PMP Questions Scardo Errors Flashcards
Daniel is managing the development of an ecommerce website for his organization. Daniel enjoys coercive powers and has assigned Julie, a project team member, to facilitate the team meetings. During any team meeting, Julie must?
Influence team members to support the project manager’s decisions
Support the team members to challenge the project manager’s decisions
Negotiate with team members to achieve the project objectives
Remain neutral and facilitate the meetings
D - Since the project manager enjoys coercive powers, it seems likely that he has assigned a neutral facilitator to facilitate the team meetings. Facilitation is a management skill. A good facilitator should always remain neutral in a meeting and help facilitate consensus when required. [PMBOK 5th edition, Page 408] [Project Stakeholder Management]
What is the primary risk with including reserves or contingency allowances in your cost estimate? Cancelling your project Understating the cost estimate Overstating the cost estimate Tracking the funds
C - Contingency funds are used to handle cost uncertainty due to unknown purchases that may be needed during a project. These funds are generally used for items that are likely to occur, but not certain to occur. [PMBOK 5th edition, Page 206] [Project Cost Management]
With the establishment of a PMO in an organization, the project management jargon is being adopted by the employees. However, few people are still struggling with the project management terminologies. One of the most common confusion is the difference between a project stakeholder and a key stakeholder. Who are the key stakeholders?
Individuals, groups or organizations in a decision making position.
Individuals, groups or organizations actively involved in the project.
Individuals, groups or organizations affected by the project.
Individuals, groups or organizations carrying out the project work.
A - All of the given choices correctly define the project stakeholders. However, the key stakeholders are the subset of the project stakeholders that are in a decision making position. [PMBOK 5th edition, Page 396] [Project Stakeholder Management]
Perform Integrated Change Control includes several configuration management activities. Which of the following is not part of Perform Integrated Change Control? Change request Configuration Verification Configuration Status Accounting Configuration Identification
A - Change request is not a valid response. The configuration management activities included in the Perform Integrated Change Control process are Configuration Identification, Configuration Status Accounting, Configuration Verification and Auditing. [PMBOK 5th edition, Page 96, 97] [Project Integration Management]
The most detailed level of the WBS is called the \_\_\_\_\_\_\_\_\_\_\_\_\_\_\_ . WBS element Work package Project scope Deliverable
B - The work package is the lowest and most detailed level of the WBS and can be scheduled, cost estimated, monitored, and controlled. [PMBOK 5th edition, Page 126] [Project Scope Management]
Which of the following is a tool or technique used in the Monitor and Control Project Work process? Expert judgment Rejected change requests Earned value technique Change control tools
A - Expert Judgment is a tool or technique used in the Monitor and Control Project Work process. [PMBOK 5th edition, Page 86] [Project Integration Management]
Mary is currently focusing on controlling the key stakeholder engagement on her project. The project management plan is an essential input to this process. Which of the following components of the project management plan is least likely to be utilized during this process?
Stakeholder communication needs and expectations
Project management processes selected for the project
Change management process
Human resource requirements
B - All of the given choices are the components of the project management plan that can be utilized during the Control Stakeholder Engagement process. However, the key project stakeholders are usually not interested in the minor details of the project; rather they are more interested in the project’s objectives, the current progress, and the current risks and issues. From the given choices, ‘the selected project management processes for the project’ is the weakest choice. [PMBOK 5th edition, Page 411] [Project Stakeholder Management]
The Project Charter formally authorizes a project. Who authorizes the project charter?
The project manager
A project sponsor or initiator internal to the project
The user of the product
A project sponsor or initiator external to the project
D - A project initiator or sponsor external to the project, at a level that is appropriate to funding the project, authorizes the project charter. [PMBOK 5th edition, Page 68] [Project Integration Management]
Which of the following is an input to the Develop Project Team process? Resource Requirements Resource Conflicts Resource Calendars Resource Breakdown Structure
C - Resource calendars are input of the Develop Project Team process. [PMBOK 5th edition, Page 273] [Project Human Resource Management]
Which of the following is an enterprise environmental factor? Configuration management knowledge base Change control procedures Historical information Commercial databases
D - The commercial databases are considered enterprise environmental factors. Rest of the choices are organizational process assets. [PMBOK 5th edition, 29] [Project Framework]
Which of the following is a classic organizational structure? Functional Projectized Composite Matrix
A - A functional organization is a classical organizational structure. [PMBOK 5th edition, Page 22] [Project Framework]
If you are developing a Project Management Plan, how should you determine the level of detail to be included in the plan?
