Project Finance, Design Economics & Cost Planning,Quantification & Costing. Flashcards

(46 cards)

1
Q

What are the typical responsibilities of the cost manager on a construction project?

A

Subject to the scope of service, typical responsibilities may include:
• Manage risk allowance expenditure.
• Initiate action to avoid overspending.
• Prepare pricing documents for tendering.
• Evaluate and analyse tender bids.
• Prepare interim valuations.
• Value variations and compensation events.
• Assess the contractor’s financial claims.
• Negotiate and agree final accounts.
• Issue financial reports or statements.
• Provide initial cost advice on capital investment costs.
• Produce cost estimates and cost plans.
• Provide advice on whole life costs.
• Produce cost reports, estimates, and forecasts.
• Prepare and maintain the cash flow forecast.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the structure of NRM 1?

A

• 1: General introduction.
• 2: Measurement rules for order of cost estimating.
• 3: Measurement rules for cost planning.
• 4: Tabulated rules of measurement for elemental cost planning.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the structure of NRM 2?

A

1: General introduction.
• 2: Detailed measurement of building works.
• 3: Rules of measurement for building works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the structure of NRM 3?

A

1: General introduction.
• 2: Measurement rules for building maintenance works.
• 3: Measurement rules for order of cost estimating.
• 4: Cost planning of R and M works.
• 5: Calculation of annualised costs for R and M works.
• 6: Elemental cost planning.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How does NRM define the ‘cost limit’ for the project?

A

NRM 1 definition: The maximum expenditure the client is prepared to make in relation to the completed building. Includes construction costs, the cost of professional services, certain other project costs, items required post completion and during its operation, and risk allowances.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How does NRM define the ‘base cost estimate’ for the project?

A

NRM 1 definition: An evolving estimate of known factors without any allowances for risk and uncertainty, or an element of inflation. The base cost estimate is the sum of the works cost estimate, the project and design team fees estimate, and the other development and project costs estimate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is an ‘order of cost estimate’?

A

NRM 1 definition: An estimate based on benchmark data for a similar type of project based on the client’s strategic definition or initial brief. Its purpose is to establish the affordability of a proposed development for a client. It takes place prior to the preparation of a full set of working drawings or bills of quantities and forms the initial build-up to the cost planning process. Order of cost estimates are a method of cost prediction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which RIBA Stage is the order of cost estimate typically produced?

A

RIBA Stage 1 – Preparation and Briefing.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the RIBA Stages of Work?

A

• Stage 0: Strategic Definition.
• Stage 1: Preparation and Briefing.
• Stage 2: Concept Design.
• Stage 3: Spatial Coordination.
• Stage 4: Technical Design.
• Stage 5: Manufacturing and Construction.
• Stage 6: Handover.
• Stage 7: Use

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Can you explain the term ‘cost per functional unit’?

A

NRM 1 definition: The unit rate that, when multiplied by the number of functional units, gives the total building works estimate (i.e. works cost estimate minus the main contractor’s preliminaries and the main contractor’s overheads and profit). The total recommended cost limit (i.e. the cost limit, including inflation) can also be expressed as a cost per functional unit when reporting costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What typical information should accompany an order of cost estimate?

A

• Covering letter.
• Executive summary.
• Cost limit.
• Specification notes.
• Assumptions.
• Exclusions.
• Drawings and other information upon which the estimate is based.
• A schedule of value-enhancing options.
• Risk register.
• Cash flow information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a cost plan?

A

NRM1 definition: In the context of cost prediction, a cost plan is ‘an estimate based on a specific design’.
• A statement showing an apportionment of an estimate of or an agreed budget between cost headings.
• Cost planning is a method of cost prediction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Do you need a programme to complete the cost plan?

A

Preliminaries are typically presented as a weekly rate in developed cost plans; therefore, a programme or at least some high-level dates will be required.
• The key information usually required is:
• Design and tendering periods.
• Start on site date.
• Construction period.
• Completion date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a cost plan risk allowance?

A

NRM 1 definition: A quantitative allowance set aside as a precaution against risks and future requirements to allow for uncertainty of outcome.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

When calculating the total fee estimate for a project, what component fees might be included?

A

Consultant fees:
• Project and design team.
• Other specialist consultants.
• Survey fees.

Contractor fees:
• Management and staff.
• Specialist support staff.
• Contractor’s design management fees.
• Contractor design team fees (if applicable).
• Framework fees (if applicable).

