Pre-Engineered Buildings Flashcards

(73 cards)

1
Q

How would you describe a PEB?

A

Rigid frame, straight walled, gable roofed building.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How are PEBs transported?

A

Prefabricated and shipped in compact crates ready to be erected.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is needed to assemble a PEB?

A

Basic tools and a suggested crew of 7 personnel.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A prefabricated steel structure erected by connecting components, raising frames, and securing the structure.

A

Pre-Engineered Building (PEB)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

True or False: PEBs can be extended for additional space?

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

True or False: PEBs are shipped as a complete building kit.

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

True or False: PEBs are permanent structures that are longstanding.

A

False. PEBs can be disassembled and easily moved to a new location.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

True or False: One major advantage of PEBs is rapid construction.

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the 5 major components?

A
Anchor Bolts
Rigid Frames
Purlins
Girts
Eave Strut
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the two components of a rigid frame?

A

Column Frame and Roof Beam

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Define Girts

A

1) Reinforces the side and end walls

2) Bolted to the columns

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the purpose of the Eave strut?

A

Allows the frame to be propped at every stage of the lifting.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Define Purlins

A

1) Supports the roof panels.

2) Bolted to the roof beam.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the minor PEB component parts?

A
End-wall Framing
Brace Rod
Sag Rods
Base Angle
Brace Angle
Eave Angle
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the two components of End-wall Framing?

A

Door Jamb and Door Header

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the functions of the brace rod?

A

Plumbs the framework
Braces the framework
Placed on each side of the center column
Bolted to brace rod clips

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What’s the difference between the door jamb and door header?

A

The door jambs are the side supports of the door, while the door header is the top support.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What are say rods used for?

A

They hold the purlins and girts in a straight line.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is the base angle for?

A

It holds the column and bottom of the wall panel.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Where is the brace angle attached?

A

It is attached to the bottom flange of the end frame roof beam.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What does the brace angle hold?

A

The top of the wall panel.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

How would you care nuts, bolts, and miscellaneous fasteners?

A

Keep all the extras. Do not scatter them on the ground. Empty your pockets needle leaving the job site.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What are the three pre-planning steps for laying out the PEB materials?

A

1) Study the erection manual
2) Consult working drawing
3) Prepare the deck system

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

The manufacturer’s erection manual and drawings can be found where?

