Project Management Plan Flashcards
(6 cards)
1
Q
Project Management Plan Components
& what process they are developed in
A
16 Project Management Plan Components:
- Scope Baseline – Create WBS process
- Schedule Baseline – Develop Schedule process
- Cost Baseline –Determine Budget process
- Scope Management Plan –Plan Scope Management process
- Requirements Management Plan —Plan Scope Management process
- Schedule Management Plan –Plan Schedule Management process
- Cost Management Plan – Cost Management process
- Quality Management Plan –Plan Quality Management process
- Resource Mgmt Plan –Plan Resource Management process
- Communication Management Plan –Plan Communications Management process
- Risk Management Plan –Plan Risk Management process
- Procurement Management Plan –Plan Procurement Management process
- Stakeholder Engagement Plan –Plan Stakeholder Engagement process
- Change Management Plan –Develop Project Management Plan process
- Configuration Management Plan –Develop Project Management Plan process
2
Q
What Baseline Plans are in the Project Management Plan?
A
Performance Measurement baseline consists of
- Scope Baseline
- - Create WBS process - Schedule Baseline
- - Develop Schedule process - Cost Baseline
- -Determine Budget process
3
Q
What sub plans are developed in the Plan Scope Management process
A
- Scope Management Plan
- -Plan Scope Management process - Requirements Management Plan
- -Plan Scope Management process
4
Q
What quality plan are included in the Project Management Plan?
A
- Quality Management Plan
- -Plan Quality Management process
5
Q
What 2 sub plans are created in the Develop Project Management Plan process?
A
- Change Management Plan
- -Develop Project Management Plan process - Configuration Management Plan
- -Develop Project Management Plan process
6
Q
Project documents include
A
statement of work project charter network diagram issues log assumption log risk register stakeholder register WBS WBS dictionary contracts requirements change control register activity list quality metrics lessons learned