Project Management Plan Flashcards

(6 cards)

1
Q

Project Management Plan Components

& what process they are developed in

A

16 Project Management Plan Components:

  1. Scope Baseline – Create WBS process
  2. Schedule Baseline – Develop Schedule process
  3. Cost Baseline –Determine Budget process
  4. Scope Management Plan –Plan Scope Management process
  5. Requirements Management Plan —Plan Scope Management process
  6. Schedule Management Plan –Plan Schedule Management process
  7. Cost Management Plan – Cost Management process
  8. Quality Management Plan –Plan Quality Management process
  9. Resource Mgmt Plan –Plan Resource Management process
  10. Communication Management Plan –Plan Communications Management process
  11. Risk Management Plan –Plan Risk Management process
  12. Procurement Management Plan –Plan Procurement Management process
  13. Stakeholder Engagement Plan –Plan Stakeholder Engagement process
  14. Change Management Plan –Develop Project Management Plan process
  15. Configuration Management Plan –Develop Project Management Plan process
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What Baseline Plans are in the Project Management Plan?

A

Performance Measurement baseline consists of

  1. Scope Baseline
    - - Create WBS process
  2. Schedule Baseline
    - - Develop Schedule process
  3. Cost Baseline
    - -Determine Budget process
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What sub plans are developed in the Plan Scope Management process

A
  1. Scope Management Plan
    - -Plan Scope Management process
  2. Requirements Management Plan
    - -Plan Scope Management process
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What quality plan are included in the Project Management Plan?

A
  1. Quality Management Plan

- -Plan Quality Management process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What 2 sub plans are created in the Develop Project Management Plan process?

A
  1. Change Management Plan
    - -Develop Project Management Plan process
  2. Configuration Management Plan
    - -Develop Project Management Plan process
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Project documents include

A
statement of work
project charter
network diagram
issues log
assumption log
risk register
stakeholder register
WBS
WBS dictionary
contracts
requirements
change control register
activity list
quality metrics
lessons learned
How well did you know this?
1
Not at all
2
3
4
5
Perfectly