Project Delivery Study Workbook: Domain 1 Flashcards

(80 cards)

1
Q

Responsibility:

Arranges project financing

A

Project team: Owner

Responsible participant: Financial institutions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Responsibility:

Advises, assists, makes
recommendations, and evaluates
the design for compliance with
the applicable building codes

A

Project team: Design

Responsible Participant: Life Safety Consultant

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Responsibility:

Arranges sales appointments,
quotes pricing information, takes
purchase orders, and arranges for
product shipment

A

Project team: Supplier

Responsible Participant: Manufactures sales employee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Responsibility:
Buys, inventories, and resells
materials, products, components,
assemblies, and equipment that
can be either fabricated or directly
incorporated into projects

A

Project team: Supplier

Responsible Participant:

Distributors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Responsibility:
Contracts with a manufacturer to
promote products within a defined
geographic area

A

Project team: Supplier

Responsible Participant: Independent Sales representative

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Responsibility:

Designs the aesthetic and
technical aspects of a project

A

Project team: Design

Responsible Participant:

Architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Responsibility:

Determines the cost of the work

A

Project team: Contractor

Responsible Participant:

Estimator

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Responsibility:

Directs, manages, and coordinates
the day-to-day activities of a
construction project

A

Project team: Contractor

Responsible Participant:

Superintendent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Responsibility:
Answers technical inquiries from
the design and construction teams,
presents seminars, and performs
other educational activities

A

Project team: Supplier

Responsible Participant:
Manufacturer technical employee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Responsibility:

Establishes, monitors, and maintains
safety on the construction site

A

Project team: Contractor

Responsible Participant:

Safety Director

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Responsibility:

Examines the soil strata beneath
the surface of the ground and
subsurface geological formations
and makes recommendations for
the design of the facility foundations

A

Project team: Owner

Responsible Participant:

Geotechnical Engineer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Responsibility:

Manages information about building
technology and sciences

A

Project team: Design

Responsible Participant:

Specifier/Knowledge manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Responsibility:

Occupies the facility for which it
was designed and constructed to
conduct activities in accordance
with its intended purpose

A

Project team: Owner

Responsible Participant:

Facility users

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Responsibility:

Provides risk coverage

A

Project team: Owner

Responsible Participant:

Insurance companies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Responsibility:

Oversees the construction contract

A

Project team: Design

Responsible Participant:

Construction contract administrator

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Responsibility:

Provides general management
of the contractor’s staff, suppliers,
and subcontractors, and guides
the project through the
construction portion of the
project delivery method

A

Project team: Contractor

Responsible Participant:

Contractor’s project manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Responsibility:

Provides the labor, materials,
and services required for the
construction of a specific portion
of the work

A

Project team: Contractor

Responsible Participant:

Subcontractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Responsibility:

Researches the market to
determine what is important
to buyers and decision makers

A

Project team: Supplier

Responsible Participant: Manufacturers Marketing employee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Responsibility:

Surveys land on which projects
are constructed to document the
existing conditions and features

A

Project team: Owner

Responsible Participant:

Surveyor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Responsibility:

Technical and engineering designer
of structures that resist or support
static and dynamic loads

A

Project team: Design

Responsible Participant:

Structural engineer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

(4 C’s)

Use proper grammar and simple sentence construction
to avoid ambiguity.

A

Clear

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

(4 C’s)

Do not leave out important information.

A

Complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

(4 C’s)

Present information accurately and precisely.
Carefully select words that convey exact meanings

A

Correct

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

(4 C’s)

Eliminate unnecessary words, but not at the expense of clarity,
correctness, or completeness.

