets, error during testing, weather patterns
Ambiguity Risks are uncertainties arising from lack of knowledge or understanding. e.g. future regulations
What is Project Resilience
Ability to handle risk that was not known. Ability to handle unknowable-unknowns
What are the three types of contracts?
Fixed-Price, Cost-reimbursable, Time and Material
Tell me about a Fixed Price (Lump Sum) contract
- Buyer pays one flat price (lump sum) for all work in the contract
- includes labor and material
- used when the scope is well-defined and understood
- all risk is with the seller (person performing work)
- 3 types:
- Firm Fixed Price (FFP): price is fixed and cannot be changed
- Fixed price incentive fee (FPF): fixed price includes additional fee for meeting a target outlined in the contract
- Fixed price economic price adjustment (FP-EPA): adjust fixed cost over the life of the contract because of economic conditions
Tell me about a cost-reimbursable contract
- Buyer pays for the work expenses and then pays the seller a fee for his profit (example: I will buy all the materials and pay you $100 to paint the room). Fixed fee for profit.
- The risk is with the buyer because the cost overrun of work expense is covered by the buyer because the seller (painter) is guaranteed the profit
3 types-- Cost plus fixed fee (CPIFF) buyer pays the work expense and then a fixed fee to the seller for profit
- cost plus incentive fee (CPIF): buyer pays the work expense and an additional fee, if a target is met, such as, finishing two weeks earlier
- cost plus award fee (CPAF): buyer pays the work expense and pays an award fee that is based on satisfaction of work
Tell me about Time and Material contract
buyer pays for both labor and material
- buyer takes all the risk of cost overrun for both the labor and materials
- should only be used when scope is high-level
What procurement document describes the type of agreement to use and how the project would like delivery to take place?
Procurement strategy
The procurement strategy documents delivery methods, types of agreements, and the procurement phases of the project.
What documents are used to get a response from potential sellers
- generally include an RFP, RFQ or RFI
Bid documents
What is a Bidder Conference (Contractor, vendor, or pre-bid conferences)
Meeting between buyer and sellers
- when you have a big project, and you want to explain the project to a bunch of people at once
what do you do if there are ANY disagreements between a buyer and a seller?
Send it to the Claims Administration
what is the list of sellers that have been properly vetted by the organization and can be used as potential sellers on a project?
Preapproved seller list
Criteria used to evaluate the sellers and can include things such as costs, delivery dates, experience, financial stability, and management experience
Source selection criteria
What are you getting when you hire an outside professional estimator to provide a benchmark to determine whether the bids form a seller are adequate for the project
Independent cost estimate
What is the difference between the procurement statement of work and the procurement management plan
The procurement management plan is part of the project management plan, while the procurement statement of work is a project document.
The procurement management plan contains the activities necessary to conduct the procurement processes.
The procurement statement of work outlines what, from the scope baseline, will be outsourced. It also contains information such as specifications, desired quality, and quality levels.
Who approves all deliverables prior to the closure of procurement?
The Project Manager
What model is used to describe stakeholders based on their power level, influence, urgency, or legitimacy.
salience model
Where should the project manager include the organization position and role of the project stakeholders?
stakeholder register
which document has all details about each work package, such as who is doing it, where it’s getting done, and its cost. Also includes acceptance criteria for each of the work packages
WBS dictionary
____ dependencies are those that are legally or contractually required or inherent in the nature of the work.
Mandatory dependencies