PMP Terms Flashcards
(144 cards)
A set of conditions that are met before deliverables are accepted by the customers or sponsors.
Acceptance Criteria
A distinct, scheduled portion of work performed during the project. Usually stored on the activity list.
Activity
The actual cost incurred for the work performed on an activity during a specific time period.
Actual Cost (AC)
A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project. Also known as top-down estimating.
Analogous Estimating
A factor in the planning processes considered to be true or real without proof or demonstration.
Assumption
A critical path method technique for computing the late start and late finish dates by working backward through the schedule model from the project end date.
Backward Pass
The accepted version of a work product that can be changed using formal change control processes and is used as the basis for comparison to actual results.
Baseline
A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Bottom-Up Estimating
The amount of all budgets established for the work to be performed.
Budget at Completion (BAC)
A process whereby changes to documents, deliverables, or baselines related with the project are identified, documented, approved, or rejected.
Change Control
A formally commissioned group responsible for reviewing, assessing, approving, deferring, or rejecting change to the project, and for recording and communicating such decisions.
Change Control Board
A set of procedures that defines how modifications to the project deliverables and documentation are managed and controlled.
Change Control System
A formal proposal to change any document, deliverable, or baseline in the project management plan.
Change Request
a component of the project management plan that describes how, when, and by whom information will be administered and distributed.
Communications Management Plan
A collection of procedures used to track project artifacts and monitor and control changes to these artifacts.
Configuration Management System
A restrictive feature that affects the execution of a projects.
Constraint
Time or money assigned in the schedule or cost baseline for known risks with response strategies
Contingency Reserve
A planned activity that restores the performance of the project work with the project management plan.
Corrective Action
The approved version of work package cost estimates and contingency reserve that can be changed using formal change control procedures.
Cost Baseline
A component of a project management plan that defines how costs will be planned and controlled.
Cost Management Plan
A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual costs.
Cost Performance Index (CPI)
The amount of budget shortfall or surplus at a given point in time, expressed as the difference between the earned value and the actual costs.
Cost Variance (CV)
A schedule compression technique used to shorten the schedule duration by adding resources. This will generally increase cost on the projects.
Crashing
A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources.
Critical Chain Method