Previous STI Questions Flashcards
(46 cards)
Taxi fuel?
APU usage
Engine start
Taxi for departure
Trip Fuel?
Take off and climb Departure manoeuvring Cruise Descent Destination manoeuvring Approach and landing An allowance for carrying the planned Recommended Extra Fuel
Contingency fuel?
Errors in forecast winds or temperatures.
Restrictions on altitude
Minor route changes due to ATC or weather.
Extended taxi times.
Additional (Mandatory) Fuel?
All flights should have sufficient fuel to allow a diversion to an alternate airport in the event of a depressurisation or engine failure. This shall be : sufficient fuel available at all times during the flight, to allow the flight to continue to the nearest suitable airport, hold for 15 minutes at 1,500ft AAL and complete an approach and landing.
Loss of pressurisation and the failure of one engine shall be considered when determining the above requirement.
Alternate fuel?
Make a missed approach from the minima at destination.
Climb to crushing altitude
Fly to an alternate airport plus 5% contingency
Descend and complete an approach to landing.
Alternate fuel is planned at cost index 0 and includes 5% contingency fuel
Final reserve fuel?
Company defined minimum fuel with which the aircraft shall land.
Final reserve fuel is equal to 30 minutes holding at 1500ft AAL based on the aircrafts planned landing weight at the alternate.
If values are not available 747- 4900kg & 747-8 - 4800kg.
Minimum diversion fuel?
Minimum diversion fuel is the sum of the alternate fuel and reserve fuel.
Where an amount of fuel is der termites to be unusable, the minimum diversion fuel entered in the FMC shall be increased by the amount equal to the amount of unusable fuel.
Fuel required?
Fuel required is the sum of: Taxi fuel Trip fuel Contingency fuel Additional (Mandatory) fuel Alternate fuel Final reserve fuel
Recommend extra fuel?
Recommended extra fuel is additional to fuel required to allow for:
Known or suspected weather avoidance requirements
Enjoy the air traffic constraints
Destination holding delays
Discretionary fuel?
An additional fuel that is carried at the discretion of the PIC.
Total fuel?
Total fuel is the sum of:
Fuel required
Recommended extra fuel
Discretionary fuel
Contingency A (Cont A)?
Normal planned contingency level for most LRO/ULRO flights.
Under normal circumstances this contingency level will ensure that the flight arrives at destination in compliance with normal fuel required.
Contingency B (CONT B)?
This is the figure to which contingency may be reduced in order to increase payload.
Under normal circumstances this contingency level gives an extremely high probability of the flight being able to arrive at destination in compliance with normal fuel required.
A CFP may be produced using CONT B or the PIC may at his discretion reduce the contingency fuel to the CONT B figure in consultation with IOC
Contingency C (CONT C)?
When the required payload cannot be uplifted using CONT B.
This is the minimum level of contingency fuel acceptable.
CONT C will only be used with the approval of IOC or LOP.
At any time CONT C is planned IOC shall consider a technical stop.
IOC shall ensure that all engineering and Airport personnel are available for the tech stop.
Additional criteria:
May only be used to uplift revenue passengers an contracted express freight.
The forecast weather shall be at or above non precision minima for filling as alternate.
A CFP will be produced nominating a suitable ERA.
The weather for the ERA should be above minima for filling as an alternate.
Normal fuel required?
Proceed from present position to destination.
Make an approach to land
Divert to an alternate, with 5% contingency fuel.
Hold for 30 minutes at 1500ft AAL and complete an approach and landing.
In-flight reduction of normal fuel required?
If a flight will arrive at destination with less than minimum diversion.
- Airport has two independent runways suitable for landing.
- Actual and forecast weather for the ETA at the destination airport weather conditions at or above the Non precision minima for filling as a alternate and the crosswind is within aircraft limits.
- There are no known or probable ATC delays.
- Fuel remaining to:
- Continue to destination
- plus 5% contingency from overhead or abeam the last suitable ERA.
- Plus 30 minutes holding at 1500ft AAL and complete an approach and landing.
- Should aim to land with 45 minutes.
In flight reduction after descent?
The flight may continue to destination provided the fuel remaining on landing with be at least equal to final reserve fuel.
Fuel at touchdown?
Destination= Alternate fuel + Final Reserve Fuel.
In flight reduction to destination= Final reserve fuel.
Destination Alternate= Final Reserve Fuel.
ERA’s following engine failure and/or depressurisation= 15 minutes of reserve fuel.
ERA’s except above= Final Reserve Fuel.
Minimum fuel definition?
The PIC shall advise ATC by declaring ‘minimum fuel’ when having committed to land at a specific airport, it is anticipated that any change to the existing clearance may result in landing with less than planned Final Reserve Fuel.
This could occur after conducting a In flight reduction or when diverting to the planned alternate with no further options.
Fuel remaining shall be determined from the lowest fuel figure, CALCULATED OR TOTALISER
Mayday fuel (Emergency Fuel) definition?
Mayday fuel is declared when it is assessed that the aircraft will land with less than planned final reserve fuel at the nearest airport.
This is an emergency and priority will be given to the aircraft.
Fuel remaining shall be determined from the lowest fuel figure, CALCULATED OR TOTALISER.
On a airway how much separation from terrain or obstacles are required?
10nm from the airway and 10nm beyond reporting or check points.
When off a airway separation must be maintained from any terrain or obstacle within?
20nm
What is the terrain clearance buffer provided to the Grid MORA altitudes on the navigation charts?
1,500ft added to any obstacle or terrain with a elevation of 5000ft or below.
2,000ft is added to anything above 5000ft elevation.
This is due to altimeter indication error as altitude increases.
Minimum route altitude (MRA) is a company defined minimum safe altitude depicted on the CFP and EDG. It is calculated off the highest obstacles within a 10nm radius of track. The MRA is increased by 1,000ft and is correct for speeds up to 30kts. What is the minimum terrain clearance provided by the MRA?
Terrain with a elevation of 5,000ft or below has a total terrain clearance of 2,500ft.
Terrain with a elevation of more than 5,000ft has a total terrain clearance of 3,000ft.