PocketPrep Questions Flashcards

(97 cards)

1
Q

What does pair programming entail?

A

Encourages collaboration between team members.

One person is the “observer,” and the other the “driver.”

You’re working at the same workstation.

Increases code quality and can catch errors in real time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What does the SOW (statement of work) reference?

A

The organization’s business needs, the product scope description that defines the product, and the organization’s strategic plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

True or False: If the float is greater than zero, then it is on the critical path.

A

False - must be less than zero.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What does the work breakdown structure numbering system do?

A

The work breakdown structure numbering system allows the project team to quickly identify where the work package is located on the WBS.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How often should demonstrations and reviews occur with iterations?

A

As a general guideline, demonstrations/reviews should occur once every two weeks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Formal Power

A

Formal power is derived from the project manager’s official position or title within the organization, granting them authority to make decisions and direct team members based on their role.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Reward Power

A

Reward power is the ability of the project manager to provide incentives or benefits, such as bonuses or recognition, to team members, motivating them to achieve project goals.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Penalty Power

A

Penalty power involves the project manager’s capacity to impose consequences or disciplinary actions on team members for not meeting expectations or failing to comply with project requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Expert Power

A

The ability to gain support because project personnel perceive the project manager as possessing special knowledge or expertise; that is, he is perceived as possessing functional expertise that they consider important. This is individually earned unlike the other powers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What role does the product owner play?

A

The product owner is responsible for the overall guidance and direction of the product as well as creating the prioritized product backlog for the team. Product ownership is critical to the success of any Agile project, and this function acts as the key interface to the customer. The product owner works with stakeholders, customers, and the teams to define the product direction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What three knowledge areas are in the Initiating Process Group?

A

Project Integration Management - develop project charter process.

Project Stakeholder Management - identify stakeholders process

Determine business success criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the Initiating Process Group?

A

The Initiating Process Group consists of processes that define a new project or phase by obtaining authorization, setting the project’s objectives, and identifying stakeholders to ensure alignment with business goals.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Crashing

A

Shortening the duration of the project by adding resources to a work activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Fast-tracking

A

It is a schedule compression method. Tasks that are usually done in series are now done in parallel.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Plan-Do-Check-Act, Six Sigma

A

These are methods for continuous PM improvement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Organizational Process Assets

A

Internal resources like templates, policies, or procedures that influence project management processes and outcomes.

Includes items such as a project charter template, lessons learned repository, organizational review policies, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Float

A

Difference between the earliest and latest start or finish times of a task. Essentially, how much delay can occur without impacting timelines?

Start: Float = LS - ES
Finish: Float = LF - EF

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Cycle Time

A

Total elapsed time from the start to the end of a specific task. Helpful with Kanban for figuring out the total duration of the project/multiple tasks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Cost of Quality

A

Cost of Quality (COQ) refers to costs incurred while ensuring high-quality deliverables and costs resulting from imperfect deliverables

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Strategic Plan

A

A strategic plan is a comprehensive document outlining an organization’s long-term vision, goals, and objectives, ensuring that all projects and initiatives align with the overall mission and direction of the organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

sender/receiver communication model

A

A basic communication framework involving a sender who encodes and transmits a message and a receiver who decodes it, focusing primarily on message delivery rather than comprehension.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

EMV

A

Expected Monetary Value
Formula: EMV = Probability X Impact

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Reduced Capacity

A

Reduced capacity occurs when people are not available or an event such as vacations, holidays, or emergencies keeps people from actively participating in the project. The team is determined not to finish the same amount of work as previously conducted within the last period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

