Project+ PK0-003 Study Material Flashcards
(27 cards)
There is a minor conflict between several members on a project team; the issue has no significant impact on the project. Which of the following would be the BEST conflict resolution technique for the project manager to employ?
Avoiding
A customer has requested an increase in the scope of a current project, but the project schedule remains the same. Which of the following is MOST likely impacted? (Select TWO).
Project quality & Project cost
Which of the following would be used to allow a project team to take action to fix problems that are causing the GREATEST number of defects?
Pareto diagram
Which of the following risk response strategies involves the use of insurance, performance bonds, or warranties?
Risk transfer
During which of the following process groups is the availability of required resources for the project determined?
Planning
Given the circumstances below, which of the following would be the BEST action for the project manager to take?
One of the key stakeholders disagrees with the project.
Two of the key staff members refuse to work with each other. The budget for the project has been reduced.
The scope of the project has changed.
The project manager should work with the stakeholders to resolve the areas of disagreement.
A product does not meet the customer’s quality specifications. Which of the following can the project manager use to bring the product quality into alignment with the specifications? (Select TWO).
Trend analysis & Pareto chart
A key stakeholder has informed the project manager that the project must be completed on time. The project is currently running behind schedule. The budget provided for the project will not allow for additional resources. In order to meet the demands of the key stakeholder, which of the following is the BEST action for the project manager to take?
Fast track the schedule.
The key stakeholder requires the project manager to advance the completion date before funding runs out. The project manager has had problems with this stakeholder in the past and wants to document this request. Which of the following should the project manager do? (Select TWO).
Complete a project change request form.
Analyze the project impact.
During a project status meeting a positive project risk is identified and is within the team’s control. Which of the following would be the BEST response?
Exploit the risk
The project manager has the MOST authority in which of the following organizational structures?
Strong Matrix
A project sponsor has just signed a document that authorizes the project manager for an upcoming project. Which of the following elements would be included in this document?
The purpose of the project
A project has just entered the execution phase. The deadline to respond to the RFP has expired. Which of the following activities describes the NEXT action to take?
Evaluate and select a seller response
A project manager has just completed the work breakdown structure (WBS) with the project team. Which of the following would be used during activity sequencing?
Precedence diagramming method
Fast tracking a schedule involves which of the following?
Performing critical path activities simultaneously
Crashing a schedule involves which of the following?
Adding resources to critical path activities
A project with a total budget of $100,000 is in the ninth month and has an earned value of $80,000 and actual costs of $90,000. The project’s cost variance is:
-$10,000
During which of the following process groups is the project charter developed?
Pre-project setup
Which of the following describes a work breakdown structure (WBS)?
Is deliverable-oriented and hierarchical in nature
During the execution phase, a customer approaches the project manager demanding a change. Which of the following are the steps the project manager should take? (Select TWO).
Fill out a change request form.
Evaluate the impact of the change.
A project team member has been re-assigned to another project. Which of the following should the project manager do FIRST?
Assess the impact on the project schedule.
During execution of the project, the project sponsor informs the project manager that a requirement needs to be added to the scope statement. Which of the following is
the FIRST action that the project manager should take?
Evaluate the impact of the change on the project.
Which of the following are reasons why formal project closure is important? (Select THREE).
Releases staff from the project, Provides historical information, Confirms completed/non-completed objectives
Which of the following is the correct order of the project life cycle?
Initiating, planning, executing, monitoring / controlling, closing