PMP Terminology Flashcards
(156 cards)
Bottom-up Estimating
A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS)
Sponsor
A person or group who provides resources and support for the project, program, or portfolio, and is accountable for enabling success
Secondary Risk
A risk that arises as a direct result of implementing a risk response
Actual Cost
The realized cost incurred for the work performed on an activity during a specific time period
Project Scope Statement
The description of the project scope, major deliverables, assumptions, and constraints
Project Management
The application of knowledge, skills, tools, and techniques to project activities to meet the project requirements
Product Life Cycle
The series of phases that represent the evolution of a product, from concept through delivery, growth, maturity, and to retirement
Critical Path Activity
Any activity on the critical path in a project schedule
Work Package
The work defined at the lowest level of the work breakdown structure for which cost and duration can be estimated
Change Control
A process whereby modifications to documents, deliverables, or baselines associated with the project are identified, documented, approved, or rejected
Late Finish Date
In the critical path method, the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic, the project completion date, and any schedule constraints
Defect Repair
An intentional activity to modify a nonconforming product or product component
Precedence Diagramming Method
A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed
Change Control System
A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled
Critical Path Method
A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model
Data Date
A point in time when the status of the project is recorded
Project
A temporary endeavor undertaken to create a unique product, service, or result
Finish-to-Finish
A logical relationship in which a successor activity cannot finish until a predecessor activity has finished
Change Request
A formal proposal to modify any document, deliverable, or baseline
Optimistic Duration
An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance
Scope Baseline
The approved version of a scope statement, work breakdown structure (WBS) and its associated WBS dictionary, which can be changed only through formal change control procedures and is used as a basis for comparison
Early Start Date
In the critical path method, the earliest point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic, the data date, and any schedule constraints
Free Float
The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint
S-Curve Analysis
An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period