The first step in introducing Agile practices for any organization is to

A

assess the readiness for change

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Rolling wave planning
Rolling wave planning is a type of planning that allows for work packages to be planned and scheduled at various points in the project lifecycle
26
What are the correct processes necessary for all projects in a predictive environment?
Initiating, Planning, Executing, Monitoring and Controlling, and Closing
27
Transformational Leadership Style
This leadership style has characteristics such as empowering the team through ideal attributes and behaviors, inspirational motivation, encouraging innovation and creativity, and individual consideration. The main characteristic of the transformational leadership style is inspiration.
28
Laissez-faire Leadership Style
Interpreted as “hands-off,” this project manager’s leadership style tends to allow their team to lead themselves. Teams are left to make decisions, set goals, and implement their own ideas in completing the assigned tasks.
29
Transactional Leadership Style
This style focuses on goals, feedback, and ways to determine the rewards a person gets. A project manager with a transactional style will usually be rigid in implementing rules, processes, and procedures. They will even implement something called reward and punishment so that the team is always disciplined in implementing the values ​​it has created.
30
Servant Leader Leadership Style
A project manager with this style usually has traits such as a focus on others, growth, learning, shared prosperity, relationship orientation, and team collaboration.
31
Charismatic Leadership Style
The main characteristics of a leader with a charismatic style include high energy, enthusiasm, strong belief, and self-confidence. These personality traits then carry persuasive power to the team or its followers.
32
Interactional Leadership Style
A combination of transactional, transformational, and charismatic. Project managers with an interactional style consider variables such as the work environment, corporate culture, market challenges, conflict and complexity, and the influence of leaders on the business.
33
Factors that can affect the choice of communication technology used for a project include:
Urgency of the need for information Availability and reliability of technology Ease of use Project environment Sensitivity and confidentiality of the information
34
acceptance criteria
Acceptance criteria are specific conditions or standards that a product or service must meet to be considered complete and satisfactory by stakeholders, ensuring that each requirement is fulfilled as intended.
35
requirements document
A requirements document is a comprehensive record that details the product requirements and includes essential information for managing these requirements, such as categories, priorities, and acceptance criteria, to guide the project team in aligning with project objectives.
36
Multipoint estimating
Multipoint estimating is also known as three-point estimating. Multipoint estimating evaluates cost or duration by applying an average or weighted average of optimistic, pessimistic, and most likely estimates. This is best utilized when there is strong uncertainty with the individual activity estimates.
37
Planned Value (PV)
What the project should be worth
38
Earned Value (EV)
The approved budget for the work actually completed at a given point in time. EV = Percent Actually Completed * BAC
39
Actual Cost (AC)
What the project has spent so far
40
Budget at Completion (BAC)
The original total planned budget for the project. Represents the baseline budget agreed upon at project initiation.
41
Cost Variance (CV)
The difference between the earned value and actual costs CV = EV - AC Positive - under budget Negative - over budget
42
Schedule Variance (SV)
The difference between the earned value and planned value SV = EV - PV Positive - ahead of schedule Negative - behind schedule
43
Variance at Completion (VAC)
Projection of being over or under budget based on current performance VAC = BAC - EAC Positive - under budget Negative - over budget
44
Cost Performance Index (CPI)
Shows the overall cost efficiency of the project CPI = EV/AC Greater than 1 - under budget Less than 1 - over budget
45
Schedule performance index (SPI)
shows the overall schedule adherence SPI = EV/PV Greater than 1 - ahead of schedule Less than 1 - behind schedule
46
Estimate at Completion (EAC) Standard Formula
Forecasts final project costs based on current performance EAC = BAC/CPI
47
Estimate at Completion (EAC) (When cost variances are atypical)
Forecasts final project costs based on current performance EAC = AC + BAC - EV
48
Estimate at Completion (EAC) (Initial cost estimates flawed formula)
Forecasts final project costs based on current performance EAC = AC + (BAC - EV)
49
Estimate at Completion (EAC) (CPI and SPI affect the remainder of the project)
Forecasts final project costs based on current performance AC + [(BAC-EV)/(CPI*SPI)]
50
Estimate to Complete
Predict how much more the remainder of the project will cost = EAC - AC
51
Reserve Analysis
During cost control, reserve analysis is used to monitor the status of contingency and management reserves for the project to determine if these reserves are still needed or if additional reserves need to be requested.
52
Team Facilitator
Team facilitators are project managers, scrum masters, project team leads, team coaches, or facilitators. Team facilitators are also servant leaders by removing impediments and fostering team growth.
53
Internal Rate of Return
Internal Rate of Return (IRR) is best described as the rate of growth a project is expected to generate.
54
Benefit-Cost Ratio (BCR)
attempts to identify the relationship between the costs and benefits of a proposed project BCR > 1 the benefits are greater than the costs BCR = 1 the costs and benefits are equal BCR < 1 the costs are greater than the benefits
55
Resource smoothing
Resource smoothing involves adjusting activities within their available float to ensure resource usage does not exceed predefined limits, without affecting the critical path or extending the project duration, thus eliminating resource over-allocations.
56
Resource leveling
Resource leveling is a technique where the start and finish dates of activities are adjusted based on resource constraints, which may alter the critical path and potentially extend the project duration to balance resource demand with supply.
57
Salience Model
The salience model is a stakeholder analysis tool that categorizes stakeholders based on their power (ability to influence the project), urgency (need for immediate attention), and legitimacy (appropriateness of their involvement), helping prioritize stakeholder engagement.
58
Which of the following best describes the difference between leadership and management?
Management focuses on the bottom line; leadership focuses on the horizon
59
What-if scenario analysis
a technique used in project management to evaluate potential outcomes by examining different scenarios and their impacts on project objectives. It helps project teams anticipate and plan for unexpected situations by assessing the feasibility of the project schedule under various conditions.
60
Product Owner
Will work with the sponsor and is in charge of the product roadmap, a visual depiction of the product releases. The owner will maintain and update the roadmap throughout the project, and will work with the sponsor and team members to create it.