Always only provide a summary or high level plan
Include only the details your manager specifically requested
Always provide the maximum level of detail possible
Provide the level of detail based on the project complexity and application area
D - The level of detail required in a Project Management Plan would vary by project and would include only the details necessary for the project. [PMBOK 5th edition, Page 78] [Project Integration Management]
In general, Perform Qualitative Risk Analysis is: not often completed complete and 100% accurate in-depth and thorough quick and cost-effective
D - Perform Qualitative Risk Analysis is quicker than Perform Quantitative Risk Analysis which is sometimes not required by the project. [PMBOK 5th edition, Page 328, 333] [Project Risk Management]
During a project update meeting for the key stakeholders, the schedule of some project activities was challenged. The VP Operations challenged that some of the critical path activities cannot be executed as scheduled as they will disturb critical operations. The VP has requested rescheduling of these tasks so that they are carried out during the non-working times of the business. What should the project manager do first?
Analyze the impact of change
Record the issue in the issue log
Send the change request to the change control board for the approval
Produce a change request
B - All of the tasks in the choices need to be carried out. However, the question is asking for the task to be carried out first. The identified issue must be documented in the project’s issue log first. This should be captured and recorded during the meeting. Rest of the tasks can be performed after the meeting. [PMBOK 5th edition, Page 408] [Project Stakeholder Management]
Susan is about to review her project stakeholder management plan to make some necessary adjustments. She has got her project management plan, the recent issue log and the work performance data. Which of the following inputs is still missing for this process? Project charter Stakeholder management plan Project documents Communication management plan
C - Since Susan is planning to adjust her project stakeholder management plan, this implies that she is about to start the Control Stakeholder Engagement process. The stakeholder management plan and the communication management plan are the components of the project management plan, hence these are already included. The project charter is not an input of the Control Stakeholder Engagement process. The missing input to the process is the project documents. [PMBOK 5th edition, Page 410] [Project Stakeholder Management]
Which of these items are important to address when determining each person’s role in the project team?
Role, authority, responsibility, and competency
Role, responsibility, and competency
Role and responsibility
Role, authority, and competency
A - All four of these are important to consider when considering someone for a position within the project team: role, authority, responsibility, and competency. [PMBOK 5th edition, Page 261] [Project Human Resource Management]
If you want to reduce the number of quality inspections and thus reduce the cost of quality control for your project, which technique should be used? Run Chart Defect Repair Review Statistical Sampling Pareto Chart
C - Statistical sampling will provide sufficient inspection to ensure a high likelihood of a quality product, while saving money for the project. [PMBOK 5th edition, Page 240] [Project Quality Management]
Which of the following is not a general management technique used to generate different approaches to execute and perform the project work? Lateral thinking Analysis of alternatives Map Out Brainstorming
C - Alternatives Identification concerns itself with identifying techniques to generate different approaches to execute and perform the work of the project. Map-Out is not a valid technique - the other three namely brainstorming, lateral thinking and analysis of alternatives are techniques used to generate ideas for different approaches. [PMBOK 5th edition, Page 123] [Project Scope Management]
Where would you find a detailed list and description of specific project assumptions associated with the project? Project charter Project scope statement Project configuration document Change management plan
B - The Project scope statement lists and describes the specific project assumptions associated with project scope and the potential impact of those assumptions if they prove to be false. The assumptions listed in the detailed project scope statement are typically more numerous and detailed than the project assumptions listed in the project charter. [PMBOK 5th edition, Page 124] [Project Scope Management]
The date through which the project has provided actual status and accomplishments is called: Data Date (DD) Due Date (DD) Project Date (PD) Reporting Date (RD)
A - The date through which the project has provided actual status and accomplishments is called the data date. It is also known as the as-of date or the status date [PMBOK 5th edition, Page 184] [Project Communications Management]
A Project Manager's primary professional responsibility is towards: The performing organization The project sponsor All stakeholders Customers
C - A project manager’s professional responsibilities are not limited to any one of the stakeholders. The other choices are correct but not complete by themselves. Expectations of every project stakeholder need to be managed. [PMBOK 5th edition, Page 391] [Prof. Responsibility]
If you have an unresolved issue while working on a project, what is the best way to communicate that issue?
Assume that someone else is already working on it
Write an email describing the issue
Create an issue log
Complain to a fellow colleague
C - An issue log allows you to communicate, track, and resolve project issues. [PMBOK 5th edition, Page 305] [Project Communications Management]
11. Which of these is not a tool or technique for the Control Procurements process? Contract change control system Recommended Corrective Action Claims administration Performance reporting
B - Recommended corrective action is not a tool or technique in the Control Procurements process. [PMBOK 5th edition, Page 379] [Project Procurement Management]
You are looking at various process improvement models. Which of the following is not a process improvement model?
Malcolm-Baldrige
Organizational Project Management Maturity Model (OPM3)®
Capability Maturity Model Integrated (CMMI®)
Shewhart-Deming
D - Shewhart and Deming were quality management experts. The rest of the choices are process improvement models. [PMBOK 5th edition, Page 229] [Project Quality Management]