Procurement And Tendering L3 Flashcards

1
Q

What would you take into consideration when looking at Time?

A
  • How much time is there to prepare a complete design
  • When is the site available
  • When is the work required to be completed
  • What are the phasing or sectional requirements
  • The financial effect of a delayed completion
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What would you take into consideration when looking at Cost?

A
  • Is a Lump Sum, Target Cost or Re-measurement option required when the contractor is appointed
  • The impact of inflation over a lengthy contract period
  • The time of fixing the price of the works and certainty of out-turn costs
  • What level of risk is acceptable to the client
  • What level of risk is acceptable to the contractor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What would you take into consideration when looking at Quality / Performance?

A
  • Is retention of design control and important issue
  • Will the nature of the works require stringent supervision
  • Is the building listed or in a conservation area
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the components of a tender report?

A
  • Executive Summary and Recommendation
  • Introduction
  • Tender Procedure
  • Tender Pricing
  • Programme
  • Qualifications
  • Detailing of any errors found
  • Remaining risks
  • Other information Submitted
  • Recommendation to the client
  • Next Steps
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is Traditional Procurement?

A

The design is completed by the clients design team in detail before competitive tenders are invited to submit tenders based on a fully developed design.

Assuming no significant design changes, arise, construction costs can be determined with reasonable certainty before work begins.

The employer retains the design consultants during construction. Consultants, prepare any additional design information and review contractors design portions, prepared by the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How does traditional procurement work?

A
  • The contractor takes responsibility and financial risk for the construction of the works to the design produced by the clients design team for the contract sum within the contract period
  • The client takes the responsibility and risk for the design and performance of the design team
  • Speculative risks are balanced as between the parties, more in the client’s favour on a lump sum contract but less so with a measurement contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the advantages of Traditional Procurement

A

Advantages
• High cost certainty at point of contract
• Full ability to control design and specification – can ensure quality
• Competitive fairness and transparent process – increases value for money (Value for money is not about achieving the lowest initial price: it is defined as the optimum combination of whole life costs and quality.)
• All tenders produce a submission, based on the same information brackets, therefore tender returns are much easier to compare).
• Minimal built-in contract to risk premium (unlike design and build).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is Design and Build Procurement?

A
  • Design and Build is more accurately a type of contract, however, it is commonly referred to as a procurement route and, therefore, needs to be considered here.
  • Where the contractor is responsible for the design, planning, organisation, control and construction of the works to the employers requirements
  • A single or two stage approach may be adopted. It is more common for the single stage method to be restricted to buildings of a reasonably simple nature where the risks to the contractor can be easily defined.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How does design and build work?

A
  • In its simplest form the employer gives tenders the ‘Employer’s Requirements’ and the contractors respond with the ‘Contractors Proposals’, which includes a price for the works
  • A method where the contractor is responsible for undertaking both design and the construction of the work in return for a lump sum price. There are variants on this option depending on the degree to which initial design is included in the client’s requirements.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the advantages Design and Build Procurement?

A

Advantages
• Design and construction risk sits with the contractor (single point of responsibility).
• Inherent buildability input – contractor’s experienced harnessed during design
• High cost certainty at point of contract over Traditional contracts.
• More efficient / earlier commencement on site is possible – design/construction overlap

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is Novation?

A

• A new contract that transfers the rights and obligations of one contractual party to a new third party i.e. design rights and obligations of the architect transferred to the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the difference between novation and assignment?

A

A novation agreement transfers both the benefits and the obligations of a contract to a third party. In contrast an assignment does not transfer the burden of a contract. This means the outgoing party remains liable for any past liabilities incurred before the assignment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

If the design team is novated, what should the client put in place?

A

A collateral warranty to the design team. Creates a contractual relationship between parties where there would otherwise not have been any.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is Management Contracting?

A

The employer appoints a management contractor to manage the entire building process who in turn appoints trade contractors to carry out the construction works.

The management contractor is usually paid a fee percentage based on construction costs.

The management contractor has a direct contractual link with the trade contractors and is responsible for the overall construction works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How does Management Contracting work?

A
  • Appointment of the contractor is usually by negotiation or tender, and interview. He is paid a management fee. The work packages are let by competitive tender.
  • The management contractor has direct contractual links with all of the works contractors
  • The have the responsibility for the construction works without actually carrying them out
  • Not all of the design need to be completed before the first works contractors start work
  • The client retains overall design control through the professional team
  • There is no certainty of over costs at the outset and work proceeds on the basis of the contract cost plan. Final costs will not be known until the last work package is let. However, the costs can be monitored by the clients QS
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the three main types of tendering?

A
  • Competitive single stage
  • Competitive two stage
  • Negotiated tender
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What are the methods of selecting tenderers?

