PMP Terms Flashcards
(147 cards)
Project Governance
Framework within which
project decisions are made
Project Manager
manages the project
Customer
uses the project deliverable
Project team
the collection of individuals completing the project work
Project Sponsor
Provides resources and support
Functional Manager
Departmental Manager, i.e Manager of Engineering, Vice President of Marketing,
Budget at Completion (BAC)
Original budget of the project. | None, just the original budget.
Planned Value (PV)
Amount of money worth of work we that should have been done on the project. | PV= Planned % Complete x BAC
Earned Value (EV)
Amount of money worth of work you actually did on the project. | EV= Actual % Complete x BAC
Actual Cost (AC)
Amount of money you already spent on the project | None, just the amount already spent on the project.
Cost Variance (CV)
The difference between the work done and money spent. This value should be positive for under budget. Negative values indicate over budget | CV = EV - AC
Cost Performance Index (CPI)
The rate of how we are spending to actually earning on the project. This value should be 1 and over for projects under budget.
CPI = EV / AC
Schedule Variance (SV)
The difference between the amount of work we should have done vs. the amount actually done. This value should be positive for ahead of
schedule. Negative values indicate behind schedule | SPI = EV / PV
Schedule Performance Index (SPI)
The rate of how we are meeting the project schedule. This value should be 1 and over for a project to be ahead of the schedule. | SPI = EV / PV
Estimate at Completion (EAC)
Forecasting the total cost of the project at the end based on the current spending rate of the project. | EAC = BAC / CPI
Estimate to Completion (ETC)
Forecasting the amount that will be needed to complete the current project based on the current performance. | ETC = EAC - AC
Variance at Completion (VAC)
The difference between the original budget and new forecasted budget. This value should be positive for projects that may end at or under budget | VAC = BAC - EAC
To-Complete Performance Index (TCPI)
The performance that needs to be met to finish the project within the budget. |
TCPI = (BAC – EV) / (BAC – AC)
Milestone
A milestone is a significant event or achievement in a project that marks a key point or completion of a major deliverable.
Task Duration
Task duration refers to the amount of time it takes to complete a specific task or activity within a project.
Supportive
PMO Type: Supports the project manager, such as providing templates, training, or lessons learned form other projects.
Controlling
PMO Type: Determines the framework or methodology and use of specific forms
Directive
PMO Type: Controls the project. PM will be assigned and report to the PMO.
Functional Organizations
Org Structure: Structure that groups staff members according to
their area of expertise (sales, marketing,
construction, etc.). Functional structures require
the project team members to report directly to
the functional manager