Review Flashcards

(64 cards)

1
Q

In _____, materials are already existing. The type of test has already been specified. The objective of this is to determine if these materials comply with the given technical specifications and will fall within the required parameters.

A

commercial testing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

In _____, materials are tested to obtain their vital and beneficial properties and determine how it can be advantageous in building a certain structure.

A

scientific testing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

In _____, researches are being conducted for existing equipment to have better understanding of its usage. For new materials, properties are being analyzed. Also, quality standards and procedures are being developed.

A

materials research

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

this is when the result is uncertain that new insight are to be gained

A

experimental

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

this is more defined procedure which are the limits and results are clear

A

testing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

materials are being tested up to its breaking point or until the material fails. It is said that this testing procedure is much easier to conduct because it results to more information regarding the material properties.

A

destructive testing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

this is the exact opposite of destructive testing. It is commonly used when the materials to be tested are still in service.

A

non-destructive testing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

tells how close the measurements are to each other.

A

precision

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

tells how close the measurement is to its true value.

A

accuracy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

is a precise statement of a set of requirements, to be satisfied by a material, product, system or service. It is desirable that the requirements, together with their limits, should be expressed numerically in appropriate units.

A

specification

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

is the result of agreement between those concerned in a particular field and involves acceptance for use by participating agencies.

A

standard specification

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

TSE

A

Turkish Standards Institute

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

ASTM

A

American Society for Testing and Materials

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

ISO

A

International Standards Organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

CEN

A

European Committee for Standardization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

This equipment facilitates the counting of voids in concrete.

A

Linear Traverse Machine

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

This equipment is used to test the behavior of a concrete sample while compressive loads are being applied on it. Some of the results obtained are its compressive strength, yield strength, ultimate strength, elastic limit, etc.

A

compression machine

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

This equipment is used to measure the consistency of the concrete before it sets. The workability of the concrete can also be determined through this test. An improperly mixed batch can be known with this procedure.

A

slump test equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

This equipment is used to analyze the particles of sample aggregates as it is sifted according to its sizes.

A

Sieve Shaker

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

This equipment determines the water content at which soil changes from a liquid to a plastic state.

A

Liquid Limit Testing Equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

This equipment determines the water content at which soil changes from a plastic to a semi-solid state.

A

Plastic Limit Testing Equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

This equipment is used to indicate how much moisture will be lost before the sample undergoes significant volume change.

A

Shrinkage Limit Testing Equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

It involves the erection of a building on a piece of property.

A

Building Construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

It means for a larger infrastructure projects. This is usually financed by government agencies, other institutions, or incorporated into master plans to serve the public good.