A
  • Open tendering
  • Selective tendering
  • Single contractor selection
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What are the advantages/disadvantages of negotiated tender on DandB?

A

Advantages
- Most contractor involvement in design process
- No programme implications of tendering
Disadvantage
- Lack of competitiveness
- May not be suitable for public procurement contracts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What are the advantages/disadvantages of negotiated tender on traditional?

A

Advantages
- Contractor involvement throughout process will enable more effective mitigation of risk throughout the design process by the contractor
-No tendering period required on programme
Disadvantages
- No competition may result in high contractor offers
- May not be suitable for public procurement contracts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What are the advantages/disadvantages of negotiated tender on MC/CM contracts?

A

Advantages
- No tendering required in programme
Disadvantages
- No competition at all on Prleims and OHP and programme

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What are the advantages/disadvantages of single stage tender on DandB contracts?

A

Advantage
- Most competitive price
Disadvantage
- Contractor not fully understanding may lead to a ‘higher risk allowance’
- Programme implication to include tender period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What are the advantages/disadvantages of single stage tender on traditional contracts?

A

Advantages
- Most competitive price
- The most linear form of tendering
Disadvantage
- No contractor involvement
- May lead to high levels of provisional sums and risk items on the client side
- Programme implication to include tender period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What are the advantages/disadvantages of 2 stage tender on MC/CM contracts?

A

Advantages
- Increased contractor involvement in design
- Some degree of competition
- Ability to overlap design and tendering
Disadvantages
- Lack of competitiveness during 2nd stage
- Programme implication to include a tender period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What are the advantages/disadvantages of 2 stage tender on DandB contracts?

A

Advantages

  • Contractor involvement may reduce outstanding design/ construction risk
  • Ability to overlap tendering and design
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What is procurement?

A

The process of purchasing goods or services for a construction project.

Many different routes by which design and construction of a building can be procured.
The selected route should follow a strategy which fits the long term objectives of the client’s business plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What is tendering?

A

The selection of the contractor that will construct the works. However, depending on the procurement route, this could be for a wider range of goods and services.

The overall objective is to achieve a price for the works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

You state that you are fully aware of main procurement routes so what are the advantages and disadvantages of traditional procurement?

A

Advantages of traditional:
- Client has full control of design
- Competitive tender done single stage
-Cost certainty
- Less risk priced in by contractor as full design is complete
Disadvantages of traditional:
-Typically take longer as full design is needed before tender takes place
-May lead to higher level of prov sums and risk items
-No contractor involvement for design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

How would you go about advising a client on the appropriate procurement route to follow?

A

I would organise a procurement workshop with the client. I first understood the client brief and built on from this at the meeting. This would involve asking key questions related to the clients drivers relating to time, cost, quality and risk and then looking at the level of priority of each. Other key considerations would be the project type (size of project, complex design with specialist input needed?), market condition, statutory regulations (OJEU).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

You have read the RICS guidance note on tendering and understand the types of procedures, what is the difference between single and two stage tendering?

A

Single stage tendering is when the contractor bids for the works with a complete design and this would be for the full amount of the works and will achieve cost certainty. A 2 stage tender is when the 1st stage is under a pre-construction services agreement, whereby the contractor will take part in the design and selection of subcontractors. There is less cost certainty as the cost could go up/down for the main contract works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Why would you advise a client to adopt one over the other?

A

I would advise a client to select a 2 stage where specialist design input is needed more than cost certainty. If the works is of a simpler nature then a single stage can achieve cost certainty.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

When would you advise a client to follow a negotiated tender path?

A
  • When the client has a pre-existing relationship with a contractor.
  • When the works needs to go on site quicker with less time and resource gone into tendering
  • When OJEU is not required
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

What are the advantages and disadvantages of construction management?

A
  • Faster to complete as works are done in parallel with design
  • Client retains control of design
  • Contractor can still have design input
  • No cost certainty until packages are let
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

When would you suggest this method of procurement be adopted (CM)?

A

-When projects need to have a quick completion date.
-When works are of complex nature and contractor will not take on liabilities
-

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

How does CM differ from Management Contracting?

A

In MC the contractor will have contracts with subcontractos whereas in CM it is the client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

On UCLH you undertook a tender analysis and prepared a tender report, explain the process of the analysis and the contents of the report.

A
  • Record on tender opening sheet (price and programme) at correct time and date
  • Check for errors and conflicts
  • Raise tender queries
  • Equalisation/ Normalisation
  • Agree cost with contractor
  • Recommendation
  • Notify tenderers of result
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

How would you deal with errors and omissions in a tender?