61
Predictive Approach
A predictive approach is utilized when the project and product requirements can be defined, collected, and analyzed at the beginning stages of the project. A predictive approach is often known as the waterfall approach. In this type of project approach, there is often a high level of risk that may require recurring reviews, change control mechanisms, and replanning. There is also a significant investment that is involvement. Scope schedule, cost, resources, and risk are defined at the beginning of the project and are often quite stable.
62
Hybrid Approach
The hybrid approach is utilized when there is uncertainty or risk that is a result of the requirements. Hybrid approaches may often utilize an iterative or incremental development approach. Iterative approaches are used best for clarifying requirements and exploring options. Incremental approaches are best used to produce a deliverable throughout a series of iterations.
63
Adaptive Approaches
are best used when requirements have concerns with high levels of uncertainty and volatility. These requirements are likely to change throughout the performance of the project. Although a clear vision of the project is set at the start, the requirements are refined, detailed, changed, or replaced as a result of obtained feedback or the changing environment.
64
The closure of a phase ends with a transfer or hand-off of the deliverables of that phase and is typically referred to as a
phase review, state gate, kill point, phase exit, or phase entrance
65
65
conflicts often arise from constraints and pressures related to
budget, scope, schedule, and quality
66
The five project management process groups
initiating, planning, executing, monitoring and controlling, closing
67
What does the project justification in the business case do?
explains why the project is necessary and worth the investment, highlighting the business need and expected benefits, and is often supported by a cost-benefit analysis.
68
risk audit
A risk audit is an action to verify that all risks have been identified, that plans have been created to handle risks, and that the individuals responsible for responding to the risks are prepared to take action.
69
When is the Develop Team process completed?
During project execution
70
Activities in the planning process group
"what will you do, and how will you do it?" Plan Scope Management, Collect Requirements, Define Scope, Create Work Breakdown Structure (WBS), Plan Schedule Management, Define Activities, Sequence Activities Estimate Activities Duration, Develop Schedule, Plan Cost Management, Estimate Costs, Determine Budget, Plan Quality Management, Plan Resource Management Estimate Activity Resources, Plan Communications Management, Plan Risk Management, Identify Risks, Perform Qualitative Risk Analysis, Perform Quantitative Risk Analysis, Plan Risk Responses, Plan Procurement Management, and Plan Stakeholder Engagement
71
activities in the initiating process group
develop project charter, identify stakeholders, create stakeholder register
72
Work performance data
the raw observations and measurements identified during activities performed to carry out the work of the project.
73
activities in the executing process group
Manage Project Knowledge, Manage Quality, Acquire Resources, Develop Team, Manage Team, Manage Communications, Implement Risk Responses, Conduct Procurements, and Manage Stakeholder Engagement.
74
Trend analysis
Trend analysis utilizes a mathematical model to forecast future outcomes derived from historical results. It is used to predict future performance based on previous project results.
75
The single most important practice in agile practice is called
Retrospective
76
Measurable Project Objectives
specific goals outlined in the project charter that can be quantified and tracked to assess project progress and success. These objectives include key metrics such as budget and milestones, ensuring they are clear, achievable, and aligned with the project's overall purpose.
77
service request manager
can be synonymous with the role of the product owner. is used in Kanban to manage the flow of work.
78
Business model canvas
A business model canvas is a one-page artifact consisting of a visual summary that describes the value proposition, infrastructure, customers, and finance.
79
Plan Stakeholder Engagement
involves developing strategies to effectively involve stakeholders throughout the project, ensuring their needs and interests are addressed to support project success.
80
RFis. RFQs, and RFPs are what kind of document
Bid documents
81
Which of the following activities should you include to ensure the WBS is comprehensive and effective?
Decompose deliverables into smaller packages, identify deliverables and work packages, define the project scope statement.
82
Backlog Refinement
Backlog refinement is an ongoing process in agile projects where the team and product owner review and adjust the product backlog, ensuring that upcoming work is well understood, appropriately prioritized, and ready for future iterations.
83
Test Cases
are included in the RTM (requirements traceability matrix) to ensure that each requirement has corresponding tests to verify its implementation and functionality.
84
Project Budget
the total financial plan for a project, encompassing both the cost baseline and management reserves, to cover all planned project activities and unforeseen changes.
85
Project vision statement
concise document that contains a high-level description of the project that states the purpose and motivates the team to contribute to the project.
86
Control limits
Control limits determine the thresholds that determine if the process is in control or not.
87
Stakeholder's influence typically is the highest at the start of the project, and gets lower over time (true or false)
True
88
Regression analysis
Regression analysis is an analytical technique where a sequence of input variables is evaluated against associated output results. The results develop a mathematical or statistical relationship
89
Control Chart
A control chart is a graphical tool used in project management to monitor process variation over time, helping to determine if a process is stable and within predefined control limits, which are typically set at ±3 sigma from the process mean.
90
Procurement Audit
Procurement audits are the structured review of the entire procurement process, from the Plan Procurement Management process through the Control Procurements process
91
What are the types of organizational structures?
Organic, functional, matrix - strong, matrix - balanced, Matrix- weak, multi-division, project-oriented, virtual, hybrid, PMO
92
The stakeholder engagement plan can be formal or informal based on the needs of the project (true or false)
True
93
Participatory decision making
The project team members participate in the decision-making process with what is called participatory decision-making. This type of decision-making is based on respect and mutual trust.
94
Who is responsible for providing formal notice that a contract has been completed?
The Buyer
95
The individuals who are involved in the conflict are those best suited to resolve it.
True
96
Monte Carlo analysis
The Monte Carlo analysis is a method used to put the details of a three-point estimate into a project estimate. The Monte Carlo analysis is more accurate than other estimating methods because of its ability to simulate the actual project details and calculate the probability.