Refrigerant 2 Flashcards
(141 cards)
- What is the minimum allowable refrigerant velocity in a reduced discharge riser?
1000-1500 fpm
What is the function of the “p” trap in vapour risers
Assists oil movement
What is the correct method to transfer HFC 404A for a refrigeration system?
. Removed as a liquid from cylinder and flashed into the system using a refrigeration manifold
When is a crankcase pressure regulator set up?
After defrost cycle has terminated and compressor has started
What pressure shall be used to calculate the superheat setting of the evaporator when a TXV is used as the metering device?
b. Evaporator outlet pressure near the sensing bulb
Defrost may be initiated by:
Time, temperature or pressure
Defrost may be terminated by:
Time, temperature or pressure
Calculate the total “u” factor of a freezer wall constructed of the following: 6” of polyurethane; having an “R” value of 6.25 per inch
8” concrete; having a “C” factor of 0.58 Btu/(hr)(ft2)(°F)
5/8” fire rated gypsum board; having a “u” factor of 3.2 Btu/(hr)(ft2)(°F).
.0253 Btu/(hr)(ft2)(°F).
What heat load value is unique when cooling fresh fruit and vegetables?
Heat of respiration
- The oil pump in a large semi hermetic compressor is located where?
on the crankshaft end
What type of TEV bulb charge is required on a large tonnage AC rooftop unit to reduce compressor overloading at startup under high load conditions?
Vapour charged
Off Cycle Defrost for a single circuit system, involves:
condensing unit off and evaporator fan on
Electric Defrost for a single circuit system, involves:
condensing unit off and evaporator fan off
Hot Gas Defrost for a multi circuit system, involves:
condensing unit on and evaporator fan off
Where is the Evaporator Pressure Regulator located
Outlet of the higher temperature evaporator
What type of oil used in stationary refrigeration and air conditioning systems will more readily absorb moisture when the container is opened?
Polyolester oil
walls of a building are 20’ high and 200’ long. The drywall has an R value of 0.5, the insulation is R10, the outside polystyrene board is R4 and the outside finish is R0.5. The indoor temperature is 72ºF and the outdoor design temp is -5ºF. Calculate the heat loss through the wall.
20,533 Btu/hr
a receiver is located in a location that may become colder than the evaporator
Thermostatically controlled heater elements are attached to the surface area of the receiver shell and shell is insulated
What is the effect on a system when the liquid line solenoid valve is installed backwards?
System won’t pump down
Where should the liquid line solenoid valve be installed?
. In the liquid line after the liquid line filter drier
What is the result when the TXV loses the charge in the sensing
Increase in evaporator superheat
Where should the TXV bulb be located for best sensing results?
. Evaporator outlet and placed to avoid effects of oil temperature
What is the correct mounting procedure of the thermostatic element bulb to ensure proper control of the TEV?
Clean evaporator outlet tubing after suction header, secure with similar metal clamp and insulate
- What is the purpose of the fan delay after a defrost cycle?
Allow moisture to drip off and the remainder to solidify on the coil