A

Firstly, I would advise to the client that the correcting of errors should always be at the discretion of the client. Then, following the JCT Tendering practice note I would advise:
Alternative 1- Give details of error and afford opportunity to confirm or withdraw. Where tenderer has accepted error, all rates and prices in the document should be reduced or increased at the same proportion as the corrected total of priced items.
Alternative 2 - The tenderer should be given an opportunity of confirming his offer or of amending it to correct genuine errors. If the tenderer does amend his tender figure, and possibly certain of the rates in his documents, he should either be allowed access to his original tender to insert and initial the correct details or be required to confirm all the alterations in a letter.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

What documents do you include in the tender pack? 

A

Invitation to tender (ITT), including cover letter with tender return information.

Form of tender.

Contract conditions and employer’s amendments.

Instructions to bidders including how errors will be dealt with.

Tender scoring matrix.

Project information, drawings, specifications, surveys, planning conditions etc.

Pricing document.

PCI (Pre-construction information).

Quality questions (such as experience and methodology).

Receipt of tender.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

How were tender queries dealt with?

A

I assembled a query sheet which i sent to each contractor. I then compiled all of the queries and answered them which was sent back to all contractors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

How did the scoring matrix you suggested to your client work? Was it just based on cost?

A

The scoring matrix was 80% cost and this was recommended because the works was of such a simple nature. The qualitative scoring element was split into 3 parts, with programme, engagement with neighbours and health and safety/previous experience forming the other part.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

Now that it has been decided to leave the EU what impact, if any, will this have on tendering procedures?

A

This year is the transition period, so there will be no change, however EU processes like OJEU still remain uncertain and depend on the UKs deal with the EU.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

What do you understand by OJEU?What are the regulations and do what do they apply?

A

Official journal of the European Union.

Public projects must comply with the regulations if the value of contracts is above specified thresholds. Aggregation rules apply to projects tendered in parts to prevent clients from avoiding the requirements of the regulations by simply dividing projects up into contracts that are below the threshold.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

If a tenderer is late in submitting his bid, what would you advise the tenderer?

A

That the tender being accepted would be at the client’s discretion, however it is likely they would not be accepted to avoid fraud, collusion or bid-rigging.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

What advice would you give your client if a tenderer is late in submitting?

A

 Safest Option is not to consider- (Fraud, Collusion, Bid-rigging)
 If private client it is at their discretion (Advise of dangers though)
 Public client: Late cannot be accepted, few minutes late…judgement call needed, to accept need authorization in writing from council/ LA
 Advise accepting late tenders sets standard, contractors may in future also not keep to deadline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

Would your advice be different if the tender was the lowest?

A

My advice would be impartial regardless of the tender amounts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

What is a prequalification questionnaire? PQQ

A

A pre-qualification questionnaire (PQQ) sets out a series of questions for potential tenderers to answer regarding their level of experience, capacity and financial standing.

prior to being invited to tender.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

Why did you recommend a 2 stage tender on Tolworth?

A

There were multiple complicated design elements where the project could have benefited from a contractor’s input. This included:

  • Bathroom pods
  • Facade
  • MEPH
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

Why would having enabling works as a separate package de-risk the site for Tolworth?

A

This was because the main contractor may price an element of risk into the enabling works. Going directly in a separate contract with an enabling works contractor meant that this risk was evaded before the main construction works would begin.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

How did you score the 20% quality aspect for Tolworth?

A

This was scored based on the quality of the submission; criteria included their approach, programme, co-operation with neighbours, health and safety and resource.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

What was discussed at the procurement workshop for Tolworth?

A

At the procurement workshop, I discussed with the client what their key drivers were. The main three were time, cost and quality. The design team also recommended that some elements such as facade and MEPH would benefit from a subcontractor specialist input. The client also wanted to transfer risk to the contractor and wanted an early start date. As a result, I recommended the 2 stage design and build approach.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

How can you you explain all the main procurement routes to your client?

A

I presented a matrix whereby I input a set of criteria with scores 1-10 and the matrix pointed towards the design and build route. I then explained the benefits of all 3 with pros and cons listed on my presentation. Furthermore, I created a procurement recommendation report.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

What did you ask in the post tender interviews for UCLH?

A

This post tender interview, was effectively a tender settlement interview with the preferred contractor where I was able to clarify on the prices they submitted which seemed ambiguous. Questions I asked included: will you agree to the cost of the FFE item which is priced as per the pre-tender estimate?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

What did you advise on the scoring matrix for Tolworth?

A

I advised that due to the nature of the works, which was of a simple nature, and the client wanting to keep a tight budget, a competitive tender with 80% scoring would be best. The companies chosen for an expression of interest were known to the client and consultant team that were capable of producing works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

What did the client brief contain on Tolworth?