A

Concise

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Write the name of each stage of the Facility Life Cycle in the text boxes.
Project conception Design Construction documents Procurement Construction facility management
26
activities associated with the facility life cycle stage: -Investigations -programming -Site evaluation and selection -Project delivery method selection
Project conception
27
activities associated with the facility life cycle stage: -Schematic Design -Design Development
Design
28
activities associated with the facility life cycle stage: -Construction Documents
Construction Documents
29
activities associated with the facility life cycle stage: -Competitive bidding/proposing -Contract negotiations -Direct purchase of goods and supplies
Procurement
30
activities associated with the facility life cycle stage: -Mobilization -Construction -Contract administration -Project closeout
Construction
31
activities associated with the facility life cycle stage: -Occupancy -O&M -Evaluation
Facility management
32
Match each document to the facility life cycle stage in which it is prepared. Then, identify the project participant who is responsible for preparing each document. Document: Bid Form
FACILITY LIFE CYCLE STAGE: Procurement RESPONSIBLE PARTICIPANT: Owner
33
Match each document to the facility life cycle stage in which it is prepared. Then, identify the project participant who is responsible for preparing each document. Document: Post Occupancy Evaluation
FACILITY LIFE CYCLE STAGE: Facility management RESPONSIBLE PARTICIPANT: Architect/Engineer
34
Match each document to the facility life cycle stage in which it is prepared. Then, identify the project participant who is responsible for preparing each document. Document: Project Schedule
FACILITY LIFE CYCLE STAGE: Project conception RESPONSIBLE PARTICIPANT: Owner
35
Match each document to the facility life cycle stage in which it is prepared. Then, identify the project participant who is responsible for preparing each document. Document: Outline Specifications
FACILITY LIFE CYCLE STAGE: Design RESPONSIBLE PARTICIPANT: Architect/Engineer
36
Match each document to the facility life cycle stage in which it is prepared. Then, identify the project participant who is responsible for preparing each document. Document: Bid/Proposal
FACILITY LIFE CYCLE STAGE: Procurement RESPONSIBLE PARTICIPANT: Contractor
37
Match each document to the facility life cycle stage in which it is prepared. Then, identify the project participant who is responsible for preparing each document. Document: Permits
FACILITY LIFE CYCLE STAGE: Construction RESPONSIBLE PARTICIPANT: Contractor
38
Match each document to the facility life cycle stage in which it is prepared. Then, identify the project participant who is responsible for preparing each document. Document: Certificate of Substantial Completion
FACILITY LIFE CYCLE STAGE: Construction RESPONSIBLE PARTICIPANT: Architect/Engineer
39
Match each document to the facility life cycle stage in which it is prepared. Then, identify the project participant who is responsible for preparing each document. Document: Construction Schedule
FACILITY LIFE CYCLE STAGE: Construction RESPONSIBLE PARTICIPANT: Contractor
40
Match the descriptions to the correct written format and standard type. Organizes the content within a single specification section
Written format: Sectionformat Standard type: Compositional
41
Match the descriptions to the correct written format and standard type. Organizes construction information based on physical parts of a facility called functional elements or systems and assemblies
Written format: Uniformat Standard type: Taxonomical
42
Match the descriptions to the correct written format and standard type. Standardizes the presentation of specification information on the printed page
Written format: Pageformat Standard type: Compositional
43
Match the descriptions to the correct written format and standard type. Standardizes preliminary project information using descriptions of basic systems and assemblies
Written format: PPDformat Standard type: Compositional
44
Match the descriptions to the correct written format and standard type. Classifies information applicable to the entire built environment
Written format: Omniclass Standard type: Taxonomical
45
Match the descriptions to the correct written format and standard type. Organizes construction, operation, and maintenance information of a facility based on work results
Written format: Masterformat Standard type: Taxonomical
46
Identify which written format is described by each statement. Includes MasterFormat and UniFormat
Written format: Omniclass
47
Identify which written format is described by each statement. Uses UniFormat as the structure for a preliminary project description
Written format: PPDFORMAT
48
Identify which written format is described by each statement. Has subjects in PART 1 that are extensions of MasterFormat Division 01
Written format: Sectionformat
49
Identify which written format is described by each statement. Used for organizing standard drawing details
Written format: Uniformat
50
Identify which written format is described by each statement. Used to structure preliminary cost estimates
Written format: Uniformat
51
Identify which written format is described by each statement. Used to organize construction specifications
Written format: Masterformat
52
Identify which written format is described by each statement. Used to organize database structures
Written format: Omniclass
53
Identify which written format is described by each statement. Used to organize product literature by work results
Written format: Masterformat
54
Identify which written format is described by each statement. Used to structure construction costs
Written format: Masterformat
55
Identify which written format is described by each statement. Organizes a MasterFormat specification section into three PARTS
Written format: Sectionformat
56
Identify which written format is described by each statement. Used to organize performance specifications
Written format: Uniformat
57
Identify which written format is described by each statement. Lays out text of a MasterFormat specification section in a standardized format
Written format: Pageformat
58
Identify which written format is described by each statement. Used to organize preliminary project descriptions
Written format: Uniformat
59
Identify which written format is described by each statement. Organizes the text of a preliminary project description
Written format: PPDFORMAT
60
List each of the four major components of NCS next to their corresponding description NCS major components: AIA CAD Layer guidelines
Provides a hierarchical organization for describing drawing layers
61