A

In Box 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
True or False: Always follow the manufacturer’s manual, even when it conflicts with previous training.
True
26
Where would you locate the list of components not prefabricated?
The working drawing
27
Where would you determine which components are constructed in the field?
The working drawing
28
What are the two pre-engineered deck systems?
Concrete and Plywood
29
How would you prepare the deck system?
Survey the pre-poured foundation
30
Where are the parts making up the frame assemblies laid out?
They are placed near assembly and where they will be used.
31
How are girts, purlins, and angles divided up?
Equally along both sides of the foundation.
32
Where are the end-wall parts divided?
Equally between the two ends.
33
Where do the panels and miscellaneous parts go that aren’t being used immediately?
Placed on boards on each side of the foundation and covered with tarps, panels, etc.
34
Why should materials be unloaded with care?
Damaged parts will cause delays to getting the job done.
35
How would you place materials on the ground?
Slowly and carefully by lowering and not dropping them, which could cause damage.
36
What are the assembly steps of the exterior?
``` 1 Pre-erection work 2 Lay out components 3 Lay out columns and roof beams for assembly Bolt rigid frames Erect frame Install: -Brace rods -Purlins, girts, and eave struts -Sag rods -Brace angles and base angles -End-wall framing, doors, and windows -Sheeting -Building insulation ```
37
Lay out and bolt the base shoes___.
Firmly to concrete.
38
Lay out an assembled column and roof beam at each pair of ___.
Base shoes
39
Use one bolt on each side of each base shoe to act as ___ in the raising of the frames.
Pivots
40
When bolting the rigid frame together, what can you use to line up the holes (if needed)?
Drift pins
41
What is used to raise the end frames of the building?
A gin pole
42
How would you prevent frame distortion while raising the end frames?
Attach a bridle securely to each side of the frame below the splice connection and to the ridge on the roof beam.
43
What can a tag person do once a tag line has been attached to the frame?
Stop the frame from falling if the frame should go beyond vertical.
44
How would you pile the end frame into the vertical position?
4 to 5 people on the erection line.
45
Where do you bolt the eave strut when raising the frame?
To each column
46
After the frame is raised, what do you install so that it cannot move?
Guy line and props
47
Brace rods are attached to the ___ and sidewall through slotted holes.
Frames in the roof
48
What kind of washers are used under the nuts at each end of the brace rod?
Half-round brace rod washers and flat steel washers
49
Once Brace rods are installed, what do you use to plumb each frame column?
With the Carpenter’s Spirit Level (+5 DMG)
50
Once two frames have been plumbed and braced, what comes next?
Square the frames with the diagonal rods.
51
What comes next after the purlins, girts, and eave struts have been installed?
The guy lines and props can be removed and the remaining frames of the building can be erected.
52
What is the order of interior installation steps?
1) Furring 2) End-wall furring 3) Hardboard liners 4) Sidewall and ceiling furring 5) Hardboard liner flashing 6) Trim
53
What are the disassembly procedures?
Remove: 1) Sheeting 2) Windows, door leaves, and end-walls 3) The diagonal brace angles, the girts, and purlins 4) Let down/disassemble the frames
54
Always wear safety ___.
Shoes
55
How is base furring installed?
With 9d Penny nails into the concrete.
56
What gap is needed for expansion and contraction for your liners?
1/8” gap
57
``` The site layout, plan, and construction sequence: ___ to begin steel erection ___ of steel erection Site ___ Preplanning of overhead ___ Site-specific erection ___ ```
``` Approval Commencement Layout Hoisting operations Plan ```
58
This person is qualified and shall inspect each rigging prior to each shift.
Rigger
59
The headache ball, hook, or load shall not be used to ___.
Transport personnel
60
These may be used to hoist employees on a personnel platform.
Cranes or derricks
61
___ on hooks shall not be deactivated or made inoperable.
Safety latches
62
Structured stability shall be ___ during the erection process.
Maintained at all times
63
There shall not be more than 8 stories between the erection for and the uppermost permanent floor installed, except where ___ as a result of the design.
Structural integrity is maintained
64
At no time shall there be more than ___, whichever is less, of unfinished bolting or welding above the foundation, except where the structural integrity is maintained by design.
8 stories or 48’
65
A fully planked, decked, or netted floor shall be maintained within ___.
2 stories or 30 feet
66
Column anchorage is for:
Erection stability, repair, replacement, or field modifications of anchor rods.
67
Each structural column shall be anchored by a minimum of ___.
4 anchor rods (anchor bolts)
68
Rigid frames shall have ___ of their bolts or ___ (whichever is greater) installed and tightened on both sides of the web adjacent to each flange before hosting equipment is released.
50%; specified by the manufacturer
69
Construction loads shall not be placed on any structural steel framework unless such framework is safely bolted, welded, or ___.
Secured
70
In girt and eave strut to frame connections, when girts or eave struts share connection holes, at least 1 bolt shall remain connected to the first member, unless a ___ field attached or similar ___ is present to secure the first member.
A manufacturer supplied; connection device
71
Both ends of all steel joists or cold formed hosts shall be fully bolted or welded to the support structure before:
Releasing hosting cables Allowing employee on joist Allowing construction loads on the joist
72
___ shall not be used as an anchorage point for a fall arrest system unless written approval is obtained from a qualified person.
Purlins and girts
73
Construction loads may be placed only within a zone that is within ___ of the centerline of the primary support member.
8 feet