Project Finance Flashcards
What is loss and expense ?
A contractors claim for loss and expense at the same time as an extension of time. It is the money required for delay and disruption, inefficient working and/or employing more resources.
“What are common heads of loss and expense?
What are common heads of Claims? (HASAN)
“
“1. Additional cost: inflation, additional work, prolongation
2. Site office overhead / Prelims
3. Head office overhead: formulas?
4. Disruption
5. Loss of profit/business opportunity
6. Finance charges”
“What are the Claims particulars ?
“
“1. Notices, preconditions, timebars, EWN
2. Contractual entitlement
3. Cause and effect
4. Records of costs incurred”
How to avoid claims ?
“1. Balanced risk allocation.
2. Enough design info and specs.
3. Good faith and partnering.
4. Right procurment route for level of design maturity.
5. Clear contract documents without ambiguities.
6. Challenge baseline program at earliest.
“
“Having advised the client and established the change control procedure on Project X, how was this then implemented?
How do you implement change control procedure? (HASAN)
How do you manage Change? (HASAN)”
”- Communicate Procedure as narrative and flow chart to the team and explain in a meeting. Include in PEP.
- Change control forms issued to the team.
- Setting regular change control meetings with the team.
- Maintain Register/tracker of change control.
- Ensure adherence to procedure before costing and send to client for approval.
- Ensure full impact of change captured and instruction issued after client signature only.”
“Your final assessment record states that you established the cost reporting protocol on project X. What approach did you take to this?
How to establish cost reporting protocol? (HASAN)”
”- Consider Procurement route,
- Report content and format,
- Frequency and timing/cut-off date of issue,
- Distribution list and means of issue,
- Interface with Client Finance team,
- Additional requirements by stakeholders/funders”
“Key issues to consider when designing change control procedures?
I see from your summary of experience that you advised the client and implemented a change control procedure on your project X. Can you tell me the key issues you considered in advising the client upon the procedure to be adopted?
How do you establish/design change control procedure? (HASAN)”
“1. Project procurement route and impact during design and construction
2. identify key decision makers to approve changes
3. Client’s priorities from monitoring change?
4. change control procedure process and forms
5. evaluation and measuring change
6. costs to include in evaluating change, finance, professional fees, vat
7. responsibility and communication matrices for raising changes
8. the contract mechanism to administer the change control management system.
“
“What measures can be taken to effectively control costs during the construction phase of a project?
Post-contract cost control tools? (Hasan)”
“Regular cost reporting which is also forward looking
Proactive risk and contingency management
Implementing a robust change control process
Management of provisional sums within budget
Final Account”
What is RIBA Plan of Work stages? (2013), for 2020 change developed design by spatial coordination
“Stage 00 – Strategic Definition
Stage 01 – Preparation and Brief
Stage 02 – Concept Design
Stage 03 – Developed Design
Stage 04 – Technical Design
Stage 05 – Construction
Stage 06 – Handover and Close Out
Stage 07 – In Use
“
What is Cost control? and Procedures you undertake to cost control?
“Process of controlling costs of activity, process or company. includes procedures to:
1) detect variance between budgeted and actual cost.
2) detect cause of cost variance.
3) Corrective measure to re-align actual cost with budget.
“
What are the cost control tools?
“Pre-Contract: Cost Plan, PTE
Post-Contract:
1. Cost Report,
2. Risk Management
3. Provisional Sum
4. Change Control
5. Final Account”
Finance control? What is it about?
“Financial management of activities to achieve desired ROI. Involves:
1) Capital investment of project,
2) Professional/legal fees,
3) Finance charges,
4) Lifecycle cost (operation and maintenance).
“
Finance Control tools?
Financial statements (budget, income, balance, cashflow, equity)
Cost Monitoring?
Proactive continuous monitor of cost impact o: changes and risks, and, items in design, and instructions.
Provisional Sum ?
“NRM2: Sum of money set aside to carry out work that cannot be described and given in quantified items (in accordance with the tabulated rules of measurement). Types: defined and undefined.
Defined: Nature of work, quantity indicate scope and extent, How and where to be fixed to building, Restrictions/limitations.
“
Impact of defined and undefined provisional sum?
Defined PS allow Contractor to Price for PS in time related Preliminaries and allow time in programme. Undefined contractor cannot price for Prelim and allow time in programme
PC Rate/ Prime Cost Sum
NRM 2 definition is a sum of money included in a unit rate to be expended on materials or goods from suppliers (e.g. supply only ceramic wall tiles at £36.00/m2) no OHP
I am client in Fidic RB 99. I want to fix specific floor finish what mechanism allow me to do so in contract?
PS, PC, or NSC?
How do you administer the cost during the post contract stage?
”* Through cost report.
* Breakdown costs into elements then compare elemental actual cost against budgeted.
* then monitor and report variance, variance root cause, and possible corrective measures/source of fund, address any risk of cost-overrun after projection final contract amount.
* Example- Main works > Tower A, Podium, basement > Tower A Structural/MEP/Finishes > Tower A structural > Masonry, Concrete, Metal > Concrete
What is change control management? Variation?
“Change control management: method to assess and manage changes in terms of scope, cost, and program to allow the client to make informed decision.
Variation: alternation to scope, size, quantity, quality, dimension of works or sequence of events”
What is Cardinal Change? why its important?
Major change over and beyond project scope of work. provide relief to contractors in some juridiction from being bound to change instruction not relevant to scope of work.
Reasons for Variations ?
“client instructions, design error/omission, site conditions.
Driven by: technological, VE, cost saving, revised drawing, social, environmental, regulations/legal, aesthetics, unforseen issues”
What is BIM? How it benefits Change control management?
“BIM: Process for creating and managing information on a construction project across its life cycle.
BIM benefits: Reduce waste and improve efficiency
enable swift assessment of alternative design proposals
Help visualize changes”
PEP?
Project execution plan (PEP): An overarching document that provides the framework to execute, monitor, and assess and control the project.