Others:
• Planning permission application fees.
• Statutory undertaker fees.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What benefit does the client get out of accurate cost planning?

A

• The cost plan confirms to the client that the scheme is affordable (or not).
• Cost planning places the client in an informed position to make commercial decisions.
• The cost plan can act as a value management tool to ensure the client gets a building that not only meets their needs but also represents best value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

How would you deal with a cost plan that is over budget?

A

• Communicate the matter to the client and project team in a clear and concise manner.
• Identify areas where potential savings can be made, possibly in terms of material specification or redesign

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

How can the cost manager help control the design to keep the project within budget?

A

• Explain to the design team where the cost plan sits against the budget and discuss the limitations.
• Identify and communicate areas of design which may not be economical.
• Regular project risk reviews and asking the design team to focus on mitigating key design risks.
• Explain how changes in the design will impact the cost plan.
• Contribute to value engineering and/or cost-saving sessions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

In your view, what are some of the key reasons we have cost overrun on a project?

A

• Ambiguous client briefs or changes in the later stages of the project.
• Unrealistic cost estimates.
• Project risk is realised or not properly managed.
• Inadequate management control or processes.
• Uncoordinated design.
• Unknown external factors (for example, global pandemics).
• Unsuitable tendering and/or procurement strategy selection.
• Statutory authority influences, such as onerous planning permission conditions.
• Inflation or changing market conditions.

20
Q

What allowance would you make for contractor OH&P in the cost plan?

A

The percentage will vary due to various factors, such as:
• Project location.
• Level of perceived risk.
• Project type and value.
• Market conditions.

21
Q

What is a provisional sum?

A

Provisional sums are generally an allowance or estimate included within the contract price that are:
• Not sufficiently defined, designed, or detailed to allow an accurate determination of its cost at the time the contract is entered; and/or
• Work that the employer may or may not wish to be carried out.

22
Q

What types of provisional sums are there?

A

• Defined and undefined.

23
Q

Please explain the deferral between defined and undefined provisional sums?

A

Defined:
• The contractor is deemed to have allowed for programming and preliminaries within the contract.

Undefined:
• The contractor does not allow for planning, programming or preliminaries. This means the contractor may be entitled to an extension of time and/or additional preliminaries when the actual works are undertaken.

24
Q

What are prime cost sums (PC sums)?

A

• A sum of money included in a unit rate to be expended on materials or goods from suppliers (e.g., supply-only ceramic wall tiles at £50/m²).
• It is a supply-only rate for materials or goods where the precise quality of those materials or goods is unknown.
• PC sums exclude all costs associated with fixing, installation, fees, OH&P, etc.

