Project Finance Control & Cost Reporting, Design Economics and Cost Planning, & Quantification and Costing Flashcards
What are the typical responsibilities of the cost manager on a construction project?
Subject to the scope of service, typical responsibilities include. Managing risk allowance expenditure, initiate action to avoid overspending, prepare pricing documents for tendering, evaluating, and analysing tender bids, preparing interim valuations, value CE’s, negotiate and agree final accounts, issues financial reports, provide initial cost advice on whole life costs, produce cost estimates and cost plans, produce cost reports, estimates, and forecasts, prepare, and maintain cash-flow forecasts.
If you are producing estimates and cost plans, which measurement rules represent industry best practice for capital building and building maintenance works in the UK?
New Rules of Measurement (NRM)
Can you name three NRM documents?
NRM1 – Order of Cost Estimating and Cost Planning for Capital Building Works
NRM2 – Detailed measurement for building works
NRM3 – Order of Cost Estimating and Cost Planning for Building Maintenance Works
Can you provide a brief overview of each of the NRM documents please?
NRM1 – Provides guidance on the quantification and costing of building works for the purpose of preparing cost estimates and cost plans. It is the ‘cornerstone’ of good cost management of construction projects, enabling more effective and accurate cost advice to be given to clients and other project team members, as well as facilitating better cost control.
NRM2 – Is written mainly for the preparation of bill of quantities and quantified schedule of works.
NRM3 – Gives guidance on the quantification and description of maintenance works for the purpose of preparing initial order of cost estimates. The rules also aid procurement and cost control of maintenance works.
What is the structure of NRM1?
General Introduction, Measurement rules for order of cost estimating, Measurement rules for cost planning, Tabulated rules of measurement for elemental cost planning, Appendices.
What is an example of a measurement rule in NRM1?
Soil Stabilisation is to be measured in M2 and the area measured is the area affected by the soil stabilisation.
Where you could find guidance on what is included and excluded in the GIFA?
The Code of Measuring Practice guidance by RICS
What is the structure of NRM2?
General introduction, Detailed measurement of building works, Rules of measurement for building works, Appendices.
What is CROME references in NRM3?
Construction, renewal, operation, maintenance, end of lift costs.
Why is it important to measure the works according to industry standards and best practice?
To provide consistency and greater accuracy in pricing. To ensure that all parties price on the same basis and therefore reduce the risk of dispute.
Is it mandatory for Chartered Surveyors to follow the procedures set out in NRM?
Following NRM is not a mandatory requirement. However, when an allegation of professional negligence is made against a surveyor, the adjudicator or court is likely to take account of the contents of any relevant guidance notes published by RICS in deciding whether the surveyor acted with reasonable competence.
What are preliminary costs?
Necessary costs which are not usually tangibly reflected in the finished works.
What are the key headings for contractor preliminaries identified in NRM2?
Employer’s requirements, Site accommodation, Site records, Site establishment, Temporary Services, Mechanical Plant, Temporary Works, Cleaning, Fees and Charges, Insurance, Bonds, guarantees, warranties.
How is risk dealt with under NRM?
NRM recommends that risk allowances are not standard percentages, but a properly considered assessment of the risk, considering the completeness of the design and other uncertainties such as the extent of site investigation undertaken.
Can you tell me the 4 risk categories identified under NRM?
Employer Change Risk, Employer Other Risk, Design Development Risk, Construction Risk.
Name some examples of Employer Change Risk?
Changes in scope of works or project brief, changes in quality, changes in time.
Name some examples of Employer Other Risk?
Inadequate or unclear project brief, unrealistic design and construction programmes, contractual claims, acceleration of construction works, delay in payment.
Name some examples of Design Development Risk?
Inadequate or unclear project brief, inadequate site investigation, use of provisional sums.
Name some examples of Construction Risk?
Inadequate site investigation, ground water, tree preservation orders, contaminated ground.
How does NRM defined the ‘cost limit’ for the project?
NRM1 – The maximum expenditure the client is prepared to make in relation to the completed building. Includes construction costs, the cost of professional services, certain other project costs, items required post completion and during its operation, and risk allowances.
How does NRM define the ‘base cost estimate’ for the project?
NRM1 – An evolving estimate of known factors without any allowances for risk and uncertainty, or an element of inflation. The base cost estimate is the sum of the works cost estimate, the project and design team fees estimate, and the other development and project costs estimate.
What are ‘other development and project costs’?
Costs not necessarily directly associated with the cost of constructing the building. Lands acquisition is an example.
What is an ‘order of cost estimate’?
NRM1 – An estimate based on benchmarked data for a similar type of project based on the client’s strategic definition or initial brief. Its purpose is to establish the affordability of a proposed development for a client. It takes place prior to the preparation of a full set of working drawings or bills of quantities and forms the initial build-up to the cost planning process. Order of cost estimates are a method of cost prediction.
What RIBA stage is the order of cost estimate typically produced?
RIBA Stage 1 – Preparation and Briefing