A

The client brief

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

What are the different types of partnering contracts?

A

Partnering agreements include the project partnering contract PPC2000, the term partnering contract TPC2005, the NEC partnering agreement and the ICE Partnering Addendum. There is also JCT Constructing excellence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

What are term contracts?

A

Used for FM.

56
Q

What happens in the 1st stage of a 2 stage tender?

A

The contractor will appoint a design team, the design will commence. Once designs are complete, there must be a conversation between the design team, if KPIs are ticked, the designs will be passed to the contractor’s commercial team who will price the project. The client’s QS team will then advise the client on the prices. QS will monitor all subcontractors prices throughout the subcontractor procurement.

57
Q

Are 2 stage tenders on traditional projects?

A

Usually only if it is a historic or complicated building where the project would benefit from extra contractor design. Normally always single stage and 2 stage for DB.

58
Q

What is the difference between open tendering and selective tendering?

A

Open tendering allows anyone to submit a tender to supply the goods or services that are required. Selective tendering only allows suppliers invited from a pre-selected list to take part in the tender process.

59
Q

What is MEAT?

A

Most economically advantageous tender. A contractor selection process which does not just use price as a means of winning the contract. Contractors must be informed of the criteria as part of the tender document.

60
Q

What was your tender procedure on King George’s Gate?

A
  • Expression of interest for tenderers (based on previous projects and client approval - below OJEU value)
  • Once received, informed them of tender docs and ITT release
  • Prepared tender doc and issued ITT
  • Met on site to answer questions (only gave information away which was in tender doc and rest went in query list issued as addendum).
  • Received tender docs and recorded on opening tender record
  • Checked for errors and inconsistencies
  • Produced tender document (tender analysis, qualitative assessment, qualifications, normalisation, tender procedure, recommendation).
61
Q

What is a bondafide tender?

A

A bid submitted in good faith, complete and in prescribed form which meets the conditions of the bidding requirements.

Confirmation that the supplier has not concluded with another party when compiling the tender.

62
Q

What is e-tendering?

A

Any information to be exchanged can be
transmitted using electronic media such as:
+ physical media (any physical platform for
holding the platform for holding the data,
including CD, DVD and memory sticks);
+ email; and
+ web-based technology.

63
Q

Explain the OJEU process

A

• Where a project is over a certain value it must be advertised in the OJEU:
• There are 4 procedures under OJEU:-
o 1) Open - any contractor allowed to tender for the work
o 2) Restricted - carried out in 2 stages 1st stage - open, 2nd stage - only contractors are invited that meet specific criteria
o 3) Negotiated - where competition is inappropriate, a single contractor is approached to negotiate a price.
o 4) Competitive Dialogue - Provides alternative to open and Restricted Procedures under OJEU. Similar to ECI process except that all contractors are involved
• A PIN is placed in OJEU at start of year to indicate what projects coming up.
• Once the project is let a Contract Notice is placed in OJEU providing further details of procedure to be followed.
• Once the contract has been awarded a Contract Award Notice must be published in the OJEU within 48 days of award.

64
Q

What regulation does OJEU fall under?

A

Public procurement contracts 2015.

65
Q

What will happen with OJEU after Brexit?

A

From the 1st of January 2021, the UK is not subject to EU procurement regulations and therefore no longer follow rules outlined for OJEU tenders.
.
Tenders will now be published on a new e-tendering portal, called Find a Tender Service (FTS).

66
Q

What is serial tendering?

A
  • Effectively strategic partnering
  • Contractors are asked to bid for a project on the basis that if they build this one satisfactorily, others of a similar type will follow and the same bill rates will be used
67
Q

What are qualifications?

A

Tenders may contain a number of comments or technical qualifications, which may include proposals for alternative similar approved materials. It is essential that the surveyor seeks clarification and recommendation from the relevant surveyor on these matters, for clarification within the tender analysis report, if necessary.
The surveyor should assess the financial implications of each and every proposal.
In order for the client to be able to make an informed decision as to which contractor to appoint, it is normal practice for the surveyor to issue a detailed tender analysis report.

68
Q

If there was a value engineering proposal suggested by a losing tenderer, which would benefit your project, would you utilise this opportunity?

A

Depends on how generic the VE option is. If a bespoke option I would seek legal advice.

69
Q

What did you look at when assessing the procurement route for Tolworth?

A

-the stage at which design certainty is assured;
risk allocation;
-the stage at which cost certainty is achieved;
-the point of financial commitment by the client;
-the experience required by the client;
-the input required by the client; and
-the overlapping of the stages, e.g. design and construction.

70
Q

How does a 2 stage tender work?

A
  • Competition to work on the 1st stage
  • 1st stage will include basis of fixed lump sums for management and supervision staff and preliminaries; approximate quantities and firm works tenders for the major sections of work that have been designed (if any), and provisional sums for the remaining work.
  • Cost certainty is achieved at the 2nd stage with the main contractor working as an intermediary between the design team and subcontractors.
71
Q

What are the main benefits of a 2 stage tender?

A
  • earlier start on site
  • the provision of contractor advice, with surveys, exploratory works and mock-ups
  • influence and control over sub-contract packaging
  • Shorter tender documentation period.
  • The compatibility of the main contractor and the sub contractor for CDPS elements can be achieved by including a list of sub-contractor names in pre-qualification documents.
72
Q

What are the disadvantages of a 2 stage tender?

A
  • There can be problems with the CDPS design not meeting the employer’s requirements; this can be addressed by early contractor involvement.
  • Needs the careful control of the interface between one CDPS and another, or between the CDPS- and consultant-designed elements. This introduces an element of cost and programme risk.
  • There will be a programme and cost penalty if the scope and value of the provisional sum works change significantly.
  • Requires the adaptation of standard contracts.
73
Q

What can a client do in order to retain the design if the 1st stage contractor is not retained?

A
  • In the PCSA there is a copyright clause to allow the client to use the design with a new contractor.
74
Q

What are the main factors which typically govern procurement route selection

A

The key is to identify the clients objectives and key drivers It terms of time cost and quality. Other factors such as risk allocation should also be considered.

It’s unusual to satisfy all elements with one procurement route. Consideration must be given to the clients list of priorities to identify the most appropriate procurement route.

75
Q

Which procurement options are you familiar with?

A

1) Traditional procurement (1 and 2 stage)
2) Design and build
3) Management contracting
4) Construction management

76
Q

What are the disadvantages of traditional procurement

A

Disadvantages
• Full design pre-tender is slow
• Competition or tendering cannot be commenced until the design is complete – reduction in cost & time certainty
• Overall project duration may be longer than others – sequential process
• No input into design or planning by the contractor

77
Q

When might traditional procurement be appropriate?

A

• The employer may have a specific or detailed design requirement.

• Cost certainty is important (traditional has significant advantages over construction management or management contracting procurement routes).

•The shortest overall program is not the employees main priority

78
Q

What are the disadvantages of design and build contracts? 

A

Disadvantages
• only as good as the employers requirements, the employer may find it difficult to prepare sufficiently comprehensive brief.
• Low client ability to control design and specification
• Harder to compare tenders – design proposals need to be balanced against price, and it is vital to check that the proposals satisfy the client’s requirements.
• Ease of fabrication may be prioritised above aesthetic quality
• Cost control more difficult due to less detailed pricing. Variations (client changes) tend to cost more due to the lack of a detailed pricing structure.
• The contractor will build in risk premiums into their tender return.

79
Q

When might Design and Build be appropriate?

A

1) where there is a need to make an early start on site, design and build has potential to overlap design and construction

2) where the employer wishes to minimise their risk profile design risk has passed on to the contractor

3) for technically complex projects to design with benefit from the contractors, buildability input.

4) where retaining control of the design, is not a priority.

80
Q

What additional insurance might be required under a D&B contract?

A

The contractor and their design team will have design responsibility. Therefore it is likely additional professional indemnity insurance will be required.

81
Q

What are employers requirements? (ERs)

A

The expression employees requirements are used to describe the documents produced by the employer to set out its requirements in relation to the projects (including performance, specifications, drawings, initial designs etc.) and this is what the design and construction of the works will be based on.

82
Q

What are contractors proposals? (CPs)

A

1) CPs offered by the contractor, which responds to the employers requirements

2) in these documents, the contractor will produce detailed design information based on the employers requirements, which will require further development throughout the course of the project.

83
Q

Which procurement route poses the least risk to the employer?

A

Design and build this is because the design risk is transferred to the contractor 

84
Q

Under design and build you executes the design for the contractor?

A

The contractor may use their own in-house designers, or they can appoint external consultants. The employers original design team can also be innovated to the contractor.

85
Q

What is construction management? 

A

The employer directly appoints multiple subcontractors (referred to as trade contractors) instead of employing a single main contractor. The single feature that makes construction management unique, particularly from management contracting, is that the employer places individual contracts with separate specialist/contractors themselves.

Key points:
•The employer places a direct contract with each trade contractor and utilises the expertise of a construction manager to coordinate the works.

• The construction manager programmes and coordinates the works.

• The construction manager has no contractual link with the trade contractors.

• The construction manager has no vested interest in the financial outcome of the project and bar professional negligence, carries no risk.

86
Q

What are the key advantages of construction management? 

