Review Flashcards
(155 cards)
planning technique to subdivide the project scope and deliverables into smaller, more manageable components. What is this technique called?
Decomposition
The three types of estimates on which three-point estimates are based are:
Most likely, optimistic, and pessimistic
Project calendar definition
A project calendar is a calendar of working days or shifts that establishes those dates on which schedule activities are worked. It also establishes non-working days that determine dates on which schedule activities are idle, such as holidays, weekends and non-shift hours.
For control and management communication, the broader and more comprehensive summary activity that is used between milestones is referred to as:
Hammock activity
a technique that computes or iterates the project cost or the project schedule many times, using input values selected at random from probability distributions of possible costs or durations. In this way, one can calculate a distribution of possible total project costs or completion dates.
Monte Carlo Analysis
The critical path method (CPM) calculates the theoretical early start and finish dates and late start and finish dates. The difference between the late and early start of a task is called:
Total float
A control chart is used to determine whether a process is stable or has predictable performance. When a process is within acceptable limits, the process need not be adjusted. At what values are the upper and lower control limits usually set?
+ / - 3 Sigma
The three categories into which contracts can be broadly classified are:
Broadly speaking, contracts can be classified as: 1. Fixed-price (Firm-fixed-price, Fixed-price incentive), 2. Cost-reimbursable (Cost-plus-fixed-fee, Cost-plus-incentive fee, Cost-plus-award fee), 3. Time-and-Materials (T&M).
The Plan-Do-Check-Act (PDCA) cycle as the basis for quality improvement is usually attributed to:
Deming
A ______ is a collection of projects or programs grouped together for strategic business needs.
Portfolio
While managing a project, you decide to award a contract to an external enterprise. You enter into a contract where you pay the external enterprise a set amount (as defined by the contract), irrespective of the seller’s costs. What would best describe this type of contract?
Firm Fixed Price FFP
What are the outputs of the Plan Procurement Management process?
The procurement management plan, procurement statements of work, and make-or-buy decisions are three of the seven outputs of the Plan Procurements process.
A tool that provides a visual representation of human resource allocation to a project, number of working hours and availability on the project is a:
The correct response is Resource Histogram. This bar chart illustrates the number of hours that a project, department or project team will be working each week or month over the course of the project. The chart can include a horizontal line that represents the maximum number of hours available for a particular resource. Bars that extend beyond the maximum available hours indicate the need for a resource leveling strategy.
Four negative risk management strategies are:
Avoid, Transfer, Mitigate, and Accept.
What does it mean if the Earned Value is equal to Actual Cost?
CV = EV - AC. If the EV is equal to the AC, then there is no cost variance on the project.
You are the project manager managing a project to design a print head for dot matrix printers. In order to determine ideal settings for print quality, the quality manager of the company suggests trying out various scenarios for printing by varying certain parameters on the print head. Identifying variables which influence the product or process under development is called:
Design of Experiments
Cause and Effect diagrams are used to illustrate how various factors might be linked to potential problems or effects. They are also called:
Ishikawa Diagrams
What is the best way to make an accurate forecast of ETC?
Manual forecasting of costs of remaining work is generally the best means of generating an accurate forecast of ETC.
What is the difference between a histogram and a Pareto chart?
A Pareto chart is a type of histogram where the causes are ordered by frequency.
Most project management software packages use a method of constructing a project schedule network diagram known as:
Precedence Diagramming Method. PDM uses Nodes to represent Activities and connects the activities with Arrows to show dependencies. This is the method most commonly used by project management software packages.
When a negative unplanned risk occurs in a project, a response to it would be called:
A workaround
A management control point where scope, budget, actual cost and schedule are integrated and compared to earned value for performance measurement is called a:
This is a control account. Control accounts are placed at selected management points of the Work Breakdown Structure (WBS). Each control account may include one or more work packages, but each of the work packages must be associated with only one control account.
You are defining the schedule activities for your project and identifying deliverables at the lowest level in the Work Breakdown Structure (WBS). You find that there is insufficient definition of the project scope to decompose a branch of the WBS down to the work package level. You now look at using the last component in that branch of the WBS to develop a high-level project schedule for that component. Such a planning component is called:
The correct response is a planning package. Control accounts and planning packages are two planning components used when there are insufficient details of the project scope.
A Project manager estimates the work to be accomplished in the near term in detail at a low level of the Work Breakdown Structure (WBS). He estimates work far in the future as WBS components that are at a relatively high level of the WBS. What is this technique called?
Rolling wave planning. In Rolling Wave Planning, the work to be accomplished in the near term is estimated in detail at a low level of the Work Breakdown Structure (WBS), while the work far in the future is estimated as WBS components that are at a relatively high level of the WBS. The work to be performed within another one or two reporting periods in the near future is planned in detail during the current period.