- The terms of union contracts are considered ______________ in your project plan.
A. Assumptions
B. Constraints
C. Requirements
D. Collective bargaining agreements
Answer: B
When you work with a union, then the union contract can have an impact on your project. That means you need to consider the union itself a stakeholder, and when you do your planning you need to make sure any union rules and agreements are considered as constraints.
Note Working with unions will add rules that your project must comply with, and the contract is an important tool to ensure compliance.
- A project manager is reporting the final status of the closed contract to the stakeholders. Which form of communication is appropriate?
A. Informal written
B. Informal verbal
C. Formal written
D. Formal verbal
Answer: C
All project reports must be communicated as formal written documents. Not only that, but anything that has to do with a contract definitely needs to be formal written.
- Which of the following is not a tool or technique of the Control Quality process?
A. Inspection
B. Quality audits
C. Pareto charts
D. Statistical sampling
Answer: B
Quality audits are when your company reviews your project to make sure that you are following all of the processes in your company correctly. They are a tool of the Manage Quality process.
You have just delivered a product to your client for acceptance when you get a call that some features they were expecting are missing. What’s the first thing you should do?
A. Get your team together and reprimand them for building a product that doesn’t meet user expectations.
B. Tell the client that the product passed all of your internal quality inspections and scope verification processes, so it must be fine.
C. Tell the team to start building the missing features into the product right away.
D. Call a meeting with the client to understand exactly what is unacceptable in the product and try to figure out what went wrong along the way.
Answer: D
You can’t do anything about the problem until you understand it. You should meet with the client to get a better understanding of what went wrong and why the product is not meeting their needs.
Which of the following is not a tool or technique of Estimate Costs?
A. Bottom-up
B. Parametric
C. Cost aggregation
D. Analogous
Answer: C
Cost aggregation is used to build your budget, but it is not a tool for cost estimation. Bottom-up, parametric, and analogous estimation techniques are used for both cost and time estimates.
Which of the following is not a source of information about specific project constraints and assumptions?
A. The Scope Management plan
B. Requirements documentation
C. The project scope statement
D. The scope baseline
Answer: A
The project Scope Management plan is a really important tool in your project. It tells you exactly how you’ll create the project scope, define the WBS, verify that the work has been done, and make changes to the scope. But it doesn’t tell you about specific assumptions that you and the team have made, or constraints on your project. To find those, you should look in the requirements documentation and the project scope statement.
Note The scope baseline contains the WBS and project scope statement, so you’ll find constraints and assumptions there, too!
A project manager uses a facilitator who holds a meeting to gather opinions from team members anonymously. One team member is having difficulty understanding the process that they are being asked to follow. Which of the following is NOT an effective way to handle this situation?
A. Follow up with the team member individually and work together to determine how to ensure that they have the correct skills in the future
B. Confront the issue by pausing the meeting, bring the team member to the front of the room, and explain in detail how the process works
C. Reschedule the meeting for a future time, without placing blame or pointing to any individual as a reason to move it
D. Schedule a training session for the entire team to learn and practice the facilitated process
Answer: B
Singling out an individual who is having trouble and correcting them in front of the entire team is highly demotivating, and can cause serious problems with teamwork in the future.
Joe is an excellent programmer. He was promoted to the role of project manager because he understands technology better than anyone else in the company. Unfortunately, he is having trouble doing the project management job and his projects are failing. What is this an example of?
A. Gold plating
B. Halo effect
C. Preassignment
D. Ground rules
Answer: B
The halo effect is when you put someone in a position he can’t handle, just because he’s good at another job. Just because Joe is a great programmer, that doesn’t mean he’ll be a good project manager.
When are the most expensive defects most likely to be introduced into a product?
A. When the product is being assembled
B. When the product is being designed
C. When the Quality Management plan is being written
D. When the product is being reviewed by the customers
Answer: B
The most expensive defects are the ones introduced when the product is being designed. This is a little counterintuitive at first, but it really makes sense once you think about how projects are run. If your team introduces a defect into a product while it’s being assembled, then they have to go back and fix it. But if there’s a flaw in the design, then you have to halt production and go back and figure out all the things that flaw affected. You may have to order new parts,reassemble components, and maybe even go back and redesign the product from the ground up.
Note That’s why your Quality Management processes are so focused on reviewing EVERY deliverable—not just the final product, but all of the components, designs, and specifications, too.
You are the project manager for a railroad construction project. Your sponsor has asked you for a forecast for the cost of project completion. The project has a total budget of $80,000 and CPI of .95. The project has spent $25,000 of its budget so far. How much more money do you plan to spend on the project?
A. $59,210
B. $80,000
C. $84,210
D. $109,210
Answer: A
This question is asking you to create a forecast using estimate to complete (ETC), which uses CPI to project how much money is likely to be spent for the rest of the project. The first step is to plug the numbers into the formula EAC = BAC / CPI, which yields EAC = $80,000 / .95 = $84,210. That’s how much money you’re likely to spend on the project. Now you can figure out ETC = EAC – AC = $84,210 – $25,000 = $59,210.
Which of the following best describes decomposition?
A. Waiting for a task to expire so that it can break down into smaller tasks
B. Taking a deliverable and breaking it down into the smaller work packages so that it can be organized and planned
C. Categorizing work packages
D. Dividing work packages into deliverables that can be planned for
Answer: B
Decomposition is the main tool for creating the WBS. It just means breaking the work down into smaller and smaller pieces based on how your company does the work until it is small enough to categorize and organize hierarchically.
Which is the best definition of quality?
A. A product made of very expensive materials
B. A product made with a lot of care by the team who built it
C. A product that satisfies the requirements of the people who pay for it
D. A product that passes all of its tests
Answer: C
Quality Management is all about making sure that the product you are building conforms to your customer’s requirements. If you have done a good job of gathering and understanding those requirements, all of the measurements you take on your project should help you see if what you are building will satisfy your clients in the end.
Which of the following is NOT a Project Constraint?
A. Quality
B. Scale
C. Time
C. Cost
B. Scale
A project manager is running a data center installation project. He finds that his stakeholder is angry that he’s run over his budget because the staff turned out to be more expensive than planned. The stakeholder’s unhappy that when the project is over, the servers won’t have as much drive space as he needs. Which of the following constraints was not affected by this problem?
A. Quality
B. Resource
C.Time
D. Cost
C. Time
Which of the following is NOT an example of operational work?
A. Building a purchase order system for accounts payable
B. Submitting weekly purchase orders through a purchase order system
C. Deploying weekly antivirus software updates
D. Yearly staff performance evaluations
A
You’re managing a project to build a new accounting system. One of the accountants in another department really likes the current system and is refusing to be trained on the new one. What is the BEST way to handle this situation?
A. Refuse to work with him because he’s being difficult
B. Appeal to the accountant’s manager and ask to have him required to take training
C. Get a special dispensation so that the accountant doesn’t have to go to the training
D. Work with him to understand his concerns and do what you can to help alleviate them without compromising your project
D. Work with him to understand his concerns and do what you can to help alleviate them without compromising your project
Which of the following is used for identifying people who are impacted by the project?
A. Resource list
B. Stakeholder register
C. Enterprise environmental factors
D. Project plan.
B. Stakeholder Register
Your manager asks you where to find a list of projects that should be managed together.
What is the BEST place to find this information?
A. Project plan
B. Project charter
C. Portfolio charter
D. Program charter
D. Program Charter
You want to know specifically which business goal a group of projects and programs is going to accomplish. Which is the BEST place to look for this information?
A. Project plan
B. Project charter
C. Portfolio charter
D. Program charter
C. Portfolio
A project coordinator is having trouble securing programmers for her project. Every time she asks her boss to give a resource to the project he says that they are too busy to help out with her project. Which type of organization is she working in?
A. Functional
B. Weak matrix
C. Strong matrix
D. Projectized
A. Functional
A project manager is having trouble getting customer feedback on her project. Even though she knows the product won’t be complete for several months, the company guidelines say she should release an early version and get feedback from end users. Which type of organization is she working for?
A. Functional
B. Virtual
C. Hybrid
D. Projectized
Answer: C
The project manager in this scenario is working for a hybrid organization. She used predictive methods to understand that her project won’t be completed for several months and is about to use adaptive methods to get early feedback on the unfinished product.
The project manager for a construction project discovers that a new water line is being created in the neighborhood where he’s managing a project. Government regulations require that a series of forms for city environmental changes need to be filled out before his team can continue work on the project. This is an example of:
A. A portfolio
B. A program
C. An enterprise environmental factor
D. A project
D. A Project
You’re a project manager working on a software engineering project. Your manager is asking you to write down your performance goals for the year and measure them for your next performance evaluation. What leadership style is your manager using?
A.Charismatic
B Interactional
C.Transactional
D. Performance
C. Transactional
Which of the following is not a stakeholder?
A. The project manager who is responsible for building the project
B. A project team member who will work on the project
C. A customer who will use the final product
D. A competitor whose company will lose business because of the product
\
D.