A

Speed (early start on site).

Overall project duration reduced by overlapping design and construction.

The construction manager can contribute to the design and project planning processes.

Changes in design can be accommodated without paying a premium.

Prices may be lower due to direct contracts with trade contractors.

The employer has means of redress with trade contractors through direct contractual links.

87
Q

What are the key disadvantages of construction management? 

A

Price certainty not achieved until the last trade package is let

The procurement route requires an informed experienced and proactive employer to work

The employer has a lot of consultants and contractors to manage.

88
Q

When might construction management be appropriate? 

A

The employer is experienced in construction and has the suitable resources to manage the project.

The employer wants to achieve an early start on site.

The employer wants the flexibility to make minor changes to the design / specification throughout
process with minimal impact on time or finances.

The project is technically complex and requires detailed engagement of specialist consultants and trade contractors.

89
Q

Which is the riskiest procurement route for the employer?

A

Construction management.

This is because the employer places individual contracts direct with each trade contractor and the construction manager carries no risk (barring professional negligence).

90
Q

What are the key advantages of management to contracting? 

A

Overall project duration can be reduced by overlapping design and construction.

The management contractor will provide buildability input.

Single point of responsibility (management contractor).

Trade packages are let competitively and transparently.

There can be considerable flexibility in the design, with changes being made throughout the construction process.

91
Q

What are the key disadvantages of management to contracting? 

A

Price certainty not achieved until the last trade package is let.

Requires an informed and proactive employer to be successful.

Depending on how the construction manager is remunerated, there may be a built-in disincentive for the construction manager to minimise costs.

92
Q

When may management contracting be appropriate?

A

When an early start on site is a priority.

Flexibility in design is required.

Buildability input from the management contractor is required.

Where cost certainty is not a priority for the employer.

93
Q

What is the key difference between management contracting and construction management? 

A

Construction management - The employer directly appoints multiple trade contractors to execute the works.

Management contracting - The employer appoints a management contractor who in turn appoints the
works contractors.

94
Q

What is a framework agreement?

A

A framework agreement is an umbrella agreement that a party enters with one or more suppliers (who may be contractors, subcontractors, suppliers or consultants) to establish governing terms.

A framework usually sets a strategic partnering relationship for the procurement of goods, works or
services.

95
Q

How long can a framework be?

A

Typically, a framework agreement last for 4 years, however, this is determined by the buyer.

they can range between 2 and 10 years

96
Q

What are the key advantages of a framework agreement? 

A

Framework agreements can help to develop stronger relationships between the parties involved and encourage long term collaboration and co-operation.

Time saving (can speed up the procurement of goods and services).

Repeat work and continuity of delivery.

Rates and prices are usually agreed upfront.

97
Q

What are the key disadvantages of a framework agreement? 

A

The contractors, suppliers or consultants can become complacent.

Bidders will invest time and money to be awarded onto a framework and then potentially not receive any work through them.

May be restrictive to new suppliers who offer innovative, new, solutions with the changing and evolving nature of technologies for example.

98
Q

Why might the employer choose a framework agreement to procure goods and services?

A

Employers that are continuously commissioning construction work might want to reduce procurement timescales, learning curves and other risks by using framework agreements.

A framework allows the employer to invite tenders from suppliers of goods and services on a call-off basis as and when required.

99
Q

What’s the difference between a framework agreement and a contract?

A

A framework agreement rarely provides any specific commitment in terms of project and value of works. It is more focused around being an approved supplier.

A contract is usually a specific fee, with project scope and timelines allowing you to quote and tailor your product/service for the specific job at hand.

100
Q

What is project partnering? 

A

Partnering is a broad term used to describe a collaborative management approach that encourages openness and trust between the contracting parties.

There is more opportunity for building working relationships, finding improvements and planning investment.

Ownership of risk is spread between the parties and a collaborative approach is encouraged to delivering the solution and overcoming problems.

101
Q

What are the key advantages of partnering? 

A

The overall construction and design programme can be shortened.

The likelihood of conflict is reduced.
Improved communication and mutual objectives.

Improved customer satisfaction.

Improved value for the employer.

Improved buildability (early involvement of contractors for example).

Better predictability of time and cost.

102
Q

What are the key disadvantages of partnering? 

A

Less opportunity to understand what other contractors/potential partners have to offer.

Difficult to find a strong partner which have the same objects, ethics, attitude etc.

103
Q

What is the difference between procurement and tendering?

A

Procurement is the overall act of obtaining goods and services from external sources and deciding the strategy on how these goods are to be acquired.

Tendering is a phase in the procurement strategy and deals with obtaining a price through a bidding process and deciding how a contractor is appointed.

104
Q

What might the PQQ ask for? 

A

Company details (including legal status).

Details of insurance cover.

Financial information (such as company accounts).

Relevant experience.

Information about technical and professional ability.

Information about capability and capacity.

Health and safety policy and records.
Quality assurance policy.

Environmental management policy.

Equal opportunities policy.

References.

105
Q

A credit check is usually part of the PQQ process. Where could you get a credit check from? 

A

Dunn and Bradstreet report

Credit agencies such as Experian

106
Q

What is single stage tendering? 

A

Tender documents are issued to several competing contractors who are all given the chance to bid for the project based on identical tender documentation 

107
Q

What are the key advantages of single stage tendering? 

A

The employer benefits from a competitive tendering process which can lead to more competitive pricing.

The employer can benefit from a fixed price through this tendering process,

108
Q

What are the key disadvantages of single stage tendering? 

A

No buildability input from contractor (at the point of tender).

The price is only as good as the design information.

Contractors may be unwilling to tender in a good economic climate (too much competition).

109
Q

If you have a 25 million new build project under design and build procurement (single stage, tender), how long would you allow for the tender period?

A

The tender period is largely dependent on the complexity of the project. However, 10 to 12 weeks would be reasonable as it will take some time to interpret the employers requirements.

110
Q

What is two stage tendering? 

A

Stage 1

The employer provides an outline project design and contractors then compete for preferred contractor status. The preferred contractor is usually chosen based on the quality of their bid, the quality of their team, preliminaries and OH&P allowances. The preferred contractor then joins the design team on a consultancy basis using a pre-construction services agreement (PCSA).

Stage 2

Once the design has sufficiently progressed, the contractor enters into a detailed contract negotiation with the employer to agree the final price, contract conditions and programme.

111
Q

What are the key advantages of to stage tendering?

A

Early appointment of the contractor to work in parallel with the design team.

Early involvement of the contractor to benefit from buildability input.

Earlier start on site is possible.

Employer involvement in subcontractor selection.

Increase opportunity to value engineer (VE) with the contractor’s input.

Improved opportunity to identify project risk.

112
Q

What are the key disadvantages of two-stage tendering? 

A

The contractor has less incentive to price the second stage competitively, negotiations may therefore be difficult.

Additional cost of the contractor’s pre-construction fee.

Potential for the negotiation stage to fail (contract sum not agreed).

113
Q

What is a negotiated tender?

A

A negotiated tender is effectively a single-stage tender carried out between the client employer and one contractor.

Negotiated tenders are obtained by the client, inviting one contractor of their choice to submit a tender response for the project.

114
Q

What are the key advantages of a negotiated tender? 

A

173.
Simplicity.

Speed, a negotiated process can have programme advantages if undertaken in good faith.

The employer has flexibility in terms of choosing their preferred contractor.

Time and cost savings involved in comparing and analysing multiple tender submissions.

The process can allow early contractor involvement.

115
Q

What are the key disadvantages of negotiated, tender?

A

Possibility of delay if contract negotiations are protracted.

Potential cost premium due to the lack of competition.

There is a heavy reliance on trust between the parties.

It can be seen as anti-competitive and exclusive.

116
Q

How could you justify value for money in a negotiated tender?

A

Insist on an open book approach when agreeing subcontract packages and a minimum of 3 quotes to be provided for each element of the works (this would need to be agreed upfront with the contractor).

117
Q

What is a “form of tender?”

A

The contractor usually signs and returns this document with their proposed tender submission.

It is formal acknowledgment that the tenderer understands and accepts the terms of conditions of the tender documents and any other requirements that are stipulated. The document also includes the contractor’s price and programme.

118
Q

What information is typically included in the form of tender?

A

Tender sum.

The date until which the price remains valid.

Construction period

Confirmation of the tender being genuine and bona fide.

Tenderer details and signature.

Acceptance of terms and conditions.

119
Q

When seeking tenders for construction work, in addition to the actual price for the work, what additional information might be requested from the contractor?

A

Track record of previous experience (for example, case studies).

Proposed team and hierarchy.

Methodology or approach.

References.

Programme.

H&S information.

Value engineering proposals.

Logistics plans.

Social value strategy.

Diversity and inclusion policy.

120
Q

Once tenders have been submitted, what should be examined for compliance with the invitation to tender and tender instructions? 

A

Arithmetical errors.

Pricing errors (items not priced).

Pricing methods (front loading).

Compare the contractor’s proposals against the employer’s requirements for compliance (D&B procurement).

Check the form of tender is complete and signed.

Resolve any qualifications.

121
Q

What happens if a tender is submitted late?

A

Public sector project - the documents should be accepted.

Private sector project - the matter should be discussed with the employer to understand if they would like to accept. The safest option is not to consider (potential fraud, collusion, bid-rigging risk etc).

122
Q

Would you open a later submission for school project?

A

The tender should be discarded on the basis of the project is funded by the public sector.

123
Q

What is the danger of accepting a very low tender submission? 

A

The contractor may be trying to ‘buy’ the project with a view recover their costs with variations and/or claims.

It could indicate the contractor is in a poor financial or cash flow position and they are eager to win the work at any cost.

Areas of the project may not be priced accurately, potential for an adversarial relationship to develop post contract.

124
Q

How do you deal with qualifications in the tender submission?

A

Procedures associated with qualifications should be outlined in the tender instructions.

If the qualifications are unauthorised, it might invalidate the tender (leading to disqualification).

The employer team and contractor should look to resolve the gualifications prior to signing the contract. Any outstanding matters should be clearly documented in the contract to avoid future disputes.

125
Q

How do you deal with errors identified in the tender submissions?

A

JCT have produced a tendering practice note where two options are suggested to deal with errors. One of these options is usually drafted into the tender pack

Alternative 1:
The tenderer should be given the details of the errors and afforded the opportunity of confirming or withdrawing their tender.
If they withdraw, the next lowest bid is considered.

Alternative 2:
The tenderer should be given the opportunity of confirming their offer or amending it to correct genuine errors.

126
Q

What would you do if you considered a contractor submitting the lowest tender to be in financial difficulty?

A

As part of the evaluation process, the company accounts would be reviewed to assess the financial stability of the contractor (if not already complete at PQQ stage). This could lead to disqualification if the contractor is having financial difficulty.

Consider a performance bond. In the event the contractor fell insolvent, the employer would be able to call on the bond and appoint another contractor to complete the project.

Consider a parent company guarantee.

127
Q

On what grounds would you advise the client to re-tender? 

A

Not enough tenderers returned tenders.

The tendering procedure is compromised for some reason.

If tenders were not at the cost level required and it was believed that re-tendering to different tenderes
would provide a different result.

Design changes or VE has been carried out that has significantly changed the design that was originally tendered on.

128
Q

How would you deal with a front loaded tender?

A

Front loading is generally not a pricing error.

Request contractor removes front loading, if the contractor refuses, this may be grounds for disqualification.

129
Q

How could you reduce the risk of contractors, pulling out during the tender process?

A

Ensuring the tender information is as accurate as possible.

Ensure tender the period is long enough (extend if required).

Go through the PQQ (pre-qualification questionnaire) to ensure the correct tenders are selected.

Check the contractor has time capacity to complete the tender.

130
Q

What grounds would you advise the client to re-tender the project?

A

Not enough tenders returned.

The tender procedure was compromised in some way (potential fraud, collusion, bid-rigging etc).

Significant design, methodology or programme changes after issuing the tender documents.

131
Q

What is the contract sum analysis document under design and build procurement?

A

A contract sum analysis (CSA) is an alternative pricing document to a schedule of works (SoW) or bill of quantities (BoQ).

It’s often prepared in a standard format by the employer’s team to support the tender analysis.

The employer’s team usually request that all tenders are returned via the same CSA format.

132
Q

What information is typically included within a tender analysis report?

A

List of tenders received.

Initial tender return totals.

Any qualifications identified.

Post-tender adjustments.

Revised tender sum.

Issues to be resolved.

Comparison of tender returns.

Comparison with pre-tender estimate.

Recommendation.

133
Q

If the tender was received on time, but the project is delayed for a few months, what would you need to check?

A

Check the form of tender, this would show how long the price (the offer) was valid for (for example 60 or 90 days after the tender return date).

134
Q

If the contractor (in the tender return) put a cost against an item and marked it provisional, what would you do?

A

I would seek further information from the contractor and request this to be removed, subject to the tender instructions. This may invalidate the submission.

135
Q

If you think the delivery program is tight, how can you give comfort to the contractor regarding liquidated damages (to avoid them excessively pricing in their tender sum)?

A

The contract and be amended to include a liquidated damages free period, for example, damages would not be levied for the first three weeks, or levied at 50% for a defined period

136
Q

What is the purpose of a pretender estimate?

A

A pre-tender estimate (PTE) is the last cost check of the project before it is issued to tender.

The design should be sufficiently developed at this stage; therefore, the PTE should be an accurate reflection of the works.

The estimate can then be used to compare against the tender submissions.

137
Q

What happens if the tender prices are higher than the pretender estimate?

A

This could be down to market conditions or some other external factor such as COVID-19 or Brexit.

The employer’s team should reconcile the tenders against the pretender estimate to identify where the major differences are.

The team could look to value engineer the project if the prices are over budget.