List each of the four major components of NCS next to their corresponding description NCS major components: CSI Uniform drawing systems
Organizes and presents the drawings and project information in a standard format for use in planning, design, construction, and operation of facilities throughout its lifecycle
62
List each of the four major components of NCS next to their corresponding description NCS major components: BIM implementation
States the NCS is the standard for design and construction drawing output from the BIM process
63
List each of the four major components of NCS next to their corresponding description NCS major components: Plotting guidelines
Ensures printed lines are easy to read so that the drawings can be interpreted properly
64
a digital representation of physical and functional characteristics of a facility. As such it serves as a shared knowledge resource for information about a facility forming a reliable basis for decisions during its lifecycle from inception onward.”
A BIM
65
Write the name of each rule courts use when interpreting contract documents next to the corresponding description. Ambiguous provisions will be interpreted against the party drafting the provision on the basis that the drafter had superior knowledge of the subject matter and should have been more specific or accurate in the preparation of the provision.
Construction against the drafter
66
Write the name of each rule courts use when interpreting contract documents next to the corresponding description. When specific information is written, the courts interpret it as intentional for the work and will be given more importance than general information or printed provisions.
Specific takes precedence over general
67
Write the name of each rule courts use when interpreting contract documents next to the corresponding description. Contract law is founded on the principle that two parties are mutually free to determine the terms of an agreement, within the bounds of lawful activities, for a specific purpose. Those who do so are seen as having the capacity to contract for products or services.
Autonomy to contract
68
Write the name of each rule courts use when interpreting contract documents next to the corresponding description. If the contract documents do not adequately establish the intentions of the contract provisions, then the court may rely on the customs and practices of an industry or a trade
Trade customs
69
Write the name of each rule courts use when interpreting contract documents next to the corresponding description. When considering questions, the court will search for the meanings of the words used and the purposes of the contract provisions. The documents will be interpreted in an effort to establish the parties’ intentions. If ambiguities or conflicts are found, other contract documents will be examined in the effort to find definitions and meanings. If an issue under consideration is of a technical nature, the specifications will be examined.
Entire agreement
70
Write the name of each rule courts use when interpreting contract documents next to the corresponding description. Ambiguous provisions will be interpreted by the court according to the practical meanings placed on them by the parties to the agreement.
Practical interpretation
71
Match each of the six (6) fundamental sustainable design approaches to the corresponding description. Repurposing historic or functionally obsolete buildings.
Historic presentation and rehabilitation
72
Match each of the six (6) fundamental sustainable design approaches to the corresponding description. Reusing building materials; using materials with recycled content; using regional materials; using materials from rapidly renewable sources; reducing waste reduction and encouraging recycling during construction and in the workplace; and using materials that do not reduce indoor air quality
Materials and resources
73
Match each of the six (6) fundamental sustainable design approaches to the corresponding description. Making best use of the site in regard to orientation; use of rainwater percolation and storage; reduced impact on infrastructure, neighborhood, and ecosystem; reduced heat island effect; use of brownfields in lieu of greenfields; and encouraging sustainable construction practices.
Site optimization
74
Match each of the six (6) fundamental sustainable design approaches to the corresponding description. Improving thermal comfort, ventilation, and moisture control; maximizing daylighting; using materials with low VOCs; controlling tobacco smoke; improving acoustic qualities; providing access to nature; and conducting building flush out or testing for off-gassing.
Environmental quality
75
Match each of the six (6) fundamental sustainable design approaches to the corresponding description. Reducing potable water usage for building and landscaping, and collecting and reusing water resources.
Water use and conservation
76
Match each of the six (6) fundamental sustainable design approaches to the corresponding description. Designing buildings with low energy usage; implementing renewable energy sources; reduce generation of greenhouse gases; implementing controls for building systems; and encouraging the use of commissioning.
Energy performance and conservation
77
For sustainability requirements, each team member has responsibilities. For each set of responsibilities, write the name of the responsible team member(s). Understand the project’s sustainability goals ‣ Have experience in the type of construction required ‣ Ensure that construction methods and techniques, purchasing of products, and management of construction waste are applied in a manner that fulfills the owner’s sustainability requirements
Contractor, Design/builder, and construction manager at risk
78
For sustainability requirements, each team member has responsibilities. For each set of responsibilities, write the name of the responsible team member(s). Implement maintenance procedures that support the sustainable design principles
Facility manager
79
For sustainability requirements, each team member has responsibilities. For each set of responsibilities, write the name of the responsible team member(s). Understand sustainability design principles and approaches and how they might affect construction cost ‣ Maintain sustainability goals throughout the facility life cycle ‣ Prioritize sustainability as a goal early during project conception
Owner
80
For sustainability requirements, each team member has responsibilities. For each set of responsibilities, write the name of the responsible team member(s). Be knowledgeable of sustainable design principles and approaches ‣ Apply the concepts properly to fulfill the owner’s requirements ‣ Understand how sustainability affects construction cost
Architect/Engineer