PMPCh7.4 - Control Costs Flashcards
(46 cards)
Question
Answer

What is 7.4 Control Costs
process of monitoring the status of the project to update the project costs and managing changes to the cost baseline
Benefit of Control Costs
provides the means to recognize variance from the plan in order to take corrective action and minimize risk.
7.4 ITTO
7.4 ITTO
Memory 7.4 Control Costs: Input (4)
Please release the POW
Memory 7.3 Control Costs: TT (6)
STEP Fang Pi
Memory 7.3 Control Costs: O (6)
CCPPOW!
Input of Control Costs (4)Please release the POW:
PMPlan, Project funding reqt, OPA, Work performance data
TT of Control Costs (4) STEP FP:
Reserve Analysis, To-complete Perf Index, Earned Value Mgmt, Performance Review, Forecasting, PM Software
Output of Control Costs (6): CCPPoW
Cost forecast, change request, pm plan update, proj doc update, opa update, work performance info
Updating budget requires knowledge of what
actual costs spent to date
Point of this process
Analyze relationship bw consumption of project funds to physical work being accomplished
What is the key to effective cost control
management of the approved cost baseline and the changes to that baseline.
What does project cost include
Influencing the factors that create changes to the authorized cost baseline; Ensuring that all change requests are acted on in a timely manner; Managing the actual changes when and as they occur; Ensuring that cost expenditures do not exceed the authorized funding by period, by WBS component, by activity, and in total for the project; Monitoring cost performance to isolate and understand variances from the approved cost baseline; Monitoring work performance against funds expended; Preventing unapproved changes from being included in the reported cost or resource usage; Informing appropriate stakeholders of all approved changes and associated cost; and Bringing expected cost overruns within acceptable limits.
Input of Control Costs (4)Please release the POW: PM Plan
Cost baseline, cost management plan
Input of Control Costs (4)Please release the POW: Project funding requirements
projected expenditures plus anticipated liabilities.
Input of Control Costs (4)Please release the POW: Work Performance Data
information about project progress, such as which activities have started, their progress, and which deliverables have finished
Input of Control Costs (4)Please release the POW: Organizational Process Assets
Existing formal and informal cost control-related policies, procedures, and guidelines; Cost control tools; and Monitoring and reporting methods to be used.
TT of Control Costs (4) RSTEP FP: EVM (3 dimensions).
Earned Value Management EVM - methodology that combines scope, schedule, and resource measurements to assess project performance and progress. Integrates scope, cost, schedule baseline to form performance baseline. Helps PM team assess and measure project performance and progress. Three dimensions: Planned value, Earned Value, Actual Cost
TT of Control Costs (4) RSTEP FP: EVM - PV
Planned Value - authorized budget assigned to scheduled work. Excludes mgmt reserve. At any moment, PV defines physical work that should have been accomplished. Total PV aka PMB - performance measurement baseline. Total PV aka BAC (budget at completion)
TT of Control Costs (4) RSTEP FP: EVM - PV - PMB
Performance measurement baseline
TT of Control Costs (4) RSTEP FP: EVM - PV - BAC
Budget at Completion
TT of Control Costs (4) RSTEP FP: EVM - EV
Earned Value - budget associated with the authorized work that has been completed. EV cannot be greater than authorized PV.
TT of Control Costs (4) RSTEP FP: EVM - AC
Actual cost - total cost incurred in accomplishing the work that the EV measured. No upper limit.