Project Finance, Design Economics & Cost Planning,Quantification & Costing. Flashcards
(46 cards)
What are the typical responsibilities of the cost manager on a construction project?
Subject to the scope of service, typical responsibilities may include:
• Manage risk allowance expenditure.
• Initiate action to avoid overspending.
• Prepare pricing documents for tendering.
• Evaluate and analyse tender bids.
• Prepare interim valuations.
• Value variations and compensation events.
• Assess the contractor’s financial claims.
• Negotiate and agree final accounts.
• Issue financial reports or statements.
• Provide initial cost advice on capital investment costs.
• Produce cost estimates and cost plans.
• Provide advice on whole life costs.
• Produce cost reports, estimates, and forecasts.
• Prepare and maintain the cash flow forecast.
What is the structure of NRM 1?
• 1: General introduction.
• 2: Measurement rules for order of cost estimating.
• 3: Measurement rules for cost planning.
• 4: Tabulated rules of measurement for elemental cost planning.
What is the structure of NRM 2?
1: General introduction.
• 2: Detailed measurement of building works.
• 3: Rules of measurement for building works.
What is the structure of NRM 3?
1: General introduction.
• 2: Measurement rules for building maintenance works.
• 3: Measurement rules for order of cost estimating.
• 4: Cost planning of R and M works.
• 5: Calculation of annualised costs for R and M works.
• 6: Elemental cost planning.
How does NRM define the ‘cost limit’ for the project?
NRM 1 definition: The maximum expenditure the client is prepared to make in relation to the completed building. Includes construction costs, the cost of professional services, certain other project costs, items required post completion and during its operation, and risk allowances.
How does NRM define the ‘base cost estimate’ for the project?
NRM 1 definition: An evolving estimate of known factors without any allowances for risk and uncertainty, or an element of inflation. The base cost estimate is the sum of the works cost estimate, the project and design team fees estimate, and the other development and project costs estimate.
What is an ‘order of cost estimate’?
NRM 1 definition: An estimate based on benchmark data for a similar type of project based on the client’s strategic definition or initial brief. Its purpose is to establish the affordability of a proposed development for a client. It takes place prior to the preparation of a full set of working drawings or bills of quantities and forms the initial build-up to the cost planning process. Order of cost estimates are a method of cost prediction.
Which RIBA Stage is the order of cost estimate typically produced?
RIBA Stage 1 – Preparation and Briefing.
What are the RIBA Stages of Work?
• Stage 0: Strategic Definition.
• Stage 1: Preparation and Briefing.
• Stage 2: Concept Design.
• Stage 3: Spatial Coordination.
• Stage 4: Technical Design.
• Stage 5: Manufacturing and Construction.
• Stage 6: Handover.
• Stage 7: Use
Can you explain the term ‘cost per functional unit’?
NRM 1 definition: The unit rate that, when multiplied by the number of functional units, gives the total building works estimate (i.e. works cost estimate minus the main contractor’s preliminaries and the main contractor’s overheads and profit). The total recommended cost limit (i.e. the cost limit, including inflation) can also be expressed as a cost per functional unit when reporting costs.
What typical information should accompany an order of cost estimate?
• Covering letter.
• Executive summary.
• Cost limit.
• Specification notes.
• Assumptions.
• Exclusions.
• Drawings and other information upon which the estimate is based.
• A schedule of value-enhancing options.
• Risk register.
• Cash flow information
What is a cost plan?
NRM1 definition: In the context of cost prediction, a cost plan is ‘an estimate based on a specific design’.
• A statement showing an apportionment of an estimate of or an agreed budget between cost headings.
• Cost planning is a method of cost prediction.
Do you need a programme to complete the cost plan?
Preliminaries are typically presented as a weekly rate in developed cost plans; therefore, a programme or at least some high-level dates will be required.
• The key information usually required is:
• Design and tendering periods.
• Start on site date.
• Construction period.
• Completion date.
What is a cost plan risk allowance?
NRM 1 definition: A quantitative allowance set aside as a precaution against risks and future requirements to allow for uncertainty of outcome.
When calculating the total fee estimate for a project, what component fees might be included?
Consultant fees:
• Project and design team.
• Other specialist consultants.
• Survey fees.
Contractor fees:
• Management and staff.
• Specialist support staff.
• Contractor’s design management fees.
• Contractor design team fees (if applicable).
• Framework fees (if applicable).
Others:
• Planning permission application fees.
• Statutory undertaker fees.
What benefit does the client get out of accurate cost planning?
• The cost plan confirms to the client that the scheme is affordable (or not).
• Cost planning places the client in an informed position to make commercial decisions.
• The cost plan can act as a value management tool to ensure the client gets a building that not only meets their needs but also represents best value
How would you deal with a cost plan that is over budget?
• Communicate the matter to the client and project team in a clear and concise manner.
• Identify areas where potential savings can be made, possibly in terms of material specification or redesign
How can the cost manager help control the design to keep the project within budget?
• Explain to the design team where the cost plan sits against the budget and discuss the limitations.
• Identify and communicate areas of design which may not be economical.
• Regular project risk reviews and asking the design team to focus on mitigating key design risks.
• Explain how changes in the design will impact the cost plan.
• Contribute to value engineering and/or cost-saving sessions
In your view, what are some of the key reasons we have cost overrun on a project?
• Ambiguous client briefs or changes in the later stages of the project.
• Unrealistic cost estimates.
• Project risk is realised or not properly managed.
• Inadequate management control or processes.
• Uncoordinated design.
• Unknown external factors (for example, global pandemics).
• Unsuitable tendering and/or procurement strategy selection.
• Statutory authority influences, such as onerous planning permission conditions.
• Inflation or changing market conditions.
What allowance would you make for contractor OH&P in the cost plan?
The percentage will vary due to various factors, such as:
• Project location.
• Level of perceived risk.
• Project type and value.
• Market conditions.
What is a provisional sum?
Provisional sums are generally an allowance or estimate included within the contract price that are:
• Not sufficiently defined, designed, or detailed to allow an accurate determination of its cost at the time the contract is entered; and/or
• Work that the employer may or may not wish to be carried out.
What types of provisional sums are there?
• Defined and undefined.
Please explain the deferral between defined and undefined provisional sums?
Defined:
• The contractor is deemed to have allowed for programming and preliminaries within the contract.
Undefined:
• The contractor does not allow for planning, programming or preliminaries. This means the contractor may be entitled to an extension of time and/or additional preliminaries when the actual works are undertaken.
What are prime cost sums (PC sums)?
• A sum of money included in a unit rate to be expended on materials or goods from suppliers (e.g., supply-only ceramic wall tiles at £50/m²).
• It is a supply-only rate for materials or goods where the precise quality of those materials or goods is unknown.
• PC sums exclude all costs associated with fixing, installation, fees, OH&P, etc.