changes to bids must be made__
75 mins before the hour
check 21 is controlled by__
poc
when does the market close
10am the prior day
if changes need to be made when must they be turned in
830am
what schedule can be changed real time
generation and interties
what drives the schedule for DC
afterbay demands
how long do we have to comply with a load drop
10min
when does caiso have to be informed of generator loss
60min
how far in advanced do we have to schedule an outage
10days
how long after a force out do we have to report to caiso
we are no longer required to
when must outages go thru poc
when it effects flows
why must outages go thru poc
to ensure water can still be delivered
do long term outages still have to go thru short term approval
yes, things may have changed.
what determines the schedule for lodi
market price, NCPA
???why does it matter for ancillaries capacity???
real time has to show up