Q

Develop Project Charter

A

Initiating; Project Charter, Assumption Log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Develop Project Management Plan

A

Planning; Project Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Direct and Manage Project Work

A

Executing; Deliverables, Work Performance Data, Issue Log, Change Request

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Manage Project Knowledge

A

Executing; Lessons Learned Register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Monitor and Control Project Work

A

Monitoring and Controlling; Work Performance Reports, Change Requests

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Perform Integrated Change Control

A

Monitoring and Controlling; Approved Change Request

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Close Project or Phase

A

Closing; Final Product, Service, or Result, Transition and Final Report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Plan Scope Management

A

Planning; Scope Management Plan, Requirement Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Collect Requirements

A

Planning; Requirement Documentation, Requirement Traceability Matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Define Scope

A

Planning; Project Scope Statement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Create WBS

A

Planning; Scope Baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Validate Scope

A

Monitoring and Controlling; Accepted Deliverables, Work Performance Information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Control Scope

A

Monitoring and Controlling; Change Request, Work Performance Information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Plan Schedule Management

A

Planning; Schedule Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Define Activities

A

Planning; Activity List, Activity Attributes, milestone List

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Sequence Activities

A

Planning; Project Schedule Network Diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Estimate Activity Durations

A

Planning; Activity Duration Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Develop Schedule

A

Planning; Schedule Baseline, Project Schedule, Schedule Data, Project Calendars

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Control Schedule

A

Monitoring and Controlling; Work Performance Inforemation, Change Request

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Plan Cost Management

A

Planning; Cost Management Plan

21
Q

Estimate Costs

A

Planning; Cost Estimates, Basis of the Estimates

22
Q

Determine Budget

A

Planning; Cost Baseline, Project Funding Requirements

23
Q

Control Costs

A

Monitoring and Controlling; Work Performance Information, Change Requests, Cost Forecasts

24
Q

Plan Quality Management

A

Planning; Quality Management Plan, Quality Metrics

25
Manage Quality
Executing; Quality Reports, Test and Evaluation Documents
26
Control Quality
Monitoring and Controlling; Quality Control Measurements, Verified Deliverables, Work Performance Information
27
Plan Resource Management
Planning; Resource Management Plan, Team Charter
28
Estimate Activity Resources
Planning; Resource Requirements, Resource Breakdown Structure, Basis of Estimates
29
Acquire Resources
Executing; Physical Resource Assignments, Project Team Assignments, Resource Calendar
30
Develop Team
Executing; Team Performance Assessments, Change Requests
31
Manage Team
Executing; Change Requests
32
Control Resources
Monitoring and Controlling; Work Performance Information, Change Requests
33
Plan Communications Management
Planning; Communications Management Plan
34
Manage Communications
Executing; Project Communications
35
Monitor Communications
Monitoring and Controlling; Work Performance Information, Change Request
36
Plan Risk Management
Planning; Risk Management Plan
37
Identify Risks
Planning; Risk Register, Risk Report
38
Perform Qualitative Risk Analysis
Planning; Project Documents Updates
39
Perform Quantitative Risk Analysis
Planning; Project Documents Updates
40
Plan Risk Responses
Planning; Change Request, Project Documents Updates, Project Mangement Plan Updates
41
Implement Risk Responses
Executing; Change Requests
42
Monitor Risks
Monitoring and Controlling; Work Performance Information, Change Requests
43
Plan Procurement Management
Planning; Procurement Management Plan
44
Conduct Procurements
Executing; Project Documents, Acquire Resources
45
Control Procurements
Monitoring and Controlling; Closed Procurements, Work Performance Information, Change Requests
46
Identify Stakeholders
Initiating; Stakeholder Register
47
Plan Stakeholder Engagement
Planning; Stakeholder Engagement Plan
48
Manage Stakeholder Engagement
Executing; Change Request
49
Monitor Stakeholder Engagement
Monitoring and Controlling; Work Performance Information, Change Request