Project Management Flashcards

(4 cards)

1
Q

What is Critical Path Analysis (CPA)?

A

Finding the longest dependent task sequence that sets the project’s minimum duration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the steps in CPA?
LEIDD

A
  1. List tasks
  2. Estimate durations
  3. Identify dependencies
  4. Draw network diagram
  5. Determine critical path
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is MoSCoW?

A

A prioritisation technique used in project management.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is PERT (Program Evaluation Review Technique)?

A

A project management tool that helps visualise and manage complex projects, particularly those with uncertain durations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly