Project Schedule Management Flashcards

1
Q

Smaller projects and schedule management

A
  • Can make defining activities, sequencing activities, estimating activity durations and developing the schedule model one single process
  • This is difficult to do with larger projects
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Iterative Scheduling with a backlog

A
  • Found in adaptive or hybrid environments

- Rolling wave planning of plans and executing over and over again

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Lean Manufacturing

A
  • Backlog of assignments
  • As team members become available the assignments go to the next available person
  • Not as much planning on who does what
  • Everyone must be capable of performing all of the tasks
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Scrum Master

A

Analogous to PM in Adaptive Environment

Acting as a Servant Leader to the team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Theory of Contraints

A
  • Identifying the most limiting factor (ex. time, resources, etc.)
  • Improve that constraint until its no longer the limiting factor
  • Scientific approach to improvement
  • Lean manufacturing
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Schedule Management Plan

A
  • First step in Schedule Management

- Defined how the schedule will be developed, managed, executed and controlled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

ITTOs: Planning Schedule Management

A
  • Inputs:
  • Project Charter
  • Project Management Plan
  • EEFs
  • OPAs

T&T:

  • Expert judgement
  • Data Analysis
  • Meetings

Outputs
- Schedule management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is in the schedule management plan?

A
  • Project schedule model development
  • Level of accuracy
  • Units of measure
  • Organizational procedure links (links to procurement, links to resources)
  • Project schedule model maintenance
  • Control thresholds
  • Rules for performance measurements
  • Reporting formats (# of activities on time, or # of activities complete, etc.)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Define Activities

A
  • Activities associated with work packages (taken from the WBS)
  • Basis for estimating scheduling and controlling work
  • Activity attributes
  • Milestone list shows all of the activities leading up to a given milestone
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

ITTOs: Define Activities

A

Inputs:

  • Project Management Plan
  • EEFs
  • OPAs

T&T:

  • Expert judgement
  • Decomposition
  • Rolling wave planning
  • Meetings

Outputs:

  • Activity list
  • Activity attributes
  • Milestone list
  • Change requests
  • PMP updates (schedule and/or cost baseline)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

8/80 rule

A
  • Rule not to breaking down the WBS too far
  • Between 8 hours and 80 hours is how long a work package should take. Anything below 8 hours is too granular. Anything greater than 80 hours is too big
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Control Accounts

A
  • Marker in the WBS

-

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Planning Packages

A
  • Decisions to be completed for a given Control Account
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Rolling Wave Planning

A
  • Imminent work is planned in detail
  • Distant work is planned at a high level
  • As work approaches, the work is planned in more detail
  • Focus on most important
  • Example of progressive elaboration
  • Possible to do this with phase gate
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Activity List

A
  • Separate document
  • Lists all project activities
  • Scope of work for each activity and an identifier
  • Links back to WBS identifier
  • Establishes relationships between activities (dependencies)
  • Reosourcing requirements
  • Imposed dates
  • Constraints and assumptions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Lead

A
  • negative time

- when we are allowing time to overlap for multiple activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Lag time

A
  • positive time

- waiting longer for one tag before completing another

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

LOE

A
  • Level of effort
  • Reporting/Budgeting
  • Don’t contribute to project scope but are needed to manage the work
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Discrete effort activities

A
  • Required to complete the project scope

- Most activities are discrete effort activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Apportioned effort

A
  • Project Management work
  • QA
  • Integrated Change Control
  • Communications
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Milestones

A
  • marker that show progress
  • noting significant events or delivery items
  • no duration or resources
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Milestone Chart

A

Up Triangle = Planned
Down Triangle = Actual

Shows variance

23
Q

Sequencing Project Activities

A
  • Computer driven, manual or blended approach
24
Q

ITTOs: Sequencing Project Activities

A

Inputs:

  • PMP
  • Project documents
  • EEF
  • OPA

T&T:

  • Precedence diagramming method
  • Dependence determination and integration
  • Leads and Lags
  • PMIS

Outputs:

  • Project schedule network diagrams
  • Project doc updates
25
Dependency determination
- mandatory dependencies - hard logic (not optional) - discretionary dependencies - soft logic (can happen whenever) - external dependencies - external constraint (waiting on someone else or another project deliverable) - internal dependencies - type of hard logic ( project team member taking a vacation)
26
Precedence Diagramming Method
- most common (Microsoft Project) - Activities in boxes or circles, called nodes - Number represent durations - Can go through and identify the paths to completion and the relative durations for each path - Identifies the critical path, early start and early finish - Arrows represent the relationship and the dependencies of the work packages - Creates the Network Diagram - Critical path should not have any float. Whole project must be done in the time from the critical path
27
Float
The amount of time a task can be delayed without impacting subsequent tasks and overall project completion
28
Law of Diminishing Returns
- Increase in resources will eventually yield diminishing returns - Some things take a set amount of time no matter how many resources you throw at the problem
29
Parkinson's Law/Student Syndrome
- Work will expand to fill the time a lotted to it
30
Range of variance
- range of +/- days or weeks | - percentage of acceptable target date
31
Basis of estimates
- Assumptions made - Known constraints - Range of possible estimates - Confidence level and risks that could impact the duration
32
Analogous estimating
- Takes similar project work to create a basis for the duration - Aka Top-Down Estimating - Fast/least expensive but also the least reliable - Requires expert judgement and historical/reliable information
33
Parametric Estimate
- Parameter for estimating | - Ex. Algorithm to calculate duration (time per unit),
34
Duration vs. Effort
- Duration is how long something will take - Effort is the billable time for labor - Ex. if you have two people who can do the same task but one is a more senior engineer and bills more, the duration is the same but the effort will be different
35
Three-Point Estimate
- Find an average of Optimistic, Most Likely and Pessimistic | - (O + ML+P)/3 = Estimate
36
PERT Estimates
- Program Evaluation and Review Technique - Beta distribution - Weighted towards the most likely - (O+ (4ML)+P)/6 = Estimate
37
Bottom-up Estimating (Resources)
- Requires a fully-decomposed WBS for each work package - Estimate how many and what type of resources you'll need to create that work package - Takes longer than other approaches, but is the most accurate
38
Contingency Reserve
- Usually associated with money | - Risk events that disrupt the project
39
Management Reserve
- Typically associated with time or money - Activities take longer than expected which interferes with the given pool of time and money because you have only budgeted for a certain amount of time
40
Reserve Analysis
- Amount of buffer in the project durations | - Goes down over time as tasks are delayed
41
Free Float
- An activity can be delayed without delaying the early float of any successor activities - Late finish - Early Finish = Late Start - Early Start = Float
42
Total Float
- An activity can be delayed without delaying project completion
43
Project Float
- A project can be delayed without passing the customer expected completion date
44
Critical Path
Longest path in terms of duration | Has no float since you can't delay any of the activities otherwise the project will be late
45
Forward Pass
Early Start + Duration - 1 = Early Finish
46
Backward Pass
Late Finish - Duration +1 = Late Start
47
Crashing a project
- Add people to get something done faster - increases costs - Subject to the law of diminishing returns (Only so many people are helpful) - Useful for projects that are effort driven
48
Fast tracking
- Multiple phases overlapping | - Increases risk since an error found in an earlier phase can impact another phase since they overlap
49
Heuristic
- Limits labor in a time period | - Extends the schedule
50
Resource Smoothing
- Limits labor except for the critical path (allow overtime) | _ Try to adhere to the deadline
51
Agile Release Planning
- High-level summary timeline of the release schedule - 3 to 6 months - Product roadmap and product vision - Determines the number of iterations or sprints - How much needs to be developed
52
ITTOs: Control Schedule
Inputs: - Project Management Plan - Project Documents - WPA - OPA T&T: - Data Analysis - Critical Path method - PMIS - Resource optimization - Leads and Lags - Schedule Compression Ouputs: - WPI - Schedule forecasts - Change Requests - PMP. updates - Project doc updates
53
Story Points
- Rating of requirements given to determine how many requirements can be completed in a sprint
54
Soft Logic
Allows the PM to make decisions based on conditions outside of the project, best practices or guidelines