Procurement & Tendering Flashcards
(54 cards)
WHAT IS PROCUREMENT?
As noted in the RICS Tendering Strategies Guidance Note:
Act of obtaining goods and services from external sources, i.e. building contractor.
Includes deciding the strategy on how to acquire the goods by reviewing the client requirements (time, cost, qualtiy, attitude to risk).
WHAT IS TENDERING?
As noted in the RICS Tendering Strategies Guidance Note:
Phase of the procurement strategy, includes the bidding process, obtaining a price and how a contractor is actually appointed.
WHAT ARE THE MAIN TYPES OF TENDERING PROCEDURES?
Single stage tendering
Two stage tendering
Negotiated tendering
WHAT IS SINGLE STAGE TENDERING?
Most common type, obtaining competitive tenders for the whole of the construction works.
Invitation to tender documents are issued to contractors for them to submit a bid, based on identical tender documentation.
This is usually done at RIBA Stage 4 so the tendering contractors receive detailed information for their bid.
Bidding contractors are givena predetermined time to submit their tenders, which are then analysed for cost and quality, before a single contractor is declared the preferred contractor.
Then, enter a building contract.
WHAT IS TWO STAGE TENDERING?
Used where time is constrained as it enables design and tendering to overlap, and benefits from the technical input of a contractor in the later design stages. Essentially, the early appointment of a contractor.
Tender documents issued to contractors at RIBA Stage 2 or 3.
The contractors are judged on the basis of the quality of their bid, their team and the prelims, overhead and profits allowances.
Contractor then joins the team as a consultant under a PCSA (Pre-Construction Services Agreement) to complete the design to RIBA Stage 4, before presenting a bid at this stage.
WHAT IS A NEGOTIATED TENDER
Essentially a single stage tender with a single contractor who submits an initial price, which is then negotiated by the client’s professional team (BS / QS).
This reduces timescale for receiving a cost for works, however, the competitive advantage of tendering is compromised.
Also, many public bodies and government departments will not allow negotiated tender as value for money is difficult to prove against market value.
WHAT ARE THE RIBA STAGES?
- Strategic Definition
- Preparation and Brief
- Concept Design
- Spatial Co-ordination
- Technical Design
5.Manufacturing & Construction - Handover
- Use
Recent RIBA Plan of Work 2013 recognises adoption of two-stage tender and the various times tendering can be carried out
WHAT IS EARLY CONTRACTOR INVOLVEMENT? (ECI)
ECI is a form of two stage tender with Contractors bids judged on quality of the team and bid, but emphasis put on Contractor as the Lead Designer from outset of the project.
More common in infrastructure projects where contractor affects design.
Allows contractor to form a design team, led by them.
WHAT IS THE JCT PRACTICE NOTE?
Current most recent version is 2017,
A best practice, informative and practical tool for employers, contractors, and professional advisers involved in private or public sector procurement for the letting of construction contracts in the UK.
WHAT IS BS 11000-1 COLLABORATIVE BUSINESS RELATIONSHIPS?
Impacted on large infrastructure projects, strictly related to Partnering projects.
Advises how to select and evaluate proposed partner bids.
WHAT ARE THE REASONS FOR A ROBUST TENDERING PROCESS?
Ensure positive tender results through:
- Accountability
- Auditability
- Ensuring all works are picked up
- Parity (being equal, fair)
- Help to reduce corruption claims
- Ensuring correct price is paid for proposed works
WHAT IS THE PRE-TENDER ESTIMATE? (PTE)
Pre-cursor to the tendering phase based on the minimal design work produced, the extent of which is dependent on the chosen procurement route.
Important to know the estimated project cost for two reasons:
1. For the client to know if they can afford the proposed works.
2. For a basis of comparison when tenders are returned, benefitting the later analysis phase.
Should be carried out in accordance with RICS NRM (New Rules of Measurement).
HOW DO I CHOOSE THE MOST SUITABLE TENDER STRATEGY?
Construction Management / Management Contracting project:
- Quick start on site required as design and tendering are overlapped
- Natural fit for construction management / management contracting procurement routes
Traditional project:
- Single stage tender where a greater level of design has occured before tender (unless complex and contractor input is required)
Design & Build project:
- Pass a large portion of risk and design responsibility to the contractor, therefore, two stage to benefit from a contractors experience and knowledge to influence design
- During two stage, the contractor is part of the design before an agreed contract sum is agreed, often appointed under PCSA as a consultant in the second stage of tender
WHAT ARE THE BENEFITS AND DRAWBACKS OF SINGLE STAGE TENDERING?
Advantage:
- Most competitve price
- Most linear form of tendering
Disadvantage:
- Contractor not fully understanding may allow a ‘risk allowance’
- Programme implication to tender period
- No contractor involvement (Traditional)
- May lead to high Provisional Sums and risk items on client side (Traditional)
WHAT ARE THE BENEFITS AND DRAWBACKS OF TWO STAGE TENDERING?
Advantage:
- Increased contractor involvement in design, reducing design/construction risk
- Some degree of competition
- Overlapped design and tendering, reducing programme
- Competitiveness for prelims, OHPcompared to Negotiated (Management)
Disadvantage:
- Lack of competitiveness during second stage
- Programme implication (but less so due to overlap)
- No risk mitigation incentive for contractor, risk on client (Traditional)
- Increased programme to accommodate tender period
WHAT ARE THE BENEFITS AND DRAWBACKS OF NEGOTIATED TENDER?
Advantage:
- Most contractor involvement in design, effective risk mitigation in design
- No programme implication for tendering
Disadvantage:
- Lack of competitiveness, may result in high contract offers
- Not suitable for public procurement
- No competition on prelims, OHP
WHAT RIBA STAGE FO EACH TENDERING STRATEGY NEED TO COMMENCE IN?
- Concept Design
- Single stage - D&B possible at this stage
- Two stage - First stage
- Negotiated - Anytime from Concept - Developed Design
- Single stage - D&B possible at this stage - Technical Design
- Two stage - Second stage negotiation
WHAT ARE THE TYPES OF CONTRATOR SELECTION TECHNIQUES?
Open tendering
Selective tendering
Single contractor selection
WHAT IS OPEN TENDERING?
Allows anyone to express interest to tender, often advertised in journals/websites.
Public procurement is a form of open tendering, albeit with caveats to as to suitable contractors).
WHAT IS SELECTIVE TENDERING?
A shortlist drawn up by the project / client team, or drawn from a pre-agreed framework / approved suppliers list.
Different to open tendering in that it is not open, and contractors are chosen by project team.
WHAT IS SINGLE CONTRACTOR SELECTION?
Works in hand with negotiation as a tender approach, a shortlist of one only.
WHAT IS CONSIDERED WHEN SELECTING SUITABLE CONTRACTORS FOR TENDER?
Previous experience
Word of mouth, recommedations, previous association on projects
Presentations from contractors looking to secure new work
The company size, financial standing, suitable H&S record, reputation, offer of services
WHAT IS A FORMAL PRE-QUALIFICATION PROCESS?
Short interview or pre-qualification questionnaire (PQQ) depending on size and complexity of project.
Aim is to ensure contractor has relevant experience, financial standing, good health and safety record.
HOW DO YOU ASSESS A SUITABLE TENDER PERIOD?
Varies on:
- Project complexity
- Size of project
- Time of year (e.g. Christmas period)
- Market conditions
Also common for first stage of two-stage tender to be shorter than a single stage tender as contractors only have to price preliminaries, overheads and profits.
Single stage need to price all works including awaiting costings from their supply chain.
A short tender period may cause improper pricing, programme drafting, or contractors refusing to submit a price.