25
Can you name some of the pricing documents we might use at tender stage?
• Bill of quantities (BoQ). • Schedule of rates (SoR). • Contract sum analysis (CSA). • Schedule of work (SoW). • Priced activity schedule
26
Can you name some of the pricing options for construction contracts?
• Lump sum. • Cost-plus (also known as cost reimbursable). • Remeasurement. • Target cost. • Guaranteed maximum price (GMP).
27
What is a lump sum contract?
• Fixed price or lump sum pricing, as the name indicates, provides for payment of a set amount. • The amount of the fixed price or lump sum is determined by a contractor by estimating their cost to provide the work, and then adding overhead and a profit margin
28
What is a cost-plus contract?
Cost-plus contracts, otherwise known as cost reimbursable contracts, involve the employer paying the contractor for the costs incurred during the project, plus a pre-agreed percentage for profit.
29
What are the key advantages of cost-plus contracts?
• Since cost-plus contracts are flexible by nature, inaccuracies in the initial bid aren’t as detrimental as they are with lump sum contracts. • Cost-plus contracts allow employers to make design changes along the way, as contractors know they’ll be paid for the extra time or materials that those changes incur
30
When might a cost-plus strategy be appropriate to use?
• A cost-plus strategy might be used where the nature or scope of work to be carried out cannot be properly defined at the outset. • This pricing strategy would suit emergency work such as infrastructure repairs or immediate reconstruction following a fire
31
What is a remeasurement contract?
• Works are carried out based on pre-agreed unit rates. • The actual quantities of work carried out are measured, and the tendered rates are applied to those quantities. • The contractor is paid for the actual work they have done, so the final value of the project will be derived based on the unit prices and exact quantities
32
What are the key advantages of remeasurement contracts?
• Since the work is tendered on approximate quantities, the contractors will submit competitive prices in their tender. • The contractor’s risk is comparatively low (compared to a lump sum contract).
33
What are the key disadvantages of remeasurement contracts?
• There is less cost certainty until the project is complete. • General accuracy of cash flow forecasting is lower. • The risk for the employer is higher (compared to a lump sum contract
34
What is a guaranteed maximum price (GMP) contract?
• A guaranteed maximum price contract (GMP) sets a limit that the employer will pay their contractor, regardless of the actual costs incurred (i.e., the contract sum will not exceed a specified maximum). • If the actual cost of the works is higher than the guaranteed maximum price, then the contractor must bear the additional cost. • If the cost is lower than the guaranteed maximum price, the contract should set out which party will benefit from the savings. Usually, the savings will be split between the employer and contractor using a pre-agreed formula or percentage
35
What are the key advantages of a GMP?
• Establishes the employer’s maximum financial commitment (subject to employer variations). If the contractor’s costs exceed the target cost, only the target cost is paid. • Both the contractor and employer have the potential to benefit from savings
36
What are the key disadvantages of a GMP?
The contractor will have to share any savings made while taking on the risk of cost overrun
37
What are contractor preliminaries?
• Items that cannot be allocated to a specific element, sub-element, or component. • Preliminaries are typically items that are necessary for the contractor to complete the works but will not actually become part of the works once the project is complete. • Contractor preliminaries may include items such as: • Management and staff. • Site establishment. • Temporary services. • Security. • Safety and environmental protection. • Insurances
38
When assessing the costs for contractor preliminaries (at tender stage), what are the key considerations to determine if they are fair and reasonable?
• Length of contract • Type of project (new build, refurbishment, infrastructure, etc.) • Size of the project and overall build cost. • Need for temporary works. • Security requirements. • Method and sequencing of works (working hours, supervision, management, etc.) • Extent of the contractor’s design responsibilities.
39
What is inflation?
NRM 1 definition: Sustained increase in the general price level of resources (ISO 15686-5). • It is included as an allowance in the order of cost estimate or cost plan for fluctuations in the basic prices of labour, plant, equipment, and materials.
40
What are the two types of inflation as defined in NRM 1?
• Tender inflation: • An allowance included in the order of cost estimate or cost plan for fluctuations in the basic prices of labour, plant, equipment, and materials during the period from the estimate base date to the date of tender return. • Construction inflation: • An allowance included in the order of cost estimate or cost plan for fluctuations in the basic prices of labour, plant, equipment, and materials during the period from the date of tender return to the mid-point of the construction period.
41
What do TPIs show?
• They measure the movement in prices agreed between clients and contractors at ‘commit to construct’, normally when the tender is accepted. • These indices are typically used for adjusting estimates and budgets to different dates
42
What is a bill of quantities (BoQ)?
• Bills of quantities are a means of breaking a project down into exact quantities that are measured in an industry-wide recognised format. • Includes all components of a building (or project) as well as preliminaries. • Usually based on mature drawings and specifications; at tender stage, the contractor inserts their cost or rate against each item. • The document then forms a precise tool for pre and post-contract cost control (such as managing variations, project expenditure, and cash flow
43
What are the key disadvantages of using a BoQ?
• Expensive and time-consuming to produce. • Potential for errors when measuring the project
44
What are the key advantages of using a BoQ?
• Ideal for post-contract cost control. • Simplified tender analysis. • Very detailed and comprehensive. • All the tenderers are pricing the same items and quantities. • Effective document for interim payments and preparing the final account
45
What are the two key types of BoQ?
Firm BoQ: • NRM 2 definition: The reliability of the tender price will increase in relation to the accuracy of the quantities provided (i.e., the more precisely the work is measured and described). • In theory, if there were no design changes, a firm BQ would provide a price at the tender stage, which would equal the final cost. Approximate BoQ: • NRM 2 definition: Approximate BQs are used when there is not enough detail to prepare a firm BQ, or where it is decided by the client that the time or cost of producing a firm BQ is not warranted. • Such contracts do not provide a lump sum price, but rather tender price totals (i.e., a quantified schedule of rates), since the quantities are subject to remeasurement on completion by the quantity surveyor/cost manager.
46
When would a BoQ with approximate quantities be used?
Since the quantities are approximate, this type of BoQ is suitable for a remeasurement form of contract.