Project Management Exam Flashcards

1
Q

Project Charter’s most important function

A

it authorizes project; shows the agreement by the key stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What’s in the Project Charter

A

project name, sponsor name, project manager name; simple, precise project statement; objective; scope; performance measure; major milestones; major deliverables; assumptions; constraints; business need met; signatures of authorized representatives to acknowledge approval of the project charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

when is the project charter created

A

in the defining/initiating stage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Checklist Purpose

A

method of assuring that all needed documents are written; only ensures that the actions on the list are addressed; one way of monitoring activities/tasks (do not monitor completeness); ambiguous/unnecessary items must be excluded

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Checklist issue

A

only as good as the completeness of the items listed and the team’s attention to the work being done; only ensures that items have been addressed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

statement of work

A

Provide more detailed descriptions of what must be planned; clarifies the actual work to be done

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Statement of work: what does it define

A

project’s outcomes in terms of objectives, specific deliverables, acceptance criteria, technical requirements, milestones, constraints, and assumptions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Work breakdown structure

A

developed from project scope and statement of work, details each activity that must be completed; helps identify specific skills, training, and experience needed on the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

product scope

A

is used to describe the portion of the scope statement that defines the features and functions of the project outcome or deliverables; the “what”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Purpose of WBS

A

organizing resources; assigning responsibility to resources; identifying the interaction and contingencies of tasks and how to assign them; control points/milestones; accurate estimating of time/cost for budget purposes; confirming expectations with the customer/sponsor; providing communications platform for the team and stakeholders; validates project scope understanding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Creating the WBS

A

will require the team to decompose the deliverables into activities and tasks that represent the work needed to produce the deliverables; anything that will require resources to complete the project should be accounted for

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The WBS is not

A

an exhaustive list of all tasks; a project plan, schedule, or chronological list; an organizational structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

risk appetite

A

the degree of uncertainty an entity is willing to take on in anticipation of a reward

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

risk tolerance

A

the degree, amount, or volume of risk that an organization or individual will withstand

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

risk threshold

A

measurements along the level of uncertainty or the level of impact at which a stakeholder may have a specific interest. Below threshold the org will accept; above the org will not tolerate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Risk Avoidance

A

during the planning, the team identifies the risk and sets a path to avoid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Risk mitigation

A

team acts to reduce the impact/likelihood of risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

risk transfer

A

shifts risk to a third party

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

risk acceptance

A

recognize the risk and accept as part of the project or normal business practice; often done with low impact

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

risk categories

A

organization, external, technical

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

PMBOK

A

risk breakdown structure; follows the wbs and insures that each activity and task in the WBS is reviewed for risk and opportunity documented as identifiec

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Top-down estimation

A

initial estimates of cost (rough costs) are necessary at the proposal phase of a project for the org to determine if the project should be approved for planning/execution; often provided by someone at the org who has knowledge or experience from prior similar projects; often documented by previous lessons learned

23
Q

Parametric estimation

A

top-down method; defining phase; ratio and reporting methods; based on the relationship between the current project and historical data

24
Q

ratio method

A

uses experience from prior projects to estimate the overall cost of the current project; can be adopted for other project types where the historic costs can be equated to the current project

25
apportion method
based on ratio method but takes into consideration functionality or types of work required; requires an overall project cost be provided
26
bottom-up estimation
require that estimates be made at the detailed work activity level of the WBS; generated by functional experts; developed during planning phase; requires people with expertise
27
cost management
process of measuring how close actual costs are to the budget and then making changes in project execution as needed
28
padding
extra time or extra money just in case; problem with bottom up estimation; provides an inaccurate estimate to the customer; encourages waste
29
contingency reserve
costs included in the budget to cover situations that may occur; included in the baseline budget
30
management reserve
amount added to the overall budget to cover unknown risk; can only be used with approval
31
PERT
estimate activity duration times
32
CPM
used for estimating project activity durations; assumes that the estimates do not vary
33
CCPM
assumes resources are limited
34
PRINCE2
focuses on specification of the outputs
35
Initiating
business need and what problem the project will solve; defines the project; evaluates proposals; project selection; identifies major stakeholders; project charter
36
planning
documents all customer requirements/deliverables; estimating resources; finalizing project scope; finalizing project budget; finalizing project schedule; creating WBS; creating the network diagram; creating the activity list; writing a plan for specific areas
37
executing
acquiring project team members; training/coaching team members; communicating with stakeholders; managing stakeholders; implementing the project plan; documenting change requests; assessing team member performance; recognizing and rewarding performance
38
monitoring and controlling
keeping the project activities in sync; verifying that the deliverables meet scope; documenting and CR; monitoring the schedule/budget; assessing project quality; resolving issues about scope/activities/interpersonal; reporting project performance; monitoring project risk; monitoring vendor/provider performance; determining when planning is needed
39
closing
paying outstanding vendor invoices; reconciling vendor accounts; returning excess materials/supplies/assets; writing lessons learned; project documentation; delivering completed project to customer; receiving sign-off from customer; archiving all project documents
40
project sponsor
person in the project org who has authority to expend resources for projects; signs the project charter
41
time value of money
money is worth more today than in the future
42
payback period
the amount of time required to earn back the cost of doing the project
43
internal rate of return
recognizes the time value of money using the duration of the investment return and the return rate
44
net present value
total future benefits of a project minus the costs of the project
45
functional/departmentalized org
oldest/most basic form; lines of authority are clearly defined; SMEs are available to work on multiple projects
46
Matrix
less clearly defined lines of reporting; the SME reports to the PM; the functional supervisor retains admin auth/responsibility for the SME; PMs have access to a large reservoir of tech skilled people/SME; issues balancing resources; SMEs are not in daily contact with other SMEs; customer issues are met with quick response; admin personnel are not duplicated in each team; more flexible
47
Projectized
PM has full authority; timely decision making/responses to stakeholders are faster/clearer; must have enough work for smes
48
PMO
aligns project investment to corporate stategy; monitors status/availability of resources; reduces overhead; central repository for project policies, procedures, historical records, lessons learned; consistent policies/procedures
49
one point estimation
provides a single estimate for an activity based on their own knowledge or historical info
50
triangular distribution
duration = O+M+P/3 | probabilistic: provides best case and worst case
51
beta distribution
duration = O+4M+P/6 | places emphasis on the most likely estimate; probabilistic
52
standard deivation
p-o/6
53
deterministic estimate
predictable
54
probabilistic
uncertain