Project Management Flashcards

1
Q

EV

A

Earned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

AC

A

Actual Costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

PV

A

Planned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

CV

A

Cost Variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

SV

A

Schedule Variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

CPI

A

Cost Performance Index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

SPI

A

Schedule Performance Index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

EAC

A

Estimated Cost at Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

BAC

A

Budgeted Cost at Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

VAC

A

Variance at Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

ECD

A

Estimated Completion Date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

ECTC

A

Estimated Cost to Complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

SC

A

Scheduled Completion Date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

CV=

A

EV-AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

SV=

A

EV-PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

CPI=

A

EV/AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

SPI=

A

EV/PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

VAC=

A

BAC-EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

EAC1=

A

BAC-CV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

EAC2=

A

BAC/CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

ECD1=

A

SC-SV(time)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

ECD2=

A

SC(time taken to perform work to date/time work should have taken)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Assumption 1:

A

Outstanding work will be completed at original budget at completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Assumption 2:

A

Outstanding work will be completed at same cost factor observed in project so far

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Stages of Project Control Analysis:
1. Define work breakdown structure 2. Identify and develop resource schedule 3. Develop time-phased budget 4. Develop actual cost of work performed 5. Collect percentage complete and multiply by original planned budget to determine the value of the work completed (EV) 6. Complete variance analysis
26
Gantt charts can be used for
effective communication in monitoring time performance across all levels
27
A tracking Gantt chart can be useful
- to track and trend schedule performance - to add actual and revised time estimates - to provide a quick overview of project status
28
Benefits of earned value analysis:
- Disciplined planning and risk management - Good project visibility - Objective and quantitative performance measurement - Early indication of problems - Ability to accurately predict project cost and schedule
29
Drawbacks of schedule variance:
- Does not show individual activity contribution on graphs - Does not distinguish between critical and non-critical activities - Directly concerned with schedule for spending money and not directly concerned with time-based schedule - Can be difficult to visualise
30
If CV>0
underbudget
31
If CV<0
overbudget
32
If SV>0
ahead of schedule
33
If SV<0
behind schedule
34
Scope creep is
the cumulative effect of minor refinements to the original project scope
35
Scope creep is common early in projects because
- additional features are added - new technologies are discovered - poor design assumptions are found
36
Scope creep can be reduced by
having a well defined scope statement and stating the limitations on the project at the start
37
Advantages of scope creep:
Small changes could decrease time to market or reduce cost
38
Disadvantages of scope creep:
- Leads to delays or cost overruns | - Reduces team motivation
39
Baseline changes are
changes during the project life cycle that are inevitable
40
Examples of baseline changes are
changes in government policy, the economy, or unforeseen problems
41
Baseline changes should only be accepted if:
- the project will fail without the change - the project will improve significantly because of the change - the customer demands the change and will pay
42
It is important that information flow
is clearly mapped and stakeholders are informed
43
Engineers should value organisational strategy because:
- They must be able to make appropriate decisions and adjustments - They must be able to be a successful advocate for themselves
44
Strategy decribes
how an organisation intends to compete with the resources available in the existing a perceived future environment
45
There are four steps to the implementations of an organisation's strategy:
1. Review and define "mission", what the organisation intends to be 2. Create long-range goals and objectives; specific, tangible and measurable actions 3. Analyse and formulate strategies to reach these objectives 4. Implement strategies through projects
46
A portfolio management system involves
- the classification of projects - the criteria used to select them - ensuring a good range of sources of project proposals are used - the evaluation of those proposals
47
A portfolio management systems ensures
projects are aligned with strategic goals and prioritised suitably
48
Benefits of project portfolio management:
- Disciplined project selection process - Ensures projects are aligned with strategic targets - Projects prioritised on measurable, common criteria and not emotions and internal politics - Supports a move towards fulfilling organisation's strategy
49
Projects can be classified in three ways:
Compliance and emergency, operational, and strategic
50
Steps for determining whether to invest in a project:
1. Define the project 2. Define the stakeholders 3. Define the decision criteria 4. Calculate the economic benefits 5. Estimate the economic costs 6. Formulate the net benefit stream 7. Complete cost-benefit analysis 8. Complete sensitivity analysis 9. Assess other benefits not included in CBA 10. Report the findings
51
To complete cost-benefit analysis it is necessary to
convert into a common unit of measurement, most commonly money, this requires subjective judgements
52
If net present value > 0
Invest
53
If net present value < 0
Don't invest
54
Net present value=
Cost for period 0 + the sum for periods 1 to t of ((cost for period t/(1 + discount rate for period t)^t)
55
To adjust for risk in cost-benefit analysis
make the discount rate higher
56
Multiple criteria analysis is
a weighted scoring model that uses a range of weighted selection criteria to evaluate project proposals
57
Compared to cost-benefit analysis, multiple criteria analysis is
more subjection but allows for things beyond financial gain to be considered
58
Criticism of cost-benefit analysis:
- Due to data constraints, largely based on assumptions - Requires intuition - Needs adaptation to local surroundings
59
Types of costs and benefits not counted in net present value:
- Transfer payments - Sunk costs - Depreciation of assets
60
Payback period (years) =
estimate project cost/annual savings
61
Purpose of payback period:
Estimated time taken to recover investment more simply that NPV
62
Use of payback period:
- Quick evaluation | - Eliminates risky (long payback period) projects
63
Limitations of payback period:
- Ignores time value of money - Assumes cost inflows for investment period only - Does not consider profitability
64
A risk is
an uncertain event of condition that, if it occurs, has a positive or negative effect on the project objectives
65
As a project goes on, in terms of risk,
the probability of a risk occurring decreases, but the knowledge of risk variables and the cost to fix a risk increase
66
Risk identification can be done through
- brainstorming - interviewing experts - mapping risks onto work breakdown structure - using a risk profile related to project type
67
A black swan event is
an event that is rare, high impact, and predictable only in hindsight
68
Risk assessment can be done by use of
a FMEA or impact-likelihood matrix
69
FMEA stands for
failure mode and effect analysis
70
Common methods of risk mitigation are:
- Reduction - Avoidance - Transfer - Retention
71
Does subcontracting work mitigate the associated risks?
NO!
72
With regard to risk, it is good practice
to encourage everyone to speak freely, identify issues early and document who is responsible
73
Contingency can be done through:
- budget reserves - management reserves - time buffer
74
An activity is
an element of a project that requires time
75
A merge activity is
an activity with one(?) or more activities preceding it
76
Parallel activities are
activities that occur at the same time
77
A burst activity is
an activity with one(?) or more activities following it
78
Total float is
the difference between the latest and earliest finish time, the amount of time an activity can be delayed by and remain on schedule
79
Free float is
the difference between the earliest start time of a subsequent activity and the earliest finish time of an activity under consideration, the amount of time an activity can be delayed without delaying successor activites
80
Critical activities are
activities with zero total float
81
Estimation is
the process of approximating or forecasting the cost and time to complete the project deliverables
82
In estimation, there is the need to balance the trade-off between
better accuracy and the cost to secure this increased accuracy
83
Uses of estimation:
- Provides information to support good decision making - Required to schedule work and resources - Used to determine an estimate of total project cost and duration - Helps to determine whether it is financially worth doing - Helps to determine cash flow - Used as the basis for project control
84
Direct costs are
chargeable to a specific work package, represents real cash outflows, and must be paid as the project progresses
85
Indirect costs include
overhead costs, fees and taxation, inflation, mark-up and contingency funds
86
A top-down approach
takes a broad overview of the whole project and supplies a fast, less accurate estimate
87
A bottom-up approach
takes time to calculate with cost a time estimated for each activity of the work breakdown structure, and supplies a thorough, detailed and accurate estimation
88
Benefits of detailed estimating methods:
- High level of confidence compared to other approaches - More detail, used for monitoring and control - Enhanced scope and activity definition - Detailed quantities to establish more accurate metrics - Can be revised as the project progresses
89
Limitations of detailed estimating methods:
- Uses up time to calculate | - It costs more
90
Labour rates include
wages, national insurance, holiday pay, bonuses, overtime etc. (not just pay received by employee)
91
Parametric estimating consists of
creating logical and repeatable relationships between independent variables and dependent variables
92
Benefits of parametric estimation:
- Versatility | - Sensitiviy
93
Drawbacks of parametric estimation:
- Assumes linearity - Database requirements - Differing definitions of the unit of capacity - Relevancy of data
94
The formula for capacity factor method is
Cost(new)=Cost(known)x(Capacity(new)/Capacity(known))^(Capacity factor)
95
Factors that could have a significant impact on estimation quality include:
- The duration of the project and how far away it is - People estimating with inappropriate expertise - Project structure and organisation (concentrated focus or efficient sharing of personnel) - "Padding out" - Equipment downtime - National holidays/legal working limits
96
Reasons why costs may overrun:
- Low initial estimates due to to poor perception of the whole project - Tasks were considered in isolation so interactions were not fully considered - Unforeseen technical difficulties - Changes in scope and project definition - Economic and other external factors
97
A work breakdown structure attempts to show
what activities must be done, who will do each activity, how long each activity will take, what materials are required for each activity and how much each activity will cost
98
The consensus method of estimation involves
using pooled experience of senior managers to estimate total project costs and time
99
Benefits of consensus method:
- Can be used when historical data not available - Estimate is developed at minimal time and cost - Experts could provide new insight into project
100
Drawbacks of consensus method:
- Lack of objectivity - Risk of one expert dominating discussion - Not regarded as accurate
101
The learning curve method states
the time to perform an activity improves with repetition
102
The main benefit of Delphi method is
it completely removes egos, bandwagons and strong personalities
103
The Delphi method involves
well-informed individuals making estimates anonymously, and being encouraged to change their opinions in light of the opinions of other experts
104
Resource scheduling is
a means to allocate resources to activities to allow the project manager to make realistic judgements of resource availability and project durations
105
Benefits of resource scheduling:
- Realistic alternatives can be considered if resources cannot be met - It is possible to gauge impacts of unforeseen events - It is possible to assess trade-offs between cost and time - It is possible to assess flexibility in resources and reduce peak demand in the project and therefore reduce costs
106
Overall schedule slippage is
when a project is delayed because another project it shares resources with is delayed
107
Disadvantages of "first come first serve" rule in project scheduling:
- Resources are not fully optimised | - Benefit of working on multiple projects not felt
108
Advantage of "first come first serve" rule in project scheduling:
More reliable completion estimates
109
The project cost baseline is
the projection of what you plan to spend during the project life-cycle
110
What are the reasons to reduce project duration?
1. Strong global competition and rapid technological development 2. Unforeseen delays 3. Imposed deadlines
111
What are the reasons not to reduce project duration?
1. Higher direct costs 2. Health and safety 3. Planned obselesence
112
How to accelerate a time-constrained project:
1. Add resources 2. Outsource project work 3. Schedule overtime 4. Appoint a core project team 5. Do it twice (the first time at a lower quality)
113
Advantages of scheduling overtime:
-Avoids additional costs, time and communication of adding resources
114
Disadvantages of scheduling overtime
- There are regulations for maximum working hours - Reduced productivity - Increased resentment
115
Outsourcing is often not possible due to
confidentiality
116
How to accelerate a resource-constrained project:
1. Fast-tracking, adjust project logic 2. Critical chain project management 3. Reduce project scope 4. Compromise quality
117
Project management is
the planning, monitoring and control of all aspects of a project and the motivation of all those involved in it, in order to achieve the project objectives within agreed criteria criteria of time, cost and performance
118
British standard stages of a project life-cycle:
1. Concept 2. Feasibility 3. Evaluation 4. Authorisation 5. Implementation 6. Completion 7. Operation 8. Termination
119
Four general stages of a project life-cycle:
1. Defining 2. Planning 3. Implementing 4. Delivery
120
A project is
a unique set of co-ordinated activities, with definite starting and finishing points, undertaken by an individual or organisation to meet specific objectives within defined schedule, cost and performance parameters
121
The project scope should include
the objective, the deliverables, the milestones, the technical requirements, the limits and exclusions and the reviews with the customer
122
The three main things to be traded-off in projects are
cost, quality and time
123
Other than the three main things to be traded off, other project parameters include
safety, environmental factors and scope
124
Role of a work-breakdown structure:
- Shows interrelationship between work packages in hierarchical framework - Assures products and work elements identified - Ensures level of integration into organisation - Forms basis of project control
125
Project management has become increasingly important because
project life cycles have become shorter
126
Examples of when the objective of a project may not be to be profitable:
- capture larger market share - develop core technology to be used in next generation products - to prevent government intervention and regulation
127
In unit-rate estimating
the output rates and costs of materials used are combined, indirect cost must be considered seperately
128
The estimator determines costs for each item in the project, based on:
- information from recently completed contracts - built-up rates from analysis of historical data - published information - estimator's experience
129
In activity-based estimation
the total of the total quantities of resources involved in each activity
130
Examples of parametric estimating techniques:
1. End products unit method 2. Physical dimension method 3. Capacity factor method 4. Ratio and factor method
131
In the specific analogy method
the known cost of similar projects are used as a starting estimate and it is revised based on differences in design
132
Benefits of specific analogy method:
- can be used before detailed data is available - estimate is developed quickly at a low cost - straightforward to justify using historical data
133
Drawbacks of specific analogy method:
- only uses a single data point - detailed cost breakdown difficult to locate - may be too subjective in adjustment factors
134
Ladders
allow activities to be split into segments, so the following activity can start sooner without delaying the project
135
Overcoming resource problems from working on multiple projects:
- first come first served rule - treat all projects as a "mega-project" - outsourcing resource allocation issues
136
Resource bottlenecking is when
resources needed across multiple projects cannot be met, hence causing a delay across some of these projects
137
Potential impacts of resource smoothing:
- loss of flexibility and reduction is float of some activities - increased risk of overall project delay