A

Heavy or Infrastructure Construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
It refers to the building of large scale manufacturing, processing and chemical plants or utility generation installations.
Industrial Construction
26
Once all the basic decisions have been approved by the owner, the architect and all consultants will commence with the final phase the _____
construction document
27
shows the dimensional relationships between all aspects of the building: their form, sizes, and quantities.
Construction Drawings / Working Drawings
28
Indicate the physical relationship between components – their location, range, the materials used, and their colors and texture.
Construction Drawings / Working Drawings
29
the basis on which the contractor generates cost estimates and are used to guide the actual construction of the building on the site.
Construction Drawings / Working Drawings
30
The construction documents include a written manual called _____.
Specification
31
describe in writing more detailed information on the exact types of materials to be used and the ways in which construction processes are conducted.
Specification
32
It provides a standard for writing specifications using a system of descriptive titles and numbers to organize construction activities, products, and requirements into a standard order.
Master Format
33
Governs the condition under which construction project will be completed and defines the relationship between the owner, architect, or firm and contractor
PROJECT DELIVERY PROCESS
34
Assume the responsibility for the construction of an entire project at a specific cost and by specific date.
GENERAL CONTRACTORS
35
Responsible for the developing project schedules and sequencing and coordinating the work of all subcontractors
GENERAL CONTRACTORS
36
Determines the actual methods and techniques of construction as well as implementing safety precautions on the building site
GENERAL CONTRACTORS
37
Signs contract with subcontractors
GENERAL CONTRACTORS
38
General contractor’s on-site representative responsible for continuous field supervision, coordination, and completion of work
SUPERINTENDENT
39
Makes sure that the work proceeds according to the project schedule and that the activities of the various subcontractors working on the site will not interfere with one another
SUPERINTENDENT
40
Who perform the required work within their technical areas, such as all the electrical, plumbing, roofing, bricklaying, carpentry or concrete
SUBCONTRACTORS
41
Work independently on site, bringing their own employees, supervisors, and tools for the job
SUBCONTRACTORS
42
Do the work required in a limited area, like elevator or communication equipment installation for instance
SPECIALTY CONSTRACTORS
43
bidding for publicly financed projects construction contractors; qualified construction contractors
COMPETITIVE BIDDING
44
bidding for privately funded projects; preselected contractors
INVITATIONAL BIDDING
45
An owner may decide on a contractor with whom they have worked on previous projects without seeking other bids
NEGOTIATED CONTRACT
46
determines how a construction project will be completed, delegates the responsibilities, rewards, and risk between participants, and regulates the relationship between the owner and the contractor.
project delivery method
47
The owner may hire a construction manager to provide input during the design phase and oversight and administration of bidding and construction phase.
Construction Management
48
It is the traditional method of project delivery that moves sequentially from conception of a project through its construction. Generally it has the lowest construction cost.
DESIGN-BID-BUILD
49
In this contracting method, the owner contracts with a single party that completes all portions of the work from design through construction. This contract tends to produce shorter overall project schedules.
DESIGN-BUILD
50
an individual who is hired by a contractor to provide the contractor with goods or services necessary to complete the tasks specified in an existing agreement.
subcontractor
51
is one of the most used scheduling techniques in the construction industry due to its simplicity and powerful resource that it can be
Critical Path Method
52
a certificate issued by the local authority having jurisdiction authorizing the construction of a project after a thorough review of construction documents to ensure compliance with local building, safety, and fire codes.
Building Permit
53
Gives precise directives for the fabrication of certain components, such as structural steel work, concrete reinforcing or pre-cast concrete components.
SHOP DRAWINGS
54
These are drawings, schedules, performance data, and brochures that give manufacturer’s information on the characteristics of a material and allow the architect to verify that the product under consideration will satisfy the requirements listed in the specification.
Submittals
55
Is a full-size model of a proposed construction system built to judge the appearance of an assembly, examine its construction details, and test for performance under actual size conditions.
Construction mock-up
56
An onsite visit by the design architect or engineer to determine if the construction materials and installations are in accordance with the documents and specifications, which includes review of testing reports.
Construction Observation
57
used by the contractor to obtain clarification on specific components and assemblies that are not fully detailed or understood through comprehensive review of the drawings and specifications.
request for information (RFI)
58
It is a written order prepared by the architect and signed by the owner directing a change in the work and stating a proposed basis for adjustments in the contract time, cost or both.
Construction Change Directive (CCD)
59
It is a written directive to the contractor issued after the execution of an argument that authorizes an addition, deletion, revision to the project along with the related adjustments in contract budget and time.
Change Order
60
finalizes all project activities completed across all phases of the project to formally close the project
Project Closeout
61
When the contractor determines that the work is nearing completion, the architect or construction manager is asked to return to the site and conduct an inspection of substantial completion.
Consultation
62
Listing the remaining items to be installed or repaired and to collate and submit all product and equipment warranties.
Assessment
63
Before a final certificate of completion can be issued, the inspecting authority must substantiate that all work is installed and complete, and the quality of workmanship meets the specified standards.
Inspection
64
The contractor will apply to the local jurisdiction for a certificate of occupancy. The certificate issued by the local building department indicating that the building is compliant with locally adopted building codes and is in proper condition to be occupied.
Consultation