PMP Prep Flashcards
(176 cards)
Budget at Completion (BAC)
Original budget of project
PV
Planned Value
Amount of money worth of work that should have been done on the project
EV
Earned Value
Amount of money worth of work actually done
AC
Actual Cost
Amount of money already spent on the project
CV
Cost Variance
Difference between work done and money spent. Negative values = bad
CPI
Cost Performance Index
Rate of how we are spending to actually earning. 1 and over is good
SV
Schedule Variance
Difference between amount of work you should have done vs actually done. Negative value = bad
SPI
Schedule Performance Index
Rate of how we are meeting project schedule. 1 and over is good
EAC
Estimate at Completion
Forecasting total cost of the project at the end based on current spending rate
ETC
Estimate to Completion
Forecasting the amount of money that will be needed to complete the project based on current performance
VAC
Variance at Completion
Difference between original budget and new forecasted budget. Negative = bad
TCPI
To-Complete Performance Index
Performance needed to finish the project within budget
Process Groups
Initiating
Planning
Executing
Monitoring and Controlling
Closing
Knowledge Areas
Project Integration Management
Project Scope Management
Project Schedule Management
Project Cost Management
Project Quality Management
Project Resource Management
Project Communications Management
Project Risk Management
Project Procurement Management
Project Stakeholder Management
Project Integration Management Processes
7
Develop Project Charter (i)
Develop Project Management Plan (p)
Direct and Manage Project Work (e)
Manage Project Knowledge (e)
Monitor and Control Project Work (mc)
Perform Integrated Change Control (mc)
Close project or Phase (c)
Project Scope Management Processes
6
Plan Scope Management (p)
Collect Requirements (p)
Define Scope (p)
Create WBS (p)
Validate Scope (mc)
Control Scope (mc)
Project Schedule Management Processes
6
Plan Schedule Management (p)
Define activities (p)
Sequence activities (p)
Estimate activity duration (p)
Develop schedule (p)
Control schedule (mc)
Project Cost Management Processes
4
Plan cost management (p)
Estimate costs (p)
Determine budget (p)
Control costs (mc)
Project Quality Management Processes
3
Plan quality management (p)
Manage Quality (e)
Control Quality (mc)
Project Resource Management Processes
6
Plan resource management (p)
Estimate activity resources (p)
Acquire resources (e)
Develop team (e)
Manage team (e)
Control resources (mc)
Project Communications Management Processes
3
Plan communications management (p)
Manage communications (e)
Monitor communications (mc)
Project Risk Management Processes
7
Plan risk management (p)
Identify risks (p)
Perform qualitative risk analysis (p)
Perform quantitative risk analysis (p)
Plan risk response (p)
Implement risk responses (e)
Monitor risks (mc)
Project Procurement Management Processes
3
Plan Procurement management (p)
Conduct procurements (e)
Control Procurements (mc)
Project Stakeholder Management Processes
Identify stakeholders (i)
Plan Stakeholder engagement (e)
Manage stakeholder engagement (e)
Monitor stakeholder engagement (mc)