Professional Practice Issues Flashcards
(44 cards)
There are several New Design Provisions within a practice, what are they?
- Contractor’s Design Submission Procedure
- Professional Indemnity insurance
- Copyright and licences
- Third party rights and collateral warranties
What are the clauses involved in the procedure for the Contractor’s Design Submission?
Clause 2.2 – Contractor’s Designed Portion- ‘the Contractor shall…complete the design for the (CDP) including the selection of any specifications…(and) comply with the directions of the Architect / CA for the integration of the design of the (CDP) with the design of the Works as a whole…’
Clause 2.9.2.1 - ‘the Contractor…shall without charge provide…2 copies of such Contractor’s Design Documents, and (if requested) related calculations and information, as are reasonably necessary to explain or amplify the Contractor’s Proposals…’
Clause 2.9.3 - ‘The Contractor’s Design Documents…shall be provided…as and when necessary from time to time in accordance with the Contractor’s Design Submission Procedure set out in Schedule 1…and the Contractor shall not commence any work to which such a document relates before that procedure has been complied with’.
How long is the Architect’s period for approval?
14 days from the date of receipt or if later then 14 days from the date stated in the Contract Documents. The Architect/CA shall then return a marked as an A, B, or C.
What happens if the architect goes over this 14 day period?
If the architect goes over their agreed time then the drawings will be regarded as “A”
What are the differences with marking the drawings A, B, or C?
‘A’ – carry out the CDP Works in strict accordance with that document;
‘B’ – carry out the CDP Works but incorporate comments and promptly resubmit.
‘C’ – do not carry out any work, address comments and resubmit or notify Architect/CA.
How many copies of the Contractor’s Design Documents should be submitted?
2 and they should be submitted in sufficient time to allow any comments from the Architect
Is the employer liable?
The employer shall not be liable to pay for any work…otherwise than in accordance with…‘A’ or ‘B’.
If the contractor disagrees with the decision of the architect, what then happens?
If the contractor disagrees…notify with reasons…within 7 days. On receipt the Architect/CA must confirm or withdraw the comment…within 7 days.
If the contractor does not reply to comments of notes made by the architect in the Contractor’s doncuments within 7 days, what happens?
It then gets treated as if there has been no variation.
What is clause 6.11?
Obligation to Insure
‘the Contractor shall… take out…a Professional Indemnity insurance policy with a limit of indemnity of the type and in an amount not less than that stated…’
‘maintain such insurance until the expiry of the period stated…’
‘produce for inspection documentary evidence…’
What is clause 6.12?
Increased cost and non-availability
‘If the Pll ceases to be available at commercially reasonable rates…notify… and discuss…’
What is clause 2.13.2 and why is this important?
2.13.2 ‘the Contractor shall not be responsible for the contents of the Employer’s Requirements or for verifying the adequacy of any design contained within them.
Unfortunately in the current market, often employers and their lawyers will force contractors to take on responsibility to fulfil the employer’s requirements.
How do JCT/SBCC aim to ensure that clause 2.13.2 remains intact?
For clarity JCT/SBCC have said that employers requirements should be the responsibility of the employer and that contractor’s proposals should be the responsibility of the contractor.
This then is a fair allocation of risk.
What is clause 2.19?
Design liabilities and limitation
‘the Contractor shall…have the like liability to the Employer…as would an architect or, as the case may be, other appropriate professional designer holding himself out as competent to take on work for such design…’
What is covered in clause 2.41 - Copyright
.1 ‘the copyright in all Contractor’s Design Documents shall remain vested in the Contractor’.
.2 ‘the Employer shall have an irrevocable, royalty-free, non-exclusive licence to copy and use the Contractors Design Documents…for any purpose relating to the Works…’ .3 ‘the Contractor shall not be liable for any use…other than that for which they were prepared’.
What does the Scottish Minor Works Building Contract with contractor’s design MWD/SCOT involve?
SECOND RECITAL ‘the Works include the design and construction of the Contractor’s Designed Portion’
THIRD RECITAL ‘the Employer has had the following documents prepared…showing or describing or otherwise stating his requirements…’
What are the contractor’s obligations under the MWD/SCOT?
1 ‘using reasonable skill care and diligence complete the design for the CDP’
2 ‘not be responsible for the…Employer’s Requirements’
3 ‘comply with the directions of the Architect/ CA for the integration of the design of the CDP’
4 ‘comply with regulation 13 of the CDM regulations’
5 ‘without charge provide…as and when necessary…two copies of such drawings and details’
6 ‘not commence any work (that relate) within 7 days’
How do you respond to variation in the MWD/SCOT and what clause does this relate to?
3.6 Variations
1 ‘The Architect/CA may… issue instructions effecting a change in the Employer’s Requirements.’
What is the common misconception in terms of extension of time when it comes to contractors and employers?
It is common belief in the construction industry that extensions of time are solely for the benefit of contractor. Giving the contractor more time to complete the works, reducing his liability for liquidated damages, they do not appear to be to the advantage of the employer. However, the effect of the extension provisions is to maintain the contractor’s obligation to complete within the defined time, and in the absence of these provisions, time is put at large by prevention (that is delays caused by the employer or those for whom the employer is responsible) and the contractor’s obligation is to complete within a reasonable time. The contractor’s liability can then only be for general damages if it can be proved that she has failed to complete within this reasonable time.
What do clauses 2.26 - 2.29 refer to? and what to they allow for?
Clauses 2.26 – 2.29 Adjustment of Completion Date allows the Architect
• To retain a defined Completion Date
• To preserve the Employer’s right to liquidated damages where the Employer or those for whom she is responsible have delayed the Contractor
• To give the Contractor relief in respect of delays caused by designated neutral events
What is covered under clause 2.27?
‘it becomes reasonably apparent that the progress of the Works … is being or is likely to be delayed’ the Contractor not only shall ‘forthwith give written notice to the Architect/Contract Administrator of the material circumstances, including the cause or causes of the delay, and shall identify in the notice any event which in his opinion is a Relevant Event’ but also, with such notice or soon as possible thereafter, ‘give particulars of the expected effects , including an estimate of any expected delay in the completion of the Works …’. In addition she must notify the Architect of any material change in the estimated delay, or in any of the other particulars given, and provide such further information as the Architect may reasonably require
What is covered under clause 2.28?
Under Clause 2.28, provided the Architect is of the opinion that: (i) any of the events stated by the Contractor to be a cause of delay is a Relevant Event; and (ii) completion of the Works is likely to be delayed beyond the current Completion Date because of that or those Relevant Events, the Architect is required to give such extension of time, if any, as she considers to be fair and reasonable.
What is the common misconception in terms of extension of time when it comes to contractors and employers?
It is common belief in the construction industry that extensions of time are solely for the benefit of contractor. Giving the contractor more time to complete the works, reducing his liability for liquidated damages, they do not appear to be to the advantage of the employer. However, the effect of the extension provisions is to maintain the contractor’s obligation to complete within the defined time, and in the absence of these provisions, time is put at large by prevention (that is delays caused by the employer or those for whom the employer is responsible) and the contractor’s obligation is to complete within a reasonable time. The contractor’s liability can then only be for general damages if it can be proved that she has failed to complete within this reasonable time.
What do clauses 2.26 - 2.29 refer to? and what to they allow for?
Clauses 2.26 – 2.29 Adjustment of Completion Date allows the Architect
• To retain a defined Completion Date
• To preserve the Employer’s right to liquidated damages where the Employer or those for whom she is responsible have delayed the Contractor
• To give the Contractor relief in respect of delays caused by designated neutral events