Quantitifcation & Costing Of Construction Works Flashcards
(46 cards)
Why were the New Rules of Measurement introduced?
- The previous Standard Method of Measurement (SMM7) was purely designed for the production of bill of quantities for tender purposes.
- This resulted in a lack of guidance and uniformity around preparing cost estimates and cost plans when using SMM7.
- The NRM was introduced to provide a common and consistent basis for the production of order of cost estimates and cost plans and to give Employers more confidence around their inclusions.
What is the structure of the NRM 1?
The key sections of NRM1 are:
o Part1: General introduction explaining the document’s purpose and how it should be used.
o Part2: Measurement rules for the production of order of cost estimates.
o Part3: Measurement rules for the production of elemental cost plans.
o Part4: Tabulated rules of measurement for elemental cost planning.
o Appendices: With references to the definitions for GIA, functional units, NIA, elemental breakdowns, templates and general information required for cost plan production.
Why should you use the New Rules of Measurement?
- The NRM provides a common and consistent basis for the production of order of cost estimates and cost plans.
- This provides added confidence to Employers.
- In the event that a QS or firm is pursued for negligence, the use of NRM would provide a means of defence as it represents best practice.
- QS’s are not required to follow the NRM if they judge it as unsuitable for their specific project but they must have a good reason as to why this approach has been taken.
What is the NRM 1?
- The RICS New Rules of Measurement 1 is the Order of Cost Estimating and Elemental Cost Planning.
- This provides a structured basis for measuring building works and for the production of Cost Estimates and Cost Plans.
What is meant by the abbreviation GEA?
- Gross External Area.
- This is the area of the building measured externally at each floor level.
What is meant by the abbreviation GIA?
- Gross Internal Area.
- This is the area of the building measured to the internal face of the perimeter wall at each floor level.
- The GIA excludes external open sided balconies, fire escapes, canopies, external walls and fuel stores.
What is meant by the abbreviation NIA?
- Net Internal Area.
- This is the area of usable space measured to the internal face of the perimeter wall at each floor level.
- The NIA excludes internal structural walls and columns, spaces with headroom less than 1.5m, permanent lift lobbies, toilets, cleaners’ cupboards and plant rooms.
Where are all of these abbreviations defined?
The Code of Measuring Practice published by the RICS.
What is the purpose of the Code of Measuring Practice?
The Code of Measuring Practice provides precise definitions to permit the accurate and consistent measurement of buildings.
What would you expect the percentage of NIA to GIA to be?
- The percentage would depends on the type of project being undertaken for example whether this was a school, hospital or office.
- In the case of an office building, I would expect the NIA to GIA percentage to be in the region of 70- 85%.
- Where 70% is considered as relatively inefficient, a percentage of 85% is extremely efficient.
What do you measure in accordance with?
- The method of measurement to be adopted depends on the region, project and client that I am working with, for example in the United Kingdom in the Building sector, typically the New Rules of Measurement would apply.
- However if working on Rail or Civils projects it is more common practice for the Civil Engineering Standard Method of Measurement to be adopted.
How do you measure structural steelwork under NRM 2?
- Lengths
- Weights
- Type
What ‘other items’ would you also need to measure for structural steelwork under NRM 2?
- Other items to measure in association with steelwork include framing erection, permanent formwork, cold rolled purlins and cladding rails, isolated structural member, filing hollow sections, surface preparation, surface treatment and localised protective coatings.
Structural Steelwork under NRM 2 - Measurement details: Length?
Lengths not exceeding 1.00m.
Lengths over 1.00m but not exceeding 9.00m. Lengths exceeding 9.00m.
Structural Steelwork under NRM 2 - Measurement details: Weights?
Weight not exceeding 25kg/m.
Weight between 25-50kg/m.
Weight between 50-100kg/m.
Structural Steelwork under NRM 2 - Measurement details: Type?
Columns.
Beams.
Rafters.
Bracing.
Purlins and cladding rails.
How do you measure brickwork walls under NRM?
- The measurement rules for Masonry are contained within section 14.
- Masonry walls are to be measured in m2 with them being itemised according to wall thickness, type of construction and method of formation
What ‘other items’ would you measure in association with a brickwork wall under NRM?
o Chimneystacks.
o Arches.
o Brick reinforcement.
o Forming cavities.
o Closing cavities.
What is the purpose of a BoQ?
- The purpose of the BoQ is to provide the estimator with an accurate picture of the scope of works and to provide a common and consistent basis for pricing.
- Following receipt of Tender submissions, the BoQ also forms the basis of the Tender Analysis allowing an accurate like for like comparison to be undertaken.
- Throughout the post contract stages it also provides the basis for the valuation rules of the contract for valuing variation items.
- It also enables the contract works to be assessed and valued for the purposes of interim payment.
How would you prepare a BoQ?
- I would meet with the design team to establish when the necessary information will be available, it is important to ensure the information provided is full and final to avoid abortive works.
- Following this I would look to compile all information necessary from the Design Team including:-
o Drawings.
o Specifications.
o Schedules.
o DocumentRegisters. - Following receipt of the information I would check to see if the information is sufficient to allow the BoQ to be complied. This largely depends on the form of contract for example under remeasurement forms the information does not have to be complete but must be substantially complete.
- I would discuss and agree with the client and design the method of measurement to be adopted.
- Prior to commencement of measurement and taking off quantities, I would consider the size of the Project and break the works down into sections and areas for example:-
o Substructure.
o Superstructure.
o ExternalWorks. - I would then commence Take-off & work from the Substructure upwards.
- When measuring is complete I would look to address the general items section & any preambles.
- Following BoQ production I would carry out regular meetings and review any updated drawings to ensure that no works items had been missed or overlooked between packages.
How would you structure a BoQ?
In accordance with an elemental breakdown structure under NRM 2, I would include the following sections:-
o Preliminaries(MainContract).
o FacilitatingWorks.
o Substructure.
o Superstructure.
o InternalFinishes.
o Fittings, Furnishings and Equipment.
o Services.
o ExternalWorks.
o ProvisionalSums.
o Dayworks.
How would you describe the preliminaries section in a Bill of Quantities?
- The preliminaries detail items of work that are required to enable the construction but are not associated within the permanent measured works items.
- This could include items such as:-
o Site setup.
o Management&supervision.
o Insurances for the project.
o TaskLighting.
o Protections and temporary barriers.
What information is required to measure preliminaries?
- Contract duration.
- Location.
- Type of project (New Build vs. Refurb).
- The size of the project.
- Temporary works.
- Security.
- Methodology.
- Programme.
- Services.
- Employers accommodation.
- Contractor designed work.
- Sectional completion.
- Insurances / Bonds.
If it was found that a Bill rate was blatantly wrong for example £100 was included as a rate instead of £1, how would this be resolved?
- The works would be valued per the agreed rate in the contract.
- If identified within the tender documents prior to the contract being agreed then the rate could be amended in accordance with the Tendering rules in place, but otherwise both parties would have